(1) That the achievements since the November 2017 meeting of the Transport Delivery Committee be noted; (2) That the progress of deliverables under the 2017/18 Capital Programme be noted and (3) That there are no variations from the baseline programme in this reporting period be noted.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
2.1The 2017/2018 Capital Programme was approved by WMCA Board as part of the wider Transport Plan on 17th March 2017.
2.2The ITB allocation for 2017/2018 is fully utilised on continuing committed schemes and in attempting to manage the existing asset base with respect to replacement and or renewal of life expired/obsolete equipment, in order to endeavour to maintain a steady state of asset condition across the estate.
2.3The Capital Programme in 2017/2018 will be a one year transition period by bringing existing schemes to a conclusion and will allow TfWM to re-focus subsequent programmes towards supporting Asset Management, Network Resilience and Capacity Enhancement projects from April 2018, or sooner should funding become available.
2.4Attached to this report (Appendix 1) is the detailed monitoring report for the 2017/2018 TfWM Capital programme outlining these deliverables, indicating the baseline date (endorsed through March report) with an indication of the current forecast date with a RAG indicator.
3.0Achievements
3.1The following elements within the 2017/18 Capital Programme have been completed during October November 2017:
WMCA have been successful in withdrawing from the Asset Management contract and a full refund on costs has been reached. TfWM are currently in testing phase following talks with bus operators (Rotala, Arriva, Stagecoach Banga Buses and First Worcester) to deliver RTI information to units on street. Interconnect study to understand mapping requirements for wayfinding in Dudley is now completed. Outdated cycle lockers at Widney Manor have been replaced with new 2 tier shelters.
4.0Variations to Baseline Programme
4.1There are no variations to the baseline programme in this reporting period.
Financial implications
Page 2 of 8 Version 0.3 [PUBLIC]
5.1The detailed financial aspects of the TfWM 2017/2018 Capital Programme are reported separately under the Financial Monitoring Report to this Committee. A summary of the final year position in financial terms is, however, attached to this report as Appendix 2.
Legal implications
6.1There are no direct legal implications arising from the recommendations set out in this report. However, legal and procurement will support, as necessary, any deliverables that may arise moving forward into 2017/2018.
Equalities implications
7.1There are no equality implications arising from the recommendations set out in this report. However, Anna Sirmoglou will support as project requires any deliverables within the 2017/2018 capital programme.
8.0Schedule of background papers
8.12017/2018 TfWM Capital Programme Delivery Monitoring Report read at Transport Delivery Committee 4 September 2017 from Sandeep Shingadia, Head of Programme Development, TfWM.
Appendices
APPENDIX 1 – Progress of Deliverables against 2017/18 Baseline Programme APPENDIX 2 – Capital Programme and Financial Summary
10.0Glossary of Terms
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Transport Delivery Committee at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.