WMCA Board, Friday 14 November 2025 at 11.00am

Delivering the West Midlands Growth Plan

Agreed Committee 2 papers

AI summaryWMCA Board endorses Growth Plan delivery, agrees £10m Employment Support Transition Fund and £18.8m for the West Midlands Growth Company for 2026/27.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedPlus £10m transition fund and £18.8m WMGC funding agreed
Money£18.8m for WMGC, £10m transition fundBoth for 2026/27, with tapered continuation to 2028/29
What happens nextFebruary 2026 Board meetingTo consider 2026/27 budget proposals including the £10m fund
Who it affectsWMCA constituent local authoritiesAnd businesses supported through WMGC services

What was decided

The Board endorsed work to deliver the West Midlands Growth Plan, including joint work with the Government, local authorities and the West Midlands Growth Company. Report P8

The Board agreed to include a £10m Employment Support Transition Fund within the 2026/27 budget proposals for the WMCA Board meeting on 13 February 2026, with delegated powers to the Executive Director for Employment, Skills, Health and Communities. Report P9

The Board agreed £18.8m funding for the West Midlands Growth Company for 2026/27 from WMCA economic development funding, as part of a three-year commitment with future amounts to be agreed in early 2026. Report P11

Why

Employment support funding streams to local authorities are coming to an end, and the Growth Plan and West Midlands Works Plan commit to an integrated employment and skills system. Report 2.7, 7.3

The West Midlands Growth Company is being positioned as the region's principal economic development body, with new services co-designed with local authorities requiring firm funding to plan for delivery from April 2026. Report 2.10, 2.11, 3.2

The Government has engaged with the Growth Plan following its launch, including sector plan investment awards and the Regional Investment Summit held in Birmingham on 21 October. Report 2.4, P27, P28, P29, P30

What happens next

The WMCA Board will consider 2026/27 budget proposals, including the £10m Employment Support Transition Fund, at its meeting on 13 February 2026. Report P9

The recruitment process for a new West Midlands Growth Company Chair will begin, with appointment expected in spring 2026, and a recommendation brought back to the Board for approval. Report 2.14, 8.5

A Programme Business Case for the Economic Development and Regeneration Pillar of the Integrated Settlement, including WMGC financial provision, is expected to be agreed in February, with further work on a West Midlands Economic Development Fund to return to the Board in the new year. Report 2.5, 2.13

The money

  • £10m Employment Support Transition Fund for 2026/27, from WMCA skills and economic development funding and other WMCA resources Report P37, P70
  • £6m Indicative tapered Employment Support Transition Fund for 2027/28, from WMCA skills and economic development funding Report P38, P71
  • £3m Indicative tapered Employment Support Transition Fund for 2028/29, from WMCA skills and economic development funding Report P39, P72
  • £18.8m Maximum funding to West Midlands Growth Company for 2026/27 from WMCA economic development and regeneration funding Report P11, 7.5
  • £100m+ Investment across recent sector plan and innovation announcements linked to the Growth Plan Report P27
  • £25m Creative Places Growth Fund Report P27
  • £30m Estimated electrification of regional automotive in DRIVE35 Report P27
  • £50m Local Innovation Partnership Fund Report P27
  • up to £360m Government Pride in Places investment over 10 years across 18 West Midlands neighbourhoods Report P30

Options considered

  • Chosen: Option 1: Allocate £18.8m to WMGC for 2026/27, setting a direction for a multi-year commitment. Enables WMGC to prepare for 2026/27 and develop its own multi-year corporate plan whilst longer-term direction is determined Report 3.2, P56, P58
  • Rejected: Option 2: Allocate £8m to WMGC from the Integrated Settlement (matching 2025/26 operating budget). Would ensure going concern status for 2026 but would not allow WMGC to begin building the capacity needed for new functions Report P56
  • Rejected: Option 3: Allocate at least £18.8m to WMGC for the three years from 2026/27 to 2028/29. Multi-Year Integrated Settlement likely to have significant tapering of revenue and capital funding, so prudent long-term commitment requires more work on sustainability Report P57

Implications

  • Financial: Funding is subject to a subsidy control assessment, and exact values remain to be confirmed by Government with strong indications provided. Report 7.6, 8.4
  • Legal: West Midlands Growth Company is a Teckal subsidiary under the Public Contracts Regulations 2015, enabling members to award contracts without procurement. Report 8.3
  • Equalities: A Tier 3 health equity impact assessment found likely positive equity impacts for age, sex, disability and ethnicity, including for approximately 20,000 young people via the Mayor's Youth Plan. Report P86
  • Staffing: Further detailed work on the transition of the Growth Company will continue, with any specific risks and issues such as TUPE implications brought to the Board as appropriate. Report 7.7
  • Other: WMGC Board will focus on operational delivery and not on strategic policy matters; strategy and policy will be led by the WMCA Board and WMCA. Report 2.3, P23

