West Midlands Combined Authority
WMCA Board, Friday 13 October 2023 at 11.00am

New Stations Package 1: Project Update

Noted Committee 1 paper

WMCA Board noted this item on Friday 13 October 2023. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

(1) The insolvency and administration proceedings of the principal contractor for the New Stations Package 1 project, Buckingham Group Contracting Ltd, was noted. (2) The decision made at West Midlands Rail Partnership Board on 28 September 2023 to novate the Package 1 main works contract to Kier Integrated Services Ltd was noted. (3) The work underway to re-assess affordability and funding was noted, and the options be bought back for consideration to a future meeting of the board. (4) It was noted that in the interim period, only work associated with scheme costs that would remain in scope and within the existing budget would continue to be incurred until a resolution to the overall scheme affordability had been reported to, and agreed by, this board. (5) The board’s continued commitment to complete Package 1 in full and as a single, fully funded programme of work, was noted.
Word for word from the decision West Midlands Combined Authority published for this meeting. Source: governance.wmca.org.uk

Follow this further

Built from West Midlands Combined Authority's papers

What the report saysPro

Report to WMCA Board

WMCA Board Date 13 October 2023

Report title New Stations Package 1: Project Update

Portfolio Lead Transport - Councillor Mike Bird

Accountable Chief Laura Shoaf, West Midlands Combined Authority Executive email: [email removed]

Accountable Anne Shaw, Executive Director for Transport for Employee West Midlands email: [email removed]

Report has been N/A considered by

Recommendation(s) for action or decision:

The WMCA Board is recommended to:

(1) Note the insolvency and administration proceedings of the principal contractor for the New Stations Package 1 project, Buckingham Group Contracting Limited.

(2) Note the decision made at WMRP Board on 28th September 2023 to novate the Package 1 main works contract to Kier Integrated Services Limited.

(3) Note the work underway to re-assess affordability and funding, and the options to be bought back for consideration to a future board.

(4) Note in the interim period, only work associated with scheme costs that will remain in scope and within the existing budget will continue to be incurred until a resolution to the overall scheme affordability has been reported to and agreed by board.

1. Purpose

1.1To update the WMCA Board on the impact on the West Midlands Rail Programme (New Stations Package 1 Project), following Buckingham Group Contracting Limited (BGCL) being placed into administration on 4th September 2023, and the subsequent decision to novate BGCL’s contract to Kier Integrated Services Limited. 2. Update

2.1The CRSTS rebase paper approved by WMCA Board on 15th September flagged an early warning in relation to New Stations Package 1 and indicated an update would be bought back to Board at a later date. Buckingham Group Contracting Limited (BGCL) was the principal contractor on the New Stations Package 1 project, to build new rail stations at Willenhall and Darlaston.

2.2BGCL was placed into administration on 4th September 2023. The rail programme team assessed the options available, seeking the best solution for the West Midlands Combined Authority. The key options reviewed were:

1. Whether to novate the existing contract from BGCL to Kier Integrated Services Limited, or 2. Terminate the contract and explore an alternative delivery route.

2.3The risks and opportunities associated with both options were assessed, and novation was considered to be more cost effective and allow for earlier delivery. Novating the contract to Kier provides opportunities to minimise disruption to the programme, maintain the current integrated delivery strategy, and retain the same resources. It also protects WMCA from negotiations from the administrators on the BGCL account.

2.4Terminating and re-procuring had the opportunity to provide greater surety of costs, but was assessed and considered likely to be a more expensive, slower, more piecemeal, and less integrated delivery solution. Re-procurement would have likely taken the form of proceeding with a design contract directly awarded to maintain progress, a separate land remediation contract, followed by a station construction contract. This would have allowed cost assessment at each stage of the works but was anticipated to prolong the programme and introduce uncertainty as cost would be dependent on the market appetite and conditions.

2.5The options were presented to WMCA Executive Director of Transport in consultation with WMCA Statutory Officers who endorsed the novation of the contract from BGCL to Kier.

2.6Although the novation is the more cost and programme efficient delivery method, there will be an impact on cost and schedule. The immediate project works to be undertaken by Kier remain within budget and the Deed of Novation has been drafted to provide flexibility for an affordable project.

3. Strategic Aims and Objectives

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
New Stations Package 1: Project UpdateReport 168 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

16 of 29 attended
AS
Andy StreetChair, present
BS
Councillor Bob SleighVice-Chair, apologies
AA
Councillor Adrian AndrewCommittee Member, present
MB
Councillor Mike BirdCommittee Member, apologies
PB
Councillor Paul BradleyCommittee Member, present
KC
Councillor Kerrie CarmichaelCommittee Member, present
JC
Councillor John CottonCommittee Member, present
IC
Councillor Ian CourtsCommittee Member, present
SD
Councillor Shaun DaviesNon-Constituent Member, absent
ID
Councillor Ian DavisonObserver Member Awaiting Membership, apologies
MD
Councillor Matthew DormerNon-Constituent Member, present
GD
Councillor George DugginsCommittee Member, present

All 29 on the meeting page

On this subject at West Midlands Combined Authority

Search all
  1. New Stations Package 1: Project UpdateThis decision
  2. New Stations Package 1: Project Costs UpdateNoted
  3. New Stations Package 1 - Full Business CaseAgreed
  4. New Stations Package 2 - Full Business CaseAgreed

More from West Midlands Combined Authority WMCA Board

All decisions
MeetingDecisionOutcome
17 Jul 2026 Apologies for AbsenceCecilie Booth (Audit, Risk & Assurance Committee), Councillor Paul Bradley (Dudley), Councillor George Duggins (Coven... Decided Open
17 Jul 2026 Chair's RemarksThe Chair provided a summary of the recent delivery and activity that he had been involved in. Decided Open
17 Jul 2026 Minutes - 12 June 2026Agreed as a correct record. Agreed Open
17 Jul 2026 Constitution Review(1) The proposed amendments to parts A and B of the constitution, as amended, were approved. (2) Authority was delega... Approved Open
17 Jul 2026 Rosewell Review Phase 2 / Transport for City Regions(1) The work undertaken as part of phase 2 of the Rosewell Review, including its proposals regarding how the Transpor... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies