(1) The cost pressures associated with the New Stations Package 1 project were noted. (2) The proposed funding solution to extend the over programming of the City Region Sustainable Transport Settlement 1 was approved. (3) The Section 151 Officer was given the delegated authority to amend the project budget by up to £15.43m, subject to satisfactory assurances being received by the Executive Director for Transport for West Midlands with respect to the anticipated final cost.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
Report title New Stations Package 1: Project Cost Update
Portfolio Lead Transport - Councillor Mike Bird
Accountable Chief Laura Shoaf, West Midlands Combined Authority Executive email: [email removed]
Accountable Anne Shaw, Executive Director for Transport for Employee West Midlands email: [email removed]
Report has been WMCA Executive Board – 8 November 2023 considered by Mayor and Portfolio Leaders Liaison Committee
Recommendation(s) for action or decision:
The WMCA Board is recommended to:
(1) Note the cost pressures associated with the New Stations Package 1 project.
(2) Approve the proposed funding solution to extend the over programming of CRSTS1.
(3) Delegate to the WMCA Section 151 Officer the ability to amend the project budget by up to £15.43m subject to satisfactory assurances being received by the Executive Director for Transport with respect to the anticipated final cost.
1. Purpose
1.1To update the Board on the cost and programme implications of the novation of the West Midlands Rail Programme (New Stations Package 1 Project) to Kier Integrated Services Limited, following the administration of Buckingham Group Contracting Limited in September 2023 due to financial insolvency. 2. Update
2.1A New Stations Package 1 Project Update paper was noted by the Board on 13th October 2023. This provided details of the decision to novate the New Stations Package 1 Project to Kier Integrated Services Limited (“Kier”), following the placing into administration of Buckingham Group Contracting Limited (BGCL).
2.2Following rigorous review, it was determined that novating the contract to Kier would minimise disruption to the programme, maintain the current integrated delivery strategy, and retain many of the same resources. It also protected WMCA from negotiations from the administrators on the BGCL account.
2.3Although novating the contract from BGCL to Kier was deemed more cost effective and allowed for more efficient delivery than re-procuring the works, the following outstanding issues remain:
• Impact to the overall project schedule as a result of a revised contractual delivery programme agreed with Kier. • A revised Target Cost for the contract with Kier, negotiated as part of the novation agreement, with cost increases arising from project downtime and re- mobilisation costs, and incorporating scope changes. • The residual cost risk to the project associated with the extent of land remediation.
2.4The schedule impact of the administration of BGCL and novation to Kier means that the new stations are likely to be operational in winter 2025 / 2026. This is currently subject to a full assurance exercise however this forecast date is based on an initial contractual programme submission from Kier. Programme mitigations are under investigation to understand how this date can be bettered.
2.5WMCA Board were notified in June 2023 through the transport capital pressure paper of a cost pressure on the project. This has primarily been driven by extensive land remediation requirements and changes to industry requirements for fire safety. The approach to land remediation previously agreed with Network Rail has been reopened with additional remediation works mandated. The fire strategy, also previously agreed, has had to be amended following changes to national standards leading to the requirement for additional infrastructure to provide a secondary means of escape.
2.6The CRSTS Rebase approved by WMCA Board in September 2023 included the proposal to meet the cost challenge through that exercise and ultimately the over programming of the CRSTS fund. This gave a locally approved revised budget for this scheme of £69.84m.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.