Who and where

  • WMCA constituent local authorities, who will receive Employment Support Transition Fund allocations and work alongside WMGC on local enterprise support Report 2.3, P9, P21
  • Up to 1,500 high-growth potential businesses in the region, to be served through a new WMGC high-growth service Report P20
  • Colleges, universities, integrated care boards, business organisations, trade unions and community organisations aligning to the Growth Plan Report 2.2
  • 93,000 more people projected to be in work by 2035 under the long-term devolved funding model being developed Report 2.7

Timeline

  • 21 July 2025: West Midlands Growth Plan launched in Wolverhampton Report 2.1
  • September 2025: Westminster launch of the Growth Plan attended by the Secretary of State for Business and Trade Report 2.4
  • 21 October 2025: West Midlands hosted the first Regional Investment Summit in Birmingham Report P28
  • 14 November 2025: WMCA Board endorsed Growth Plan delivery and agreed funding decisions Report P2
  • 13 February 2026: WMCA Board to consider 2026/27 budget proposals including the £10m Employment Support Transition Fund and Programme Business Case for the Economic Development and Regeneration Pillar Report P9, 2.13
  • Spring 2026: Appointment of new WMGC Chair to progress Report 2.14, 8.5
  • April 2026: WMGC to begin delivering new functions co-designed through the economic development review Report 3.2
  • 2026/27 to 2028/29: Indicative tapered Employment Support Transition Fund: £10m, £6m, £3m Report P37, P38, P39

Plain English for the jargon

  • WMCA: West Midlands Combined Authority
  • WMGC: West Midlands Growth Company, the region's principal economic delivery organisation
  • Teckal Company: A subsidiary company that complies with Regulation 12 of the Public Contracts Regulations 2015, allowing public bodies to award contracts to it without a procurement exercise
  • Multi-Year Integrated Settlement: A consolidated funding stream from Government representing just under half of total national public funding for economic growth linked to the WMCA
  • DRIVE35: A Government programme on electrification of regional automotive, with an estimated £30m for the West Midlands
  • Rosewell Review: A review informing the establishment of a prioritised major capital pipeline including provision for viability-gap funding
  • Office for Investment: A Government body working alongside WMGC to secure inward investment
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10

Resolved

(1) The work to deliver the West Midlands Growth Plan, including joint work with the Government, local authorities and the West Midlands Growth Company, was endorsed. (2) It was agreed that the WMCA include a £10m Employment Support Transition Fund within the 2026/27 budget proposals to be considered by the WMCA Board at its meeting on 13 February 2026, with powers delegated to the Executive Director for Employment, Skills, Health & Communities, in consultation with the Section 73 Officer, to agree allocations and make onwards awards to local authorities. (3) The intention to continue to provide a tapered level of Employment Support grant to local authorities in 2027/28 and 2028/29, which would be reflected in the WMCA's onward financial planning, was noted. (4) A commitment of £18.8m funding for the West Midlands Growth Company for 2026/27 from WMCA economic development funding, as part of agreeing to a three-year funding commitment for the West Midlands Growth Company, with the amounts for 2027/28 and 2028/29 being agreed in early 2026 as part of medium-term financial planning for economic development functions, was agreed. (5) The impact of West Midlands Growth Company activities in first two quarters of 2025/26 and further stretch targets, as agreed by the West Midlands Growth Company Board, were noted. (6) Progressing with the appointment of the West Midlands Growth Company Chair in spring 2026, including supporting the recruitment process with information about the role of the West Midlands Growth Company Board, was endorsed.
Word for word from the decision West Midlands Combined Authority published for this meeting. Source: governance.wmca.org.uk

Follow this further

Built from West Midlands Combined Authority's papers

What the report saysPro

Report to WMCA Board

Name of meeting: WMCA Board

Meeting date: 14 November 2025

Report title: Delivering the West Midlands Growth Plan

Responsible Director: Ed Cox, Chief Executive Jonathan Skinner, Head of Economic Policy & Partnerships Report author: Paul Edwards, Head of Economic Development & Delivery Key Decision? Yes

Is the ability for the Combined Authority to make a decision internally reliant on Constituent or Non-Constituent Councils making a formal decision first?

