(1) The governance, assurance and risk monitoring arrangements for WM5G Ltd be noted. (2) The ongoing governance, assurance and risk monitoring arrangements for WMCA’s other arm’s length companies - Midland Metro Ltd, West Midlands Growth Company, West Midlands Rail and West Midlands Development Capital Ltd - be noted.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
2.1To date, WMCA has had 4 Arm’s length companies which are active and have been in operation. Assurance has previously been provided to SLT and ARAC on their governance, risk and assurance arrangements. It was agreed at ARAC in January 2019 that a six monthly check in would be undertaken with each of these companies to confirm that the Director of Finance and the Head of Governance continue to be satisfied with the control processes that are in place to monitor their assurance arrangements and any potential risk exposure to WMCA.
2.2To confirm their arrangements, each Arm’s Length Company is required to complete an Arm’s Length Company Assurance Checklist. For commercial sensitivity purposes the completed checklists have not been shared publically with WMCA ARAC, however they have been shared with the ARAC Chair. Prior to submission, the Director of Finance and the Head of Governance have confirmed that they are satisfied with the arrangements that are in place and they provide sufficient controls for WMCA.
3. WM5G Assurance, Risk & Governance Arrangements
3.1The remit of WM5G is to accelerate the deployment of 5G digital technologies in the West Midlands. Funding of £21 million (£1 million of which has been provided during mobilisation) is initially available from DCMS to support delivery of the 5G project, subject to approval of aforementioned business plans. Regional partners including West Midlands Combined Authority, the region’s three LEPs or other local public bodies are required to enable £21 million match funding. Of this initial tranche of £21 million local funding, West Midlands Combined Authority is required to contribute £5.0 million, this will be funded through the Investment Programme and subject to the WMCA Assurance requirements/ appraisal.
3.2WM5G Limited is a Company Limited by Guarantee and a wholly-owned subsidiary of WMCA. Accordingly, WMCA has rights over WM5G Limited by way of the articles of association and member's agreement with WMCA. The aforementioned member's agreement sets out the reporting and reserved matters on WM5G. 3.3 WM5G Limited will be managed by its own Board of Directors. However, the member's agreement requires WM5G Limited to provide reports and the business plan to WMCA for review. Moreover, WMCA retains an element of control over WM5G Limited through reserved matters in the member's agreement.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Audit, Risk & Assurance Committee at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Business Continuity Programme Update(1) That a reduction in overall programme risk and that Business Continuity Resilience, Response and Recovery (BCRRR)...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.