The Sandwell Aquatic Centre Energy Cost uplift Business Justification Case for a maximum grant of £1,395,754 funded by the Commonwealth Games Legacy Enhancement Fund and subject to the terms and conditions of the funding agreement in place between DCMS and the WMCA and additional clawback clauses if there is an additional expected underspend be approved; 2. The release of £604,246 on the back of the previous March 2023 WMCA Board Commonwealth Games Legacy Enhancement Fund (CWGLEF) allocation be approved (such changes are in line with the WMCA’s change control process, enabled by the Single Assurance Framework and signed off by the relevant boards of the WMCA and the change control process confirms that any underspends that emerge from the CWGLEF, are directed first towards the regional Plan for Growth or Community Grants programmes) be approved; 3. Subject to the approval of this investment, the WMCA pays a grant, quarterly in arrears, to Sandwell MBC from October 2023 based on monthly monitoring reports on actual spend and any additional underspends identified by 30 April 2024 be directed in line with the WMCA’s change control process first towards the regional Plan for Growth or Community Grants programme be noted and 4. Sandwell MBC funds £515,323 of the energy costs and any overspend above the forecast of £1,911,077 be noted.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
Report title CWG Legacy and Enhancement Fund -Sandwell MBC Aquatic Centre Energy Costs Business Justification Case Portfolio Lead Councillor Izzy Seccombe OBE – Wellbeing Portfolio Holder. Accountable Chief Laura Shoaf CBE Executive Chief Executive West Midlands Combined Authority [email removed] Accountable Clare Hatton Employee Interim Director of Employment, Skills and Communities email: [email removed]
Simon Hall Strategic Lead for Wellbeing and Prevention email: [email removed] Report has been Ben Percival, Assistant Director Borough Economy – considered by Contracts, Projects, Strategy and Policy Sandwell MBC. Cat Orchard, Head of Commonwealth Games Legacy and Enhancement Funding. Mubasshir Ajaz Head of Health and Communities
Recommendation for decision:
The Investment Board is recommended to:
(1) Approve the Sandwell Aquatic Centre Energy Cost uplift Business Justification Case for a maximum grant £1,395,754 funded by the Commonwealth Games Legacy and Enhancement Funding (CWGLEF) and subject to the terms and conditions of the funding agreement in place between DCMS and the WMCA and additional clawback clauses if there is an additional expected underspend.
(2) Approve the release of £604,246 back of the previous March 2023 WMCA Board £2m CWG LEF allocation. Such changes are in line with the WMCA’s change control process, enabled by the Single Assurance Framework and signed off by the relevant governance boards of the WMCA. This change control process confirms that any underspends that emerge across the CWGLEF, are directed first towards either the regional Plan for Growth or Community Grants programmes. (3) Note, subject to approval of this investment, WMCA will pay a grant quarterly in arrears to Sandwell MBC from October 2023 based on monthly monitoring reports on actual spend. Any additional underspends identified by 30 April 2024 will also be directed in line with the WMCA’s Change control process first towards the regional plan for growth or community grants programme
(4) Note that Sandwell MBC will fund £515,323 of the energy costs and any overspend above the forecast of £1,911,077.
1. Purpose
The WMCA Board agreed that all Commonwealth Games Legacy and Enhancement Funding (CWG LEF) Business Justification Cases would come to the Investment Board for approval. The Sandwell Aquatic Centre (SAC) Energy Cost project sets out the Business Justification Case for investment which will contribute towards the energy cost uplift forecasting for the SAC until 31 March 2025. In response to cost pressures, including the fluctuating energy market, this investment enables Sandwell MBC to continue to provide quality leisure provision at this Games venue and across the Borough delivering positive health, wellbeing, education, and employment outcomes.
2. Background 2.1 A paper was taken to WMCA Board in December 2022 to approve the WMCA as the accountable body for the receipt of up to £70m of the Commonwealth Games Legacy Fund, granted by the Department for Digital, Culture, Media & Sport from 75% of the unallocated contingency funding in the Commonwealth Games budget. The funding allocation was agreed to be split across four pillars, one of which is Wellbeing and Sustainability. The WMCA Board at its March 2023 meeting, approved the amendment to the CWG LEF Wellbeing and Sustainability Piller to include a £2m allocation to The SAC project building on the CWG delivery and the investment to redesign and open the “state of the art” SAC to the community at a time of significant cost pressures.
2.2A venue conceived and built for the 2022 Commonwealth Games, modified and recently opened as a key community local facility and a hub for swimming across the region, operated by the Sandwell Leisure Trust (SLT), the Council’s Leisure Management Contractors. A legacy facility for the community, replacing the ageing leisure facilities at Smethwick and Langley and a swimming competition venue for the West Midlands
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Investment Board at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.