Resolved
That the contents of the report be noted.
Transport Delivery Committee noted this item on Monday 4 February 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
That the contents of the report be noted.
2.1The Midland Metro investment programme has continued to make progress during the 3 months since the last update. This note provides an overview of the main activities of the West Midlands Metro team (comprising TfWM, Midland Metro Limited and the Midland Metro Alliance) and the actions being taken to manage the principal risks / issues and opportunities that have arisen.
1 2.2 TfWM is currently making good progress in developing the funding and finance strategy that will allow the Metro expansion to be delivered in full, in two tranches by 2023 and by 2026.
2.3The following is a summary of the principal highlights of the Programme
2.3.1 Westside Extension – Centenary Square. Despite additional works arising from the diversion of a district heating main and repairs to the A38 tunnel roof works are progressing well in all sections and the project remains on schedule to open in December 2019 2.3.2 Westside Extension – Edgbaston. Enabling works have commenced to strengthen the Broad Street canal bridge and arrangements are in hand to commence the main tramway construction works on 23 April. The project remains on schedule to open in December 2021 2.3.3 Wolverhampton Extension: Construction of stages 2 and 3 has progressed well and the track laying has been completed. Urban realm works are progressing ahead of the planned demobilisation of the worksite pending completion of the Wolverhampton Station forecourt works. Opening of this extension is dependent upon the completion of the station enhancement project. 2.3.4 Wednesbury Brierley Hill: Works are progressing to finalise the business case and secure the full funding package to allow the scheme to be delivered by 2023. MMA are finalising the Target Cost 1 project proposal and are now undertaking a Value Engineering exercise. The Inquiry into the Transport and Works Order Application will take place from 19 March. 2.3.5 Birmingham Eastside: MMA are finalising the Target Cost 1 proposal and discussions are continuing with HS2 and DfT around the potential construction interfaces between the Metro and Curzon Street station works. Approval of the Final Business Case and commencement of the works is on hold pending award of the Transport & Works Act Order granting WMCA statutory powers to progress the scheme. 2.3.6 East Birmingham Solihull: The submission of the Outline Business Case and application for powers has been deferred to 2020 to allow for further scheme refinement, assessment of the impacts and benefits of the proposal, definition of the overall funding strategy and to allow time for a thorough consultation on the proposal to be undertaken in the second half of 2019. The project remains on schedule to open in 2026. 2.3.7 3rd Generation Trams: 7 submissions were received in response to the Supplier Questionnaire. An invitation to negotiate is planned to be issued in Quarter 1 2019 with award of contract planned for Q3 2019.
2 3. Financial Implications
All financial information is contained within the report.
No legal implications are identified for this current report, however any further details reported back after this report require legal consideration.
None.
6. Inclusive Growth Implications
These are addressed in formal submissions relating to each project.
7. Geographical Area of Report’s Implications
The Metro Programme report encompasses Programmes and Projects works in Wolverhampton, Sandwell, Dudley, Birmingham, Solihull and Coventry.
8. Other Implications
None.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Metro Investment Programme BriefingReport | 11 MB | DownloadRead as text |
Follow Transport Delivery Committee at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 6 Feb 2023 | Apologies for AbsenceCouncillor Bill Gavan (Sandwell), Councillor Anne Millward (Dudley), Councillor Clare Simm (Wolverhampton) and Counci... | Decided | Open |
| 6 Feb 2023 | Chair's RemarksThe Chair noted the recent death of William Whiting, Chair of the Stourbridge Line Users Group and former Chair of We... | Noted | Open |
| 6 Feb 2023 | Minutes - 9 January 2023Agreed as a correct record. | Agreed | Open |
| 6 Feb 2023 | Matters ArisingThe committee noted matters arising from the minutes. | Noted | Open |
| 6 Feb 2023 | Forward PlanA plan of items to be reported to future meetings was noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.