Change Request Skills Programme Business Case

Approved Committee 2 papers

Investment Board approved this item on Monday 19 June 2023. Below is the council's own wording, with the papers it was decided on.

Item14

Resolved

A change request to the Skills Programme Business Case (PBC), subject to approval of the CWG LEF – Jobs and Skills Business Justification Case (BJC), in order to receive additional funding for employment and skills activity awarded as part of the Commonwealth Games Legacy Enhancement Fund (CWGLEF) be approved and 2. Delegated authority for the development and onward issuing of the LA Grant Funding Agreements to the Director of Employment and Skills in consultation with the WMCA S. 151 Executive Director and Director of Law and Governance be agreed.
Word for word from the decision West Midlands Combined Authority published for this meeting. Source: governance.wmca.org.uk

Follow this further

Built from West Midlands Combined Authority's papers

What the report saysPro

Report to Investment Board

CHANGE REQUEST FORM V3.0

Change Request Form

WHAT CONSTITUTES A WMCA CHANGE REQUEST?

Change Control is the process through which all requests to change the approved baseline of a project, programme or portfolio are captured, evaluated, and then approved, rejected or deferred. This Change Request Form is required when the tolerances that were set out in the approved Business Case are or will be breached. These include changes to Time, Cost and Scope.

The Change Control Process should be initiated by the Project Team in the following circumstances:

 There is a cost implication that cannot be managed within the existing contingency budget and results in the requirement of 10% or more of the originally approved budget  There is movement of over 10% of total project/programme timings (measured in months) which impacts key milestones, the project start/end date and any associated dependencies  The scope of the project/programme has changed and the outputs, outcomes and benefits which were approved have been impacted (if an output is to be changed, this is also known as a material change)

CHANGE REQUEST FORM GUIDANCE

 Text shown in grey is to be used as guidance in the writing of this form, it should be deleted prior to submission.  Parts 1, 2 and 3 should be completed by the Applicant / Project Team  Part 4 should be completed by the Programme Assurance and Appraisal Team / Finance Business Partner  Please refer to the original WMCA approved Business Case when detailing any variance within this form  Requested appendices will be shown in orange to support this form, these are to be attached with the submission  If a partial or full Business Case re-write is required, you will be informed by WMCA

For further information regarding the Change Request Process or to submit this form for review, please contact [email removed] SINGLE ASSURANCE FRAMEWORK

1 CHANGE REQUEST DETAIL

CHANGE SUMMARY Project Name: Commonwealth Games Legacy Fund – Jobs and Skills & Mental Health Commission Programme Name (if applicable) Skills Programme Business Case Directorate (if WMCA internal): Economy, Skills and Communities Organisation (if WMCA external): WMCA This Change Request is seeking £5.75m additional WMCA funding of: This Change Request is seeking a n/a time extension of: This Change Request is seeking To increase the Skills PBC funding allocation to the following change to the scope: enable receipt of the CWG Legacy Funding. Enabling the skills team to expand the employment and skills offer to residents on programmes that are critical to securing good outcomes for residents but are currently either outside current funded programmes or will significantly enhance and boost the current offer as set out in the Skills PBC.

STAKEHOLDER INVOLVEMENT Provide the names of the following stakeholders who have been sighted on this change request prior to submission, note this is a mandatory requirement: Governance: n/a Senior Responsible Owner (SRO): Clare Hatton Programme SRO (if applicable) WMCA Executive Director: Julie Nugent Finance Lead: Phil Cole Legal Representative: Lorraine Moses-Copeman Procurement Lead: Brad Benson Other (i.e., HR / Health & Safety): n/a

VERSION CONTROL Version: 2 Date: 02/05/23 Change Prepared by: Lisa Hamilton Job Title: Snr Delivery Manager: Project & Programmes

pg. 2 SINGLE ASSURANCE FRAMEWORK

2 BASELINE ASSESSMENT, CHANGE REQUEST DESCRIPTION AND RATIONALE

2A WHICH BUSINESS CASE STAGE IS THIS CHANGE AGAINST? (SELECT ONE OPTION BELOW)

Business Justification Case (BJC CWG LEF – Jobs and Skills )☒

Programme Business Case (PBC)☒

2B ROOT CAUSE

Determine the root cause of this change request i.e. the source of the change requirement from the list below:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CWG Legacy Skill PBC Change Request Form FinalReport 752 KB DownloadRead as text
PDF
Change Request Skills Programme Business CaseReport 359 KB Download

At this meeting

Whole meeting

Who was there

9 of 11 attended
BS
Councillor Bob SleighChair, apologies
MB
Councillor Mike BirdCommittee Member, present
SC
Councillor Steve ClarkCommittee Member, present
PH
Councillor Peter HughesCommittee Member, present
KG
Councillor Karen GrinsellCommittee Member, present
JO
Councillor Jim O'BoyleCommittee Member, present
SS
Councillor Stephen SimkinsCommittee Member, present
ST
Councillor Sharon ThompsonCommittee Member, present, as expected, virtual
PB
Paul BrownCommittee Member, present, as expected, virtual
SS
Sue SummersCommittee Member, apologies
GT
Gary TaylorCommittee Member, present

On this subject at West Midlands Combined Authority

Search all
  1. Change Request Skills Programme Business CaseThis decision
  2. Housing Multi-Year Integrated Settlement Programme Business Case and Change Request to the 2025/26 Housing Integrated Settlement Programme Business CaseApproved
  3. Single Assurance Framework Change Request: UK Shared Prosperity Fund (2025-2026 Integrated Settlement Award)Approved
  4. Change Request to Global West Midlands (2025/26)Approved
  5. UK Central Infrastructure Programme Re-basing Change Request (June 24) & Project UpdateNoted
  6. Thrive into Work Individual Placement and Support in Primary Care - Change RequestApproved

More from West Midlands Combined Authority Investment Board

All decisions
MeetingDecisionOutcome
17 Aug 2026 Minutes - 20 July 2026The minutes of the meeting held on 20 July 2026 were approved as a correct record. Approved Open
17 Aug 2026 Rosewell Review Phase 2/ Transport for City Regions UpdateResolved that: 1. The principles developed to help guide the allocation of the remaining £405m of funding to the Port... Noted Open
17 Aug 2026 Investment Programme UpdateResolved that: 1. Since the previous sitting of the WMCA Investment Board there have been no change requests approved... Approved Open
17 Aug 2026 Investment Programme Dashboard- Red Rated Projects UpdateResolved that: 1. The current position of the eight red-rated projects within the Investment Programme Dashboard, inc... Noted Open
17 Aug 2026 Commercial Investment Fund DashboardResolved that: The report be noted. Noted Open