AI summaryWest Midlands Combined Authority Board notes Investment Board minutes, which approved grant funding for 455 new homes at Abbotts Lane, Coventry, and deferred a decision on Curzon Street Ventures Limited.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedWMCA Board noted 20 October 2025 Investment Board minutes
Money£160,000 project costs approvedCharged to Land Fund for Abbotts Lane grant
What happens nextCurzon Street decision deferredTo a future Investment Board meeting
Who it affectsHousing and start-up sector455 homes at Abbotts Lane, regional start-up funding

What was decided

The WMCA Board noted the minutes of the Investment Board meeting of 20 October 2025. Report P1, P2

The Investment Board approved grant funding from the Land Fund to support a development of a minimum of 455 new homes at Abbotts Lane, Coventry, plus £160,000 in project costs to the Land Fund. Report P29, P30, P31, P33

The Investment Board deferred a decision on equity investment into Curzon Street Ventures Limited to a future meeting, citing gaps in the evidence provided. Report P22, P24, P26, P27, P28

Why

The Abbotts Lane grant addresses planning delays and a significant cost increase caused by the Building Safety Act 2022, which created a viability gap for the 455-home brownfield scheme. Report P30, P31

Curzon Street Ventures was deferred because the board considered the report lacked the necessary information, including evidence on jobs and GVA, founder investment, governance, and alignment with WMCA economic delivery vehicles. Report P24, P26

What happens next

The Director of Commercial and Investment is delegated authority to negotiate and agree the Abbotts Lane grant funding agreement and vary the obligations in the 23 November 2020 grant agreement. Report P33

Additional information is to be prepared for Curzon Street Ventures Limited before it returns to a future Investment Board meeting. Report P27, P28

The money

  • £248,000 Additional grant funding from CRSTS Capital Funding allocation for the Walking, Cycling & Green Infrastructure Investment Programme, approved under delegated authority Report P10
  • £960,000 Existing grant award from the WMCA Investment Programme across 2 Walking, Cycling & Green Infrastructure projects Report P10
  • £160,000 Project costs to be charged to the Land Fund for assessment, negotiation and contract management of the Abbotts Lane grant funding agreement Report P33

Options considered

  • Chosen: Approve grant funding from the Land Fund for Abbotts Lane, Coventry (455 new homes). To address viability gap caused by Building Safety Act 2022 cost increases and planning delays Report P29, P30, P31, P33
  • Rejected: Approve WMCA equity investment into Curzon Street Ventures Limited. Report did not provide the necessary information on jobs, GVA, founder investment, governance or alignment with WMCA economic delivery vehicles Report P22, P24, P26, P27, P28
  • Chosen: Note various Investment Programme and fund dashboard reports (Commercial Investment Fund, Brownfield Land & Property Development Fund, Residential Investment Fund, property investment loan outputs) Report P12, P13, P15, P17, P19, P35, P38, P41, P44

Implications

  • Financial: An additional £160,000 of project costs will be drawn from the Land Fund to support the Abbotts Lane grant agreement. Report P33
  • Risk: Curzon Street Ventures decision deferred due to concerns over evidence on returns, founder investment, governance arrangements and market testing. Report P24, P26
  • Other: Delegated approval of £248,000 extra CRSTS grant extends the Walking, Cycling & Green Infrastructure project to allow completion of the OBC for the Dickens Heath to Solihull Town Centre project by 31 August 2026. Report P10

Who and where

  • Residents and future occupants of the Abbotts Lane, Coventry development Report P30, P33
  • The applicant (developer) at Abbotts Lane, Coventry, in receipt of Land Fund grant Report P31, P33
  • Regional start-up businesses, as potential beneficiaries of Curzon Street Ventures Limited Report P22
  • West Midlands constituent local authorities and the wider regional economy Report P26

Timeline

  • 23 November 2020: Original grant agreement made between WMCA and the Abbotts Lane developer for site remediation Report P33
  • 22 September 2025: Previous Investment Board meeting, whose minutes were approved at the 20 October meeting Report P8
  • 1 October 2025: Position date for the Commercial Investment Fund, Brownfield Land & Property Development Fund, Residential Investment Fund and property investment loan dashboards Report P14, P16, P18, P34, P36, P39
  • 20 October 2025: Investment Board meeting, ending at 11.39 am Report P2, P45
  • 14 November 2025: WMCA Board meeting at which these minutes were noted
  • 31 August 2026: Deadline to complete the OBC for the Dickens Heath to Solihull Town Centre project under the extended Walking, Cycling & Green Infrastructure programme Report P10

Plain English for the jargon

  • CRSTS: City Region Sustainable Transport Settlement, central government capital funding for transport
  • OBC: Outline Business Case, an early stage in the development of a transport or infrastructure project
  • GVA: Gross Value Added, a measure of economic output
  • CSV: Curzon Street Ventures Limited, the proposed start-up investment vehicle considered by the board
  • WMCA: West Midlands Combined Authority
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item14

Resolved

The minutes were noted.
Word for word from the decision West Midlands Combined Authority published for this meeting. Source: governance.wmca.org.uk

