Investment Programme Update

Approved Committee 3 papers

Investment Board approved this item on Monday 11 November 2024. Below is the council's own wording, with the papers it was decided on.

Item72

Resolved

Approval under delegated authority by WMCA Officers of the business case submission disclosed at Section 4 of the report be noted; 2. The WMCA Investment Programme funding status and current affordable limit as outlined in Section 4 of the report be noted and 3. The Regional Investment Programme delivery update detailed within this report and appendices (including the project-level summary within the WMCA Investment Programme dashboard at Appendix 20 be noted.
Word for word from the decision West Midlands Combined Authority published for this meeting. Source: governance.wmca.org.uk

Follow this further

Built from West Midlands Combined Authority's papers

What the report saysPro

Report to Investment Board

Background

4.1The Investment Board was established by the WMCA Board as a key element of the approvals process across the Investment Programme.

4.2The Investment Board considered and endorsed an enhanced Terms of Reference at its meeting on 20th April 2020 (approved by WMCA Board 24th July 2020). This set out an enhanced role supporting decision-making, greater post approval controls, performance management and effective delivery of monitoring & evaluation requirements.

4.3The enhanced Terms of Reference included the following:

• To oversee and monitor all investments made through the Investment Programme.

• To add conditions to any funding decision that falls within its delegated authority. Minimum conditions should specify the availability period, conditions to drawdown of funds, conditions for withdrawal of support and terms of clawback, start date and completion date for the project or programme.

• Where oversight of monitoring and evaluation applies to the Investment Board, to consider whether a formal review of project or programme is required, and to consider this review itself or instruct the Investment Panel to do so on its behalf.

4.4On the 10th of June 2022, WMCA Board approved extending the role and remit of WMCA Investment Board to cover all WMCA projects (including the CRSTS programme), allowing investment decisions to be made for values between £5 million and £20 million in line with the Single Assurance Framework.

Investment Programme Assurance Summary

4.5Approved grant funding awarded and administered by the WMCA to programmes within the Regional Investment Programme totals £848.3 million as at 31st October 2024.

4.6These commitment values above exclude the provisional ‘ear-marked’ allocations agreed by WMCA Board in March 2021 that are yet to obtain formal approval. Commitments for some of these ear-marked items will be confirmed via the approval of further reports to WMCA Board. 4.7 Since the last sitting of WMCA Investment Board a Change Request was approved by the WMCA Investment & Commercial Activities director on 7th October 2024 for the Keresley Link Road project within the Coventry North package. The Change Request sought to extend the approved delivery dates for two sections of the project to 31st March 2026 and 31st March 2029.

4.8The TfWM Executive Director for transport also approved an Outline Business Case for the A452 Chester Road Corridor Enhancement project on 23rd October 2024. Funding from the Investment Programme previously awarded for the development of the Outline Business Case but not spent, totalling £309k, was approved to be re- allocated for detailed design work and FBC development alongside a further award of funding of £806k from the CRSTS programme.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
IP Update Report Nov-24 (Published)Appendix 1 112 KB Download
PDF
Investment Programme UpdateReport 223 KB DownloadRead as text
PDF
October 2024 IP Dashboard PublishedReport 293 KB Download

At this meeting

Whole meeting

Who was there

6 of 8 attended
PH
Councillor Peter HughesChair, present
CB
Councillor Christopher BurdenCommittee Member - Voting, present
SC
Councillor Steve ClarkCommittee Member - Voting, present
KM
Councillor Karen McCarthyCommittee Member - Voting, present
JO
Councillor Jim O'BoyleCommittee Member - Voting, apologies
BS
Councillor Bob SleighCommittee Member - Voting, present
MS
Councillor Mark StathamCommittee Member - Voting, present
SS
Sue SummersCommittee Member - Non-Voting, apologies

On this subject at West Midlands Combined Authority

Search all
  1. Investment Programme UpdateThis decision
  2. Investment Programme UpdateApproved
  3. Investment Programme Dashboard- Red Rated Projects UpdateNoted
  4. Investment Programme UpdateApproved
  5. Investment Programme UpdateApproved
  6. Investment Programme UpdateApproved

More from West Midlands Combined Authority Investment Board

All decisions
MeetingDecisionOutcome
17 Aug 2026 Minutes - 20 July 2026The minutes of the meeting held on 20 July 2026 were approved as a correct record. Approved Open
17 Aug 2026 Rosewell Review Phase 2/ Transport for City Regions UpdateResolved that: 1. The principles developed to help guide the allocation of the remaining £405m of funding to the Port... Noted Open
17 Aug 2026 Investment Programme UpdateResolved that: 1. Since the previous sitting of the WMCA Investment Board there have been no change requests approved... Approved Open
17 Aug 2026 Investment Programme Dashboard- Red Rated Projects UpdateResolved that: 1. The current position of the eight red-rated projects within the Investment Programme Dashboard, inc... Noted Open
17 Aug 2026 Commercial Investment Fund DashboardResolved that: The report be noted. Noted Open