The progress made on the CRTS Programme in Q4 of FY 23/24 be noted and 2. The submission of the FY23/24 annual report to the Department for Transport (DfT) be approved. Actions: Carl Beet
Investment Board noted this item on Monday 22 July 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
The progress made on the CRTS Programme in Q4 of FY 23/24 be noted and 2. The submission of the FY23/24 annual report to the Department for Transport (DfT) be approved. Actions: Carl Beet
3.4The Investment Board was established by the WMCA Board as a key element of the approvals process across the WMCA Investment Programme.
3.5On 10 June 2022, WMCA Board approved extending the role and remit of WMCA Investment Board to cover all WMCA projects (including those within the CRSTS programme), allowing investment decisions to be made for values between £5m and £20m in line with the WMCA Single Assurance Framework.
3.6The Investment Board considered and endorsed an enhanced Terms of Reference at its meeting on 24th July 2020. This set out an enhanced role supporting decision- making, greater post approval controls, performance management and effective delivery of monitoring & evaluation requirements.
3.7The enhanced Terms of Reference included the following:
• To add conditions to any funding decision that falls within its delegated authority. Minimum conditions should specify the availability period, conditions to drawdown of funds, conditions for withdrawal of support and terms of clawback, start date and completion date for the project or programme. • Where oversight of monitoring and evaluation applies to the Investment Board, to consider whether a formal review of project or programme is required, and to consider this review itself or instruct the Investment Panel to do so on its behalf.
4. Overview of the CRSTS Programme
4.1The National Infrastructure Strategy committed to investments in local transport networks to improve productivity in our largest cities. The national CRSTS programme aims to deliver transformational change through investments in public and sustainable transport infrastructure in some of England’s largest city regions through grant funding of £5.7bn over five years (2022/23 – 2026/27).
4.2The CRSTS funding is aimed at achieving the following objectives:
4.3Driving growth and productivity;
4.4Decarbonising transport; and
4.5Levelling up services and areas
4.6The West Midlands submitted a programme level business case consisting of 50 projects and programmes totalling an investment of over £1bn in transport improvements. This investment includes a government grant of £1.05bn along with £120.1m as a local contribution from WMCA and Local Authorities.
4.7The CRSTS funding consolidates a number of historic funding sources (including highways maintenance) and provides a very welcome five-year planning and resourcing horizon. 5. CRSTS Rebase and Historic Change Control Applications to DfT
6.1As noted in the Q2 FY23-24 update, approval of the inclusion of Rail Packages 1&2 into the programme was received on 22nd November 2023. Approval of the inclusion of Dudley Interchange into the programme was received on 5th May 2023.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CRSTS Annual Report 2023_24Appendix 2 | 3.4 MB | Download |
PDF |
Update Report : City Region Sustainable Transport Settlement -Quarter 4 FY 2023 -24Report | 292 KB | DownloadRead as text |
Follow Investment Board at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Aug 2026 | Minutes - 20 July 2026The minutes of the meeting held on 20 July 2026 were approved as a correct record. | Approved | Open |
| 17 Aug 2026 | Rosewell Review Phase 2/ Transport for City Regions UpdateResolved that: 1. The principles developed to help guide the allocation of the remaining £405m of funding to the Port... | Noted | Open |
| 17 Aug 2026 | Investment Programme UpdateResolved that: 1. Since the previous sitting of the WMCA Investment Board there have been no change requests approved... | Approved | Open |
| 17 Aug 2026 | Investment Programme Dashboard- Red Rated Projects UpdateResolved that: 1. The current position of the eight red-rated projects within the Investment Programme Dashboard, inc... | Noted | Open |
| 17 Aug 2026 | Commercial Investment Fund DashboardResolved that: The report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.