Resolved
The update provided with respect to the Coventry South Transport Package Schemes be noted and 2. Comments from Investment Board be taken forward and relayed back to the scheme promoters as appropriate.
Investment Board noted this item on Monday 11 November 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
The update provided with respect to the Coventry South Transport Package Schemes be noted and 2. Comments from Investment Board be taken forward and relayed back to the scheme promoters as appropriate.
Name of meeting: Investment Board
Meeting date: 11 November 2024
Report title: Coventry South Transport Package
Responsible Director: Ian Martin, Director of Commercial & Investment
Report author: John Seddon, Coventry City Council
Key Decision? No
Is the ability for the Combined Authority to make a decision internally reliant on Constituent or Non-Constituent Councils making a formal decision first?
☐Yes ☒No
(If Yes – please contact the Member Relationship Manager to manage this process)
Public/private Public report:
Exempt by virtue Choose an item. To view the reasons why a report could be made of paragraph: exempt please check the Report Writing Guidance.
1. Decision/s Recommended 1.1 That the update provided with respect to the Coventry South Transport Package schemes be considered and any comments relayed back to the scheme promoters.
2. Voting Requirements 2.1 N/a
3. Executive Summary 3.1 This report provides an update for the Investment Board on the status of four projects contained within the Coventry South Transport Package, namely: 3.1.1. A46 Stoneleigh Junction 3.1.2. A46 Link Road Phase Two 3.1.3. A46 Link Road Phase Three 3.1.4. Coventry South Interchange 4. Matters for Consideration
4.1The WMCA investment programme agreed in 2016/17 identified four main strategic transport packages within Coventry. These were: (a) Coventry City Centre First
(b) Coventry Very Light Rail
(c) Coventry North Transport Package
(d) Coventry South Transport Package
4.2The Coventry South Transport Package comprises the following schemes:
(a) A46 Binley Junction – completed
(b) A46 Walsgrave Junction – under development by National Highways
(c) Tile Hill Station – under development by CCC and TfWM as part of the CRSTS programme
(d) A46 Stoneleigh Junction – under construction
(e) A46 Link Road Phase Two and Three – scheme development led by CCC
(f) Coventry South Interchange – scheme development
4.3It should be noted that the schemes listed under a) and b) above do not form part of the WMCA’s investment programme, being/having been taken forward by National Highways instead.
4.4This report focuses upon the schemes listed under d), e), and f) above following an Investment Board request for an update on these specific schemes. The following sections provide a more detailed update on each of these schemes.
A46 Stoneleigh Junction
4.5The A46 Stoneleigh Junction comprises the first phase of the A46 Link Road scheme. It involves the improvement of the original junction layout through the construction of a new bridge across the A46 main carriageway to allow the provision of a full gyratory layout, which will reduce congestion, improve safety, and incorporate improved pedestrian and cycle routes through the junction. The scheme design is appended within section 18 of this report and further detailed information on the scheme is available on the WCC website (see link in 20.1).
4.6The Full Business Case for the A46 Stoneleigh Junction was approved by the Department for Transport in 2018, and a funding package approved comprising:
(a) Growth Deal funding (CWLEP / DfT) - £19.6m
(b) WMCA funding - £6.6m
(c) WCC funding from Section 106 contributions - £2.118m (d) WCC funding - £10m
4.7WCC are responsible for the construction of the scheme, as the junction lies wholly within Warwickshire. Construction commenced in 2020, and a key milestone was achieved in 2023 with the completion of the bridge lift, with the new bridge being lifted into place utilising a weekend closure of the A46. Completion of the scheme has been delayed, with the current estimate from WCC being that the new junction will be opened to traffic in mid-2025.
4.8A formal Change Request will be submitted in due course, however in summary the causes of the delay are:
(a) Problems in sourcing appropriate material to form the approach embankments to the new bridge allowing completion of the new roundabout.
(b) Contractual dispute between WCC and their primary contractor, Colas.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Coventry South Transport PackageReport | 998 KB | DownloadRead as text |
Follow Investment Board at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Aug 2026 | Minutes - 20 July 2026The minutes of the meeting held on 20 July 2026 were approved as a correct record. | Approved | Open |
| 17 Aug 2026 | Rosewell Review Phase 2/ Transport for City Regions UpdateResolved that: 1. The principles developed to help guide the allocation of the remaining £405m of funding to the Port... | Noted | Open |
| 17 Aug 2026 | Investment Programme UpdateResolved that: 1. Since the previous sitting of the WMCA Investment Board there have been no change requests approved... | Approved | Open |
| 17 Aug 2026 | Investment Programme Dashboard- Red Rated Projects UpdateResolved that: 1. The current position of the eight red-rated projects within the Investment Programme Dashboard, inc... | Noted | Open |
| 17 Aug 2026 | Commercial Investment Fund DashboardResolved that: The report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.