☐Yes ☐No

(If Yes – please contact the Member Relationship Manager to manage this process)

Recommendations (1) Endorse work to deliver the West Midlands Growth Plan, including joint work with Government, local authorities and the West Midlands Growth Company (WMGC).

(2) Agree that WMCA include a £10m Employment Support Transition Fund within the 2026/27 budget proposals to be considered by WMCA Board in February 2026 with powers delegated to the Executive Director for Employment, Skills, Health and Communities in consultation with the Section 73 Officer to agree allocations and make onwards awards to local authorities.

(3) Note the intention to continue to provide a tapered level of Employment Support grant to Local Authorities in 2027/28 and 2028/29 which will be reflected in WMCA's onward financial planning.

(4) Agree to a commitment of £18.8m funding for the WMGC for 2026/27, from WMCA economic development funding, as part of agreeing to a three-year funding commitment for the WMGC, with the amounts for 2027/28 and 2028/29 being agreed in early 2026, as part of medium-term financial planning for economic development functions.

(5) Note the impact of WMGC activities in first two quarters of 2025/26 (Appendix A) and further stretch targets, as agreed by the WMGC Board. (6) Endorse progressing the appointment of the WMGC Chair in spring 2026, including supporting the recruitment process with information about the role of the Growth Company Board.

Voting Requirements The Mayor, and separately, at least two-thirds of the members appointed by the constituent councils, in attendance in the meeting room and indicating their preference are required to vote in favour of any recommendation/proposition for it to become decision of the board [‘Requirement B’ as specified in paragraph 18.9(b) of the constitution].

1. Executive Summary 1.1 The report explains how the WMCA, local authorities and partners across the West Midlands are delivering the priorities of the Growth Plan to see living standards rise across all parts of the region.

1.2It shapes how economic development activities will be funded and delivered in the West Midlands by the WMCA, West Midlands Growth Company, local authorities and other partners so investment is used to generate greater impact for businesses and communities, and those returns are used to reinvest in growth.

2. Matters for Consideration

2.1Launched on 21 July 2025 in Wolverhampton, the West Midlands Growth Plan provides a single, coherent direction to further improve conditions for growth in the region. It explains steps for Our People to be more skilled and have greater opportunity, Our Businesses invest in more productive practices, Our Places have the infrastructure so communities flourish, and Our Story is used in a more consistent and compelling way.

2.2No single organisation can deliver the Growth Plan in its entirety, but it serves an important role to align partners’ activities. Led by the Mayor and chief executive, the WMCA is seeking to strengthen its relationships, making it easier for bodies like colleges and universities, integrated care boards, business organisations, trade unions and community organisations and Government agencies to articulate how they contribute to delivery of the Growth Plan and take account of impacts in their business planning.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
for Delivering the WM Growth PlanAppendix 1 87 KB Download
PDF
Delivering the West Midlands Growth PlanReport 375 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 29 attended
RP
Richard ParkerChair, expected
ST
Councillor Sharon ThompsonVice-Chair, expected
AA
Councillor Adrian AndrewCommittee Member, expected
MB
Councillor Mike BirdCommittee Member, expected
PB
Councillor Paul BradleyCommittee Member, expected
KC
Councillor Kerrie CarmichaelCommittee Member, expected
LC
Councillor Lee CarterNon-Constituent Member, expected
JC
Councillor John CottonCommittee Member, expected
IC
Councillor Ian CourtsCommittee Member, expected
ID
Councillor Ian DavisonNon-Constituent Member, expected
CD
Councillor Carol DeanNon-Constituent Member, expected
GD
Councillor George DugginsCommittee Member, expected

All 29 on the meeting page

More from West Midlands Combined Authority WMCA Board

All decisions
MeetingDecisionOutcome
17 Jul 2026 Apologies for AbsenceCecilie Booth (Audit, Risk & Assurance Committee), Councillor Paul Bradley (Dudley), Councillor George Duggins (Coven... Decided Open
17 Jul 2026 Chair's RemarksThe Chair provided a summary of the recent delivery and activity that he had been involved in. Decided Open
17 Jul 2026 Minutes - 12 June 2026Agreed as a correct record. Agreed Open
17 Jul 2026 Constitution Review(1) The proposed amendments to parts A and B of the constitution, as amended, were approved. (2) Authority was delega... Approved Open
17 Jul 2026 Rosewell Review Phase 2 / Transport for City Regions(1) The work undertaken as part of phase 2 of the Rosewell Review, including its proposals regarding how the Transpor... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies