That the year to date net revenue expenditure for 2017/ 18 shows a favourable variance of £3.8m compared to budget and a full year forecast variance of £5.7m following the second re-forecast of the year be noted; 2. That the total capital expenditure to the end of November 2017 within the overall transport programme was broadly in line with budget, showing a 4 % variance (£1.4m) be noted and 3. That the treasury indicators are within the expected range and there are no issues to highlight be noted.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
Accountable Director Sean Pearce Director of Finance Tel 0121 214 7936 Email - [email removed] Accountable employee(s) Linda Horne, Head of Finance & Business Planning Tel 0121 214 7508 Email [email removed] Report to be/has been Cllr Worrall (Lead Member- Finance and Performance considered by Monitoring)
Recommendation(s) for action or decision:
The Transport Delivery Committee is recommended to:
1. Note that the year to date net revenue expenditure for 2017/18 shows a favourable variance of £3.8m compared to budget and a full year forecast favourable variance of £5.7m following the second re-forecast of the year.
2. Note that total capital expenditure to the end of November 2017 within the overall transport programme was broadly in line with budget, showing a 4% variance (£1.4m)
3. Note that the treasury indicators are within expected range and there are no issues to highlight.
Page 1 of 11 [NOT PROTECTIVELY MARKED]
1.0Purpose
1.1This report sets out the financial position as at 30 November 2017 and is the fourth monitoring report for the 2017/18 financial year. The content relates to the financial position of the Combined Authority’s Transport Delivery Revenue and Capital Budgets. The report consists of the following Sections:
Section A Summary TFWM Revenue Budget
Section B Summary TFWM Capital Budget
Section C Treasury Management Indicators
SECTION A
2.0Summary Revenue Position
2.1As at the end of November 2017 there is a net favourable variance against budget of £3.8m. Following the second re-forecast of the year there is a favourable full year position of £5.7m against budget. This is a favourable movement of £3.8m from the first forecast undertaken in July and reflects in the main Combined Authority approved change to the Capital finance policy in November.
2.2Year to Date and Full Year Variances:
The following are a summary of the main movements within the categories of spend set out in the table following paragraph 2.3.
Concessions:
The favourable variances of £570,000 year to date and forecast £1.011m full year are as previously reported mainly as a result of savings on the national bus concession scheme owing to lower patronage, and the release of a provision within the Child and Rail Concessions budget for fare and patronage increases that are no longer required.
Bus Services:
The adverse year to date variance of £160,000 and anticipated full year adverse position of £276,000 are due to a number of infrastructure cost pressures as a result of increased maintenance requirements seen in-year and projected for the remainder of the year in relation to Bus Stations and on-street infrastructure.
Rail and Metro services:
The adverse year to date variances of £342,000 and projected adverse full year position of £670,000 are largely due to the previously reported provision set aside within Metro Operations for Midland Metro Limited mobilisation. The Bromsgrove Rail Station favourable movement is due to greater grant income from the Department for Transport in relation to the long term fixed charge that partly funds the investment in the new station.
Page 2 of 11 [NOT PROTECTIVELY MARKED]
Integration:
The favourable year to date and full year variances of £44,000 and £115,000 respectively mainly relate to one-off additional ticketing commission income.
Business Support Costs:
The favourable year to date and full year variances of £280,000 and £297,000 respectively are as previously reported primarily as a result of savings within staff costs due to restructures that were implemented at the start of the year and some vacant posts as well as higher than budgeted investment income due to more favourable cash balances.
Finance Costs:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Transport Delivery Committee at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.