WMCA Assurance Overview November 2019

Noted Finance 1 paper

Audit, Risk & Assurance Committee noted this item on Tuesday 12 November 2019. Below is the council's own wording, with the papers it was decided on.

Item188

Resolved

(1) The assurance reviews and activities that had been undertaken since the last reporting period be noted. (2) The committee were satisfied with the assurance activity from November 2018 to October 2019.
Word for word from the decision West Midlands Combined Authority published for this meeting. Source: governance.wmca.org.uk

Follow this further

Built from West Midlands Combined Authority's papers

What the report saysPro

Report to Audit, Risk & Assurance Committee

Background

2.1The intention of the report is to summarise the assurance activity since the last reporting period and highlight any matters that are of concern that require further consideration or additional assurance activity.

2.2Since the last update and as we move out of the transitional arrangements to WMCA, the Corporate Assurance team have continued to develop and refine appropriate assurance processes for the West Midlands Combined Authority. A brief summary of this activity is also provided in this report for note at this point in time.

Project & Programme Assurance

TfWM / Corporate Services Minor Project Assurance Summary

2.322 assurance reviews have taken place between November 2018 and October 2019 of minor projects. Each review is rated against criteria across 12 areas of focus (in line with industry standards of best practice) and given an overarching RAG rating.

2.4Of the 22 reviews conducted 13 were rated as green, 6 were rated amber and 3 were rated red. These projects have followed the WMCA Gated Project Management Lifecycle and a PMO (Programme Management Office) led compliance check referred to as a Tier 1 assessment and independent and objective assessment led by Programme Assurance referred to as a Tier 2 assessment.

2.5Following assessment by Programme Assurance, the team works with project stakeholders with the intention that recommendations are acted upon before the project seeks approval for progression at the relevant project governance forum. Whether recommendations are acted upon or not, the Independent Programme Assurance assessment accompanies the project output for visibility at decision making forums.

2.6Of these projects, there have been examples (such as Dudley Interchange) where the overall value is in excess of £5 million (upper threshold for classification of ‘minor’ projects) but they are not Investment Programme funded. This has presented challenges around the route to be taken for appraisal, assurance and approval activities. In these scenarios, key stakeholders including Programme Assurance have identified safe and appropriate routes forward to ensure the schemes continue to progress.

2.7Common themes and areas of improvement arising from these reviews are as follows: a. Plans and schedules are not effectively defined b. Objectives, project success / acceptance criteria and benefits are not adequately defined c. Project costs escalate and/or budget forecasts are underestimated d. As portfolios and respective programmes and projects mature, governance structures to manage and control change initiatives are evolving resulting at times in limited controls being place to effectively monitor and manage projects

WMCA Investment Programme Major Project Assurance Summary

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
WMCA Assurance Overview November 2019Report 181 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 24 attended
DL
David LaneChair, present
RL
Councillor Ram LakhaVice-Chair, present
AB
Councillor Ahmad BostanCommittee Member, present
AB
Councillor Alan ButtCommittee Member, present
SF
Sean FarnellCommittee Member, present
MG
Councillor Michael GoughCommittee Member, present
FG
Councillor Fred GrindrodCommittee Member, apologies, sent representative
AL
Councillor Andrea LaytonCommittee Member, expected
AP
Councillor Alexander PhillipsCommittee Member, apologies
JT
Councillor June TandyCommittee Member, expected
DT
Councillor David ThainCommittee Member, expected
VW
Councillor Vera WatersCommittee Member, present

All 24 on the meeting page

On this subject at West Midlands Combined Authority

Search all
  1. WMCA Assurance Overview November 2019This decision
  2. WMCA Assurance Overview September 2020Noted
  3. WMCA Assurance Report - Arm's Length CompaniesNoted
  4. WMCA Cost AssuranceNoted
  5. WMCA Assurance Overview September 2017Noted

More from West Midlands Combined Authority Audit, Risk & Assurance Committee

All decisions
MeetingDecisionOutcome
14 Jul 2026 Terms of Reference - To NoteResolved that: The Terms of Reference be noted. Noted Open
14 Jul 2026 West Midlands Combined Authority (WMCA) Financial Monitoring Outturn 2025/26Resolved that: The update be noted. Noted Open
14 Jul 2026 Annual Review Letter 2025/26Resolved that: The Local Government and Social Care Ombudsman’s annual review letter for 2025/26 be noted. Noted Open
14 Jul 2026 Business Continuity Programme Update(1) That a reduction in overall programme risk and that Business Continuity Resilience, Response and Recovery (BCRRR)... Noted Open
14 Jul 2026 Consideration of Private Internal Audit Reports(1) The contents of the latest Internal Audit Update Report and progress against delivery of the 2025/26 Internal Aud... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies