Transport Delivery Committee
Date 8th January 2018
Report title Investment Programme
Accountable Director Laura Shoaf, Managing Director Transport for West Midlands Accountable Phil Hewitt, Metro Programme Director Employee Email: [email removed] Tel: 0121 214 7254 Councillor Roger Horton – Lead Member Rail and Metro Report to be/has been considered by
Recommendation(s) for action or decision:
The Transport Delivery Committee is recommended to note the report:
1.0Purpose
1.1To report on matters relating to the Metro Investment Programme in the West Midlands.
Metro Investment Programme Overview – December 2017 Since the last update in September progress has continued to be been made in most areas of the Metro Programme in line with expectations. This note provides a brief overview of the main activities of the Metro team and the actions being taken to manage the principal risk / issues and opportunities that have arisen.
2.0Birmingham City Centre Extension. 2.1 The access between St Chad’s tramstop and Queensway has now opened to the public. A review of the tramstop environment has highlighted the need for improved passenger information (wayfinding signage, local area and service information, real time display etc) and the Metro operations marketing team have produced a series of recommendations for enhancing the platform and ground level environments. These will be reviewed against available residual BCCE budgets.
2.1National Express have installed additional pedestrian deterrent measures at the north end of the St Chads platform. A review is being carried out into accessibility of the bridge parapets from public areas and proposed measures to reduce this risk are being developed.
2.2Following completion of the majority of outstanding works and agreement with Balfour Beatty over the timing of the remedial works to the St Chads switches a practical completion certificate has now been issued and Balfour Beatty’s defect correction period (12 months) has commenced.
2.3Handback of the highway to Birmingham City Council is being progressed however the failure by Amey to deal with documentation continues to impact on our ability to formally return the highway to BCC maintenance with the risk that TfWM will be left with highway liabilities. BCC are working with us to aim to resolve this issue and ensure that the highway is transferred as soon as possible.
3.0Catenary Free Trams 3.1 Tram 18 successfully completed its factory testing in Zaragoza and was returned to Wednesbury in September. Site acceptance tests are progressing to schedule in accordance with the project Safety Verification Plan. Once Safety Verification has been completed an application will be made to the Secretary of State for Transport in January 2018 for authority to run the modified tram in passenger service in accordance with the provisions of the Midland Metro Act 1989.
3.2A review is under way with CAF and National Express of the fleet modification programme to ensure that this will ensure all trams are modified ahead of the opening of the Centenary Square and Wolverhampton extensions (earliest date Q3 2019) whilst minimising the risk of disruption to passenger services. An extended programme may be implemented that will meet both objectives within the overall Catenary Free project budget.
3.3The necessary modifications to Wednesbury depot to accommodate the revised tram configuration and to allow for safe discharge of the overhead line and batteries prior to works being undertaken on the vehicles have been substantially completed with snagging
Metro Investment Programme Overview – December 2017 and modifications to the interlocking of the electrical discharge / vehicle access systems awaiting implementation.
Tram unloading at Wednesbury following traction battery fitting 18 –
4.0Bilston Road Project Cost Construction Start Completion £16m 12 June 2017 1st December 2017
Powers: Midland Metro Act 1989 Funding Funded through HS2 Connectivity Debt £650k contribution from City of Wolverhampton
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Metro Investment ProgrammeReport | 8.2 MB | DownloadRead as text |
Follow Transport Delivery Committee at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 6 Feb 2023 | Apologies for AbsenceCouncillor Bill Gavan (Sandwell), Councillor Anne Millward (Dudley), Councillor Clare Simm (Wolverhampton) and Counci... | Decided | Open |
| 6 Feb 2023 | Chair's RemarksThe Chair noted the recent death of William Whiting, Chair of the Stourbridge Line Users Group and former Chair of We... | Noted | Open |
| 6 Feb 2023 | Minutes - 9 January 2023Agreed as a correct record. | Agreed | Open |
| 6 Feb 2023 | Matters ArisingThe committee noted matters arising from the minutes. | Noted | Open |
| 6 Feb 2023 | Forward PlanA plan of items to be reported to future meetings was noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.