New Stations Package 1 - Full Business Case

Agreed Committee 1 paper

WMCA Board agreed this item on Friday 15 January 2021. Below is the council's own wording, with the papers it was decided on.

Item12

Resolved

(1) The Full Business Case for new stations Package 1 (Darlaston and Willenhall stations) was authorised. (2) A total project budget of £55.84m based on the Estimate at Completion for the scheme at Full Business Case stage was agreed, subject to the WMCA securing the funding for the project. (3) The release of £6m from the WMCA Investment Programme was authorised, subject to Department for Transport approval of sufficient Rail Network Enhancement Pipeline funding being made available. (4) It was noted that the WMCA intended to be the accountable body for the entirety of the funding package. (5) It was noted that the costs included within the Full Business Case were the current best estimates prior to the completion of single option development (GRIP 4). (6) The BCR of 6.5, representing very high value for money for the scheme, was noted, and the continued very high value for money for the scheme even taking into account the Department for Transport’s COVID-19 long-term impact scenario, leading to a BCR of 4.7 in a reasonable worst case scenario, was noted. (7) The aim of securing funding in Quarter 1 2021 to enable the project to proceed as per stated timescales was noted. (8) The WMCA Monitoring Officer and WMCA Director of Finance were jointly authorised to award contracts to the successful tenderer for the design and build stage, subject to: (i) The project being within the £55.84m recommended budget; (ii) Adequate funding being secured to allow for the delivery of the new stations; (iii) All funding agreements being signed and sealed to the satisfaction of the WMCA Director of Director and the WMCA Monitoring Officer; (iv) The operating costs of the stations being fully quantified and affordable. (9) Delegations to the WMCA Monitoring Officer and WMCA Director of Finance to enter into the various funding agreements and contracts which would be reasonably required to enable delivery of the new stations, including (if necessary) the issuing of a Letter of Intent to ensure the project schedule was maintained whilst funding agreements were being finalised, subject to the risks of doing so being acceptable to the WMCA Section 151 Officer and the WMCA Monitoring Officer, were approved.
Word for word from the decision West Midlands Combined Authority published for this meeting. Source: governance.wmca.org.uk

Follow this further

Built from West Midlands Combined Authority's papers

What the report saysPro

Report to WMCA Board

Background

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
New Stations Package 1: Full Business CaseReport 2.4 MB DownloadRead as text

At this meeting

Whole meeting
1Apologies for AbsenceDecided 4Minutes - 13 November 2020Agreed 5Forward PlanNoted 6Financial Monitoring Report 2020/21Noted 7WMCA Draft Budget 2021/22Noted 8Black Country Land & Property Investment Fund - Programme Update and Reprofile ApprovalNoted 9West Midlands Digital RoadmapAgreed 10Young Combined Authority Vision and Priorities for the West MidlandsNoted 11Recovery Co-ordination Group Community Recovery Roadmap and ProspectusNoted
12New Stations Package 1 - Full Business CaseThis decision
13New Stations Package 2 - Full Business CaseAgreed 14Perry Barr Railway Station and Bus Interchange - Full Business CaseApproved 15Midland Metro Buy Before BoardingNoted 16Midland Metro ByelawsNoted 17Midland Metro Penalty FareNoted 18Audit, Risk & Assurance Committee - 26 October 2020Noted 19Investment Board - 9 November 2020Noted 20Transport Delivery Committee - 9 November 2020Noted 21Strategic Economic Delivery Board - 19 November 2020Noted 22Overview & Scrutiny Committee - 23 November 2020Noted 23Environment & Energy Board - 9 December 2020Noted 24Overview & Scrutiny Committee - 11 December 2020Noted 25Investment Board - 14 December 2020Noted 26Skills Advisory Board - 14 December 2020Noted 27Transport Delivery Committee - 14 December 2020Noted 28Public Service Reform Board - 14 December 2020Noted 29Exclusion of the Public and PressDecided 32Ring & Ride Customer Contact TransformationPrivate 33The Marches Help to Own (H2O) Project, WolverhamptonPrivate 34Date of Next MeetingDecided

Who was there

0 of 32 attended
AS
Andy StreetChair, expected
BS
Councillor Bob SleighVice-Chair, expected
NA
Nick AbellNon-Constituent Member, expected
GA
Councillor George AdamsonNon-Constituent Member, expected
AA
Councillor Adrian AndrewCommittee Member, expected
MB
Councillor Mike BirdCommittee Member, expected
IB
Councillor Ian BrookfieldCommittee Member, expected
IC
Councillor Ian CourtsCommittee Member, expected
MC
Councillor Maria CromptonCommittee Member, expected
SD
Councillor Shaun DaviesNon-Constituent Member, expected
AD
Councillor Andrew DayObserver Member Awaiting Membership, expected
MD
Councillor Matthew DormerNon-Constituent Member, expected

All 32 on the meeting page

On this subject at West Midlands Combined Authority

Search all
  1. New Stations Package 1 - Full Business CaseThis decision
  2. New Stations Package 1: Project Costs UpdateNoted
  3. New Stations Package 1: Project UpdateNoted
  4. New Stations Package 2 - Full Business CaseAgreed

More from West Midlands Combined Authority WMCA Board

All decisions
MeetingDecisionOutcome
17 Jul 2026 Apologies for AbsenceCecilie Booth (Audit, Risk & Assurance Committee), Councillor Paul Bradley (Dudley), Councillor George Duggins (Coven... Decided Open
17 Jul 2026 Chair's RemarksThe Chair provided a summary of the recent delivery and activity that he had been involved in. Decided Open
17 Jul 2026 Minutes - 12 June 2026Agreed as a correct record. Agreed Open
17 Jul 2026 Constitution Review(1) The proposed amendments to parts A and B of the constitution, as amended, were approved. (2) Authority was delega... Approved Open
17 Jul 2026 Rosewell Review Phase 2 / Transport for City Regions(1) The work undertaken as part of phase 2 of the Rosewell Review, including its proposals regarding how the Transpor... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies