Resolved
That the report be noted.
Transport Delivery Committee noted this item on Monday 10 September 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be noted.
2.1The Midland Metro investment programme has continued to make progress during the 3 months since the last update. This note provides an overview of the main activities of the West Midlands Metro team (comprising TfWM and the Midland Metro Alliance) and the actions being taken to manage the principal risks / issues and opportunities that have arisen.
1 2.2 Current funding secured for the Metro Investment Programme is [£665m] with additional funding required of up to £1,000m to complete the full programme by 2026. TfWM is currently completing a review of the programme costs and funding in order to confirm the extent of the expanded network that can be delivered within the existing funding envelope ahead of confirmation during 2018/9 of the planned mechanism for funding the full network.
Birmingham City Centre Extension In this period there have been no further incidents to report on the completed scheme. Minor defects have been raised formally with the Contractor and a schedule has been provided identifying the timescales for rectification. The defects correction period ends 1st September 2018, pending satisfactory completion of the defects retention monies will then be released.
Ongoing design work continues to mitigate vehicle incursions on the Snow hill Grass Track. Trial holes have been completed and the design is nearing completion for a “tank trap” style system. This work is scheduled for construction and completion around August.
Further design work is being undertaken for issues at Stephenson Place to control as far as reasonably practicable the pedestrian entrapment issue that has been previously identified. A joint workshop has been undertaken with representatives from BCC Highways and Planning departments to identify the possible and acceptable solutions. Works will be completed around the autumn after approval.
Handback of the highway to Birmingham City Council is being progressed with BCC. To date, discussions have focused on TfWM maintaining the highway around the Metro infrastructure with workshops scheduled to identify liabilities and obligations.
Catenary Free Trams The first retrofitted CAT Free Tram (Tram 18) went back into passenger service on 20th April 2018 following investigations which closed out a minor irregularity on one of the commissioning tests. The tram runs between Soho, Benson Road and Handsworth, Booth Street on existing Line One using battery power to ensure that the system is in use during the warranty period. This will remain the case until the future permanent CAT Free sections are tested and commissioned into the expanded operational network as part of Centenary Square Extension, the extension to Wolverhampton Station and Birmingham Eastside The retrofit roll out of the complete 21 tram fleet continues at Wednesday depot and requires 2 trams to be removed from passenger service at one time. The 2nd tram due to complete endurance testing and enter passenger service during June 2018. The 3rd tram is has been retrofitted and is currently being tested.
2 Picture: Tram 18 running on battery power with pantograph retracted on Soho, Benson Road
3 Bilston Road Bilston Rd Project Cost Construction Start Completion £16m 12 June 2017 1st December 2017
Powers Midland Metro Act 1989 Funding Funded through HS2 Connectivity Debt £650k contribution from City of Wolverhampton
Programme Completed [2 Weeks Early] Cost On Budget
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Metro Investment ProgrammeReport | 15 MB | DownloadRead as text |
Follow Transport Delivery Committee at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 6 Feb 2023 | Apologies for AbsenceCouncillor Bill Gavan (Sandwell), Councillor Anne Millward (Dudley), Councillor Clare Simm (Wolverhampton) and Counci... | Decided | Open |
| 6 Feb 2023 | Chair's RemarksThe Chair noted the recent death of William Whiting, Chair of the Stourbridge Line Users Group and former Chair of We... | Noted | Open |
| 6 Feb 2023 | Minutes - 9 January 2023Agreed as a correct record. | Agreed | Open |
| 6 Feb 2023 | Matters ArisingThe committee noted matters arising from the minutes. | Noted | Open |
| 6 Feb 2023 | Forward PlanA plan of items to be reported to future meetings was noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.