Follow this further

Built from West Midlands Combined Authority's papers

What the report saysPro

Report to WMCA Board

Investment Board

Monday 20 October 2025 at 10.00 am

Minutes

Present Councillor Peter Hughes (Chair) Sandwell Metropolitan Borough Council Councillor Bob Sleigh (Vice-Chair) Solihull Metropolitan Borough Council Councillor Mike Bird Walsall Metropolitan Borough Council Councillor Christopher Burden City of Wolverhampton Council Councillor Steve Clark Dudley Metropolitan Borough Council Councillor Majid Mahmood Birmingham City Council Councillor Jim O'Boyle Coventry City Council

In Attendance Aanisah Begg West Midlands Combined Authority Cecilie Booth Chair of Audit, Risk & Assurance Committee Bal Chahal West Midlands Combined Authority Louise Cowen West Midlands Combined Authority Oliver Dyke West Midlands Combined Authority Adam Hunt Coventry City Council Ian Martin West Midlands Combined Authority Nick Oakley West Midlands Development Capital

Item Title No. 68. Apologies for Absence Apologies for absence were received from Sue Summers (West Midlands Development Capital).

69. Chair's Remarks The Chair welcomed the new Chair of Audit, Risk and Assurance Committee, Cecilie Booth who was observing the meeting virtually.

70. Minutes - 22 September 2025 The minutes of the meeting held on 22 September 2025 were approved as a correct record.

71. Investment Programme Update The board considered a report of the Director of Commercial and Investment that provided an update on the status of the Investment Programme to help set the context of any investment decisions made by the board.

Page 1 of 5 The Director of Commercial and Investment, Ian Martin, reported that since the last meeting on 22 September, one business case submission for grant funding had been approved under delegated authority. This related to the Walking, Cycling & Green Infrastructure Investment Programme; a change request was approved for £248,000 of additional grant funding from the CRSTS Capital Funding allocation, to supplement the existing £960,000 grant award from the Investment Programme (across 2 projects). It was noted that this approval extends the duration of the project, allowing time to complete the OBC for the Dickens Heath to Solihull Town Centre project by 31 August 2026.

The Director of Commercial of Investment also provided a summary of the Investment Programme dashboard.

Resolved that:

1. Approval under delegated authority by WMCA Officers of the business case submission disclosed at Section 4 of the report be noted. 2. The WMCA Investment Programme funding status and current affordable limit as outlined in Section 4 of the report be noted. 3. The Regional Investment Programme delivery update detailed with this report and appendices (including the project-level summary within the WMCA Investment Programme dashboard as at Appendix 2) be noted.

72. Commercial Investment Fund Dashboard The board considered a dashboard report detailing the Commercial Investment Fund (public iteration) as of 1 October 2025.

Resolved that: The report be noted.

73. Brownfield Land & Property Development Fund The board considered a report detailing the Brownfield Land and Property Development Fund (public iteration) as of 1 October 2025.

Resolved that: The report be noted.

74. Residential Investment Fund Dashboard The board considered a dashboard report detailing the Residential Investment Fund (public iteration) as of 1 October 2025.

Resolved that: The report be noted.

75. Exclusion of the Public and Press Resolved that:

In accordance with s100(A) of the Local Government Act 1972, the public and press be excluded from the meeting for the following items of business as they are likely to involve the disclosure of exempt information as specified in paragraphs of the Act. Page 2 of 5 76. Curzon Street Ventures Limited The board considered a report of the Chief Executive that sought approval of the Business Justification Case for Curzon Street Ventures Limited.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Investment Board: 20 October 2025Minutes 177 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 29 attended
RP
Richard ParkerChair, expected
ST
Councillor Sharon ThompsonVice-Chair, expected
AA
Councillor Adrian AndrewCommittee Member, expected
MB
Councillor Mike BirdCommittee Member, expected
PB
Councillor Paul BradleyCommittee Member, expected
KC
Councillor Kerrie CarmichaelCommittee Member, expected
LC
Councillor Lee CarterNon-Constituent Member, expected
JC
Councillor John CottonCommittee Member, expected
IC
Councillor Ian CourtsCommittee Member, expected
ID
Councillor Ian DavisonNon-Constituent Member, expected
CD
Councillor Carol DeanNon-Constituent Member, expected
GD
Councillor George DugginsCommittee Member, expected

All 29 on the meeting page

On this subject at West Midlands Combined Authority

Search all
  1. Investment Board - 20 October 2025This decision
  2. Investment Programme Dashboard- Red Rated Projects UpdateNoted
  3. Commercial Investment Fund DashboardNoted
  4. Residential Investment Fund DashboardNoted
  5. Commercial Investment Fund DashboardNoted
  6. Residential Investment Fund DashboardNoted

More from West Midlands Combined Authority WMCA Board

All decisions
MeetingDecisionOutcome
17 Jul 2026 Apologies for AbsenceCecilie Booth (Audit, Risk & Assurance Committee), Councillor Paul Bradley (Dudley), Councillor George Duggins (Coven... Decided Open
17 Jul 2026 Chair's RemarksThe Chair provided a summary of the recent delivery and activity that he had been involved in. Decided Open
17 Jul 2026 Minutes - 12 June 2026Agreed as a correct record. Agreed Open
17 Jul 2026 Constitution Review(1) The proposed amendments to parts A and B of the constitution, as amended, were approved. (2) Authority was delega... Approved Open
17 Jul 2026 Rosewell Review Phase 2 / Transport for City Regions(1) The work undertaken as part of phase 2 of the Rosewell Review, including its proposals regarding how the Transpor... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies