Global West Midlands - Full Business Case

Approved Committee 3 papers

Investment Board approved this item on Monday 16 October 2023. Below is the council's own wording, with the papers it was decided on.

Item51

Resolved

The release of £12.2m of West Midlands Combined Authority funding to West Midlands Growth Company (WMGC) over the next two years to 31 March 2025 be approved. This is comprised of: a. £9.9m from the Commonwealth Games Legacy Enhancement Fund allocation, from the total £14.1m agreed by the WMCA Board in March 2023, of which £2.5m was agreed by the Investment Board at the Strategic Outline Case stage: i.£1.8m which has been utilised by WMGC in order to develop the Full Business Case and to begin delivery against the local and regional priorities in the Programme in Quarters 1 and 2 of 2023/24 and ii. £0.7m which has been granted to local authorities from the WMCA to support an increase in capacity to deliver against priorities in the programme. b. £1.6m of UK Shared Prosperity Funding for 2024/25 with the same amount previously released for 2023/24 by the WMCA Board on 16 December 2022. c. £0.7m of WMCA core funding for 2024/25, with the same amount previously released for 2023/24 by the WMCA Board on 16 December 2022. 2. The appended Full Business Case and the total budget of £22.5m which includes all funding requesting in this report and approved at previous boards be noted and allocated as follows: a.£21.8m for the West Midlands Growth Company with the WMCA providing £18m and the remaining £3.8m from commercial and other funding leveraged by the WMGC; 3. The WMGC funding will enable the delivery of WMGC’s Business Plan 2023-25 which was agreed by the Economic Growth Board in July 2023 and is comprised of the following: - £14.1m from the Commonwealth Games Legacy Enhancement Fund, of which £0.7m has been granted to local authorities from the WMCA to support an increase in capacity to deliver against priorities in the programme, with the balance of £13.4m for WMGC - £3.2m from the UK Shared Prosperity Fund - £1.4m from the WMCA core budget 4. The balance of WMGC budget is comprised of £3.8m of commercial and other funding leveraged by the WMGC be noted; 5. The WMGC’s Business Plan 2023-2025 that was approved by the Economic Growth Board on 12 July 2023 be noted and 6. Agreed that Investment Board receive a 6 monthly update report on the Global West Midlands Programme.
Word for word from the decision West Midlands Combined Authority published for this meeting. Source: governance.wmca.org.uk

Follow this further

Built from West Midlands Combined Authority's papers

What the report saysPro

Report to Investment Board

Investment Board

Date 16th October 2023

Report title Global West Midlands – Full Business Case

Portfolio Lead Economy and Innovation

Accountable Chief Executive Neil Rami Chief Executive, West Midlands Growth Company Ed Cox Executive Director – Strategy, Economy and Net Zero Accountable Employee Katie Trout Director of Policy & Partnerships, West Midlands Growth Company Jonathan Skinner Head of Economic Policy and Partnerships Report has been considered by Investment Panel – 25th September 2023

Recommendation(s) for action or decision: The Investment Board is recommended to: (1) Approve the release of £12.2m of West Midlands Combined Authority (WMCA) funding to West Midlands Growth Company (WMGC) over the next two years, to 31st March 2025. This is made up of: a. £9.9m from the Commonwealth Games Legacy Enhancement Fund allocation, from the total £14.1m agreed by the West Midlands Combined Authority (WMCA) Board in March 2023, of which £2.5m was agreed by the Investment Board at the Strategic Outline Case stage: i. £1.8m which has been utilised by WMGC in order to develop the Full Business Case and to begin delivery against the local and regional priorities in the Programme in Quarters 1 and 2 of 2023/24; and ii. £0.7m which has been granted to Local Authorities from the WMCA to support an increase in capacity to deliver against priorities in the Programme. b. £1.6m of UK Shared Prosperity Funding (UKSPF) for 2024/25, with the same amount previously released for 2023/24 by the West Midlands Combined Authority (WMCA) Board on 16th December 2022. c. £0.7m of WMCA core funding for 2024/25, with the same amount previously released for 2023/24 by the West Midlands Combined Authority (WMCA) Board on 16th December 2022. (2) Note the appended Full Business Case (FBC) and, in doing so, the total budget of £22.5m, which includes all funding requested in this paper and approved at previous Boards. This is allocated as follows: a. £21.8m for the West Midlands Growth Company (WMGC), with WMCA providing £18.0m and the remaining £3.8m from commercial and other funding leveraged by the WMGC. b. £0.7m shared equally across the seven Local Authorities over the next two financial years. (3) Note the WMGC funding will enable the delivery of WMGC’s Business Plan 2023-25 which was agreed by the Economic Growth Board in July 2023, and is comprised of the following: • £14.1m from the Commonwealth Games Legacy Enhancement Fund, of which £0.7m has been granted to Local Authorities from WMCA to support an increase in capacity to deliver against priorities in the programme, with the balance of £13.4m for WMGC • £3.2m from the UK Shared Prosperity Fund • £1.4m from the WMCA core budget

(4) Note that the balance of WMGC’s budget is comprised of £3.8m of commercial and other funding leveraged by the WMGC. (5) Note the WMGC’s Business Plan 2023-2025 which was approved by the Economic Growth Board on 12th July 2023. A copy can be found in Appendix A.

1. Purpose 1.1. The key purpose of this FBC is to set out how WMGC will work in partnership with the WMCA, Local Authorities and other partners to: • Build on and maximise the conversion of the pipeline of leads generated from the Commonwealth Games Business and Tourism Programme (BATP), thereby fully exploiting the economic legacy of the Games; • Run a full programme of international promotion in key markets identified in the West Midlands’ forthcoming International Strategy (due to be available in draft in September 2023) to increase the region’s profile and reputation, resulting in the further growth of the current pipeline. This would also help to maximise the economic impact of other major sporting and cultural events that take place in the region; and • Secure the release of an additional £9.9m to enable WMGC to deliver the Global West Midlands (Global WM) programme as set out in the Full Business Case.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Global West Midlands: Full Business CaseReport 341 KB DownloadRead as text
PDF
Global West Midlands Risk and Investment Appraisal Board Report: v1.0Report 266 KB Download
PDF
WMGC Business Plan 2023-2025 post-Board 0.6Report 1.2 MB Download

At this meeting

Whole meeting

Who was there

8 of 13 attended
AA
Councillor Adrian AndrewCommittee Member, present
BS
Councillor Bob SleighChair, apologies, sent representative
MB
Councillor Mike BirdCommittee Member, apologies, sent representative
SC
Councillor Steve ClarkCommittee Member, present
MD
Councillor Matthew DormerCommittee Member, present
PH
Councillor Peter HughesCommittee Member, present
KG
Councillor Karen GrinsellCommittee Member, present
JO
Councillor Jim O'BoyleCommittee Member, apologies
SS
Councillor Stephen SimkinsCommittee Member, apologies
ST
Councillor Sharon ThompsonCommittee Member, expected
PB
Paul BrownCommittee Member, in attendance, virtual
SS
Sue SummersCommittee Member, apologies

All 13 on the meeting page

On this subject at West Midlands Combined Authority

Search all
  1. Global West Midlands - Full Business CaseThis decision
  2. Change Request to Global West Midlands (2025/26)Approved
  3. West Midlands Growth Company Q3 Performance Report against the 'Global West Midlands' Business PlanNoted
  4. WM Growth Company Q1 & Q2 Performance Report against the 'Global West Midlands' Business PlanApproved
  5. Global West Midlands - Strategic Outline CaseAgreed

More from West Midlands Combined Authority Investment Board

All decisions
MeetingDecisionOutcome
17 Aug 2026 Minutes - 20 July 2026The minutes of the meeting held on 20 July 2026 were approved as a correct record. Approved Open
17 Aug 2026 Rosewell Review Phase 2/ Transport for City Regions UpdateResolved that: 1. The principles developed to help guide the allocation of the remaining £405m of funding to the Port... Noted Open
17 Aug 2026 Investment Programme UpdateResolved that: 1. Since the previous sitting of the WMCA Investment Board there have been no change requests approved... Approved Open
17 Aug 2026 Investment Programme Dashboard- Red Rated Projects UpdateResolved that: 1. The current position of the eight red-rated projects within the Investment Programme Dashboard, inc... Noted Open
17 Aug 2026 Commercial Investment Fund DashboardResolved that: The report be noted. Noted Open