West Midlands Combined Authority
Investment Board, Monday 17 November 2025 at 10.00am

Annualised Integrated Settlement (IS) Active Travel Allocation

Approved Committee 5 papers

AI summaryWMCA Investment Board approved allocation of £12,341,244 of 2025/2026 Active Travel funding to programme delivery and West Midlands local authorities, with all spend required by 31 March 2027.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedAcross four defined funding streams
Money£12,341,244Total 2025/2026 Annualised IS Active Travel
What happens nextGrant agreements to be issuedDelegated to Executive Director of Transport
Who it affectsWest Midlands local authoritiesAll Constituent Local Authorities benefit directly

What was decided

The board approved a change to the Active Travel Programme Business Case to incorporate £12,341,244 of 2025/2026 Annualised Integrated Settlement Active Travel funding.

The board approved allocation of the funding across four streams: £953,199.20 to WMCA, £2,677,373.43 for Development Awards, £5,979,142.30 for Delivery Awards, and £2,731.529.07 for Shovel-Ready Schemes.

The board delegated authority to the Executive Director of Transport, in consultation with Finance, Legal and Procurement leads, to finalise and issue grant agreements with local authorities.

Why

The Finance Business Partner confirmed £12,341,244 of Integrated Settlement funding is available for Active Travel capital, with 7.72% (£953,199.20) used as revenue. Report 7.1, 7.2

WMCA Legal confirmed the authority is permitted to receive and issue grants under Section 31 of the Local Government Act 2003 and related legislation. Report 8.1

Programme Appraisal recommended approval after a high-level Risk and Investment Appraisal found risks to be manageable within existing programme controls. Report 9.2, 10.1

What happens next

WMCA Legal Services will finalise grant agreements with local authorities, ensuring compliance with Active Travel England guidance and WMCA assurance procedures. Report 8.2

Design elements must be complete by 31 March 2026, and all spend and claims must be submitted by 31 March 2027, unless a change control process is approved. Report 7.3

No payments will be released without signed grant agreements and evidence of spend; any material variations will be managed through formal change control. Report 7.3, 8.3

The money

  • £12,341,244 Total 2025/2026 Annualised IS Active Travel funding incorporated into the Programme Business Case Report 7.1
  • £953,199.20 WMCA retained for programme delivery as revenue-ised capital (7.72% of total) Report 7.2
  • £2,677,373.43 Development Award Allocation, via grant agreements with local authorities
  • £5,979,142.30 Delivery Award Allocation, via grant agreements with local authorities subject to business case approval
  • £2,731.529.07 Delivery Only (Shovel-Ready) Schemes, via grant agreements with local authorities

Options considered

  • Chosen: Approval of change to Active Travel Programme Business Case and four-stream allocation. Programme Appraisal recommended approval; funding is available and risks are manageable Report 9.2, 10.1

Implications

  • Financial: Up to 10% of the allocation may be used as revenue; this request converts 7.72% (£953,199.20). No payments released without signed grant agreements and evidence of spend. Report 7.2, 7.3
  • Legal: WMCA is authorised to receive and issue grants under Section 31 of the Local Government Act 2003; grant agreements must comply with Active Travel England guidance. Report 8.1, 8.2
  • Equalities: Health and Equity Impact Assessment identifies positive benefits for older people, disabled people (including neurodivergent), women, ethnic minorities and deprived communities, with 27% of regional households without a car and 11.9% in transport poverty. Report P18, P21, P22, P23, 9.7, 9.8
  • Climate: Investment supports WMCA net zero objectives by encouraging walking and cycling in place of short car trips and improving air quality. Report P25, 9.8
  • Risk: Inclusion of 2025/2026 Annualised IS Active Travel Funding introduces limited new risk to the Programme Business Case, manageable within existing programme controls. Report 10.1, 10.2

Who and where

  • All Constituent Local Authorities of WMCA (direct funding allocations for scheme development and delivery) Report 11.1
  • Non-constituent members (not financially impacted but may benefit from regional connectivity improvements) Report 11.2
  • Residents in transport poverty (11.9% of West Midlands region) and households without a car (27%) Report P18, 9.8
  • Older people, disabled people, women, ethnic minorities and deprived communities, who stand to gain from improved active travel infrastructure Report P21, P22, P23

Timeline

  • 31 March 2026: Design elements must be complete Report 7.3
  • 31 March 2027: All spend and claims must be submitted, unless change control process is approved Report 7.3

Plain English for the jargon

  • IS: Integrated Settlement, a funding stream allocated to WMCA
  • PBC: Programme Business Case
  • WMCA: West Midlands Combined Authority
  • SRO: Senior Responsible Officer
  • HEIA: Health and Equality Impact Assessment, used here to mean the Transport Functional Strategy assessment
  • LTN 1/20: Local Transport Note 1/20, the national cycle infrastructure design standard
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item88

Resolved

Resolved that: 1. A change to the Active Travel Programme Business Case (PBC) to incorporate £12, 341, 244 of 2025/2026 Annualised Integrated Settlement Active Travel funding within the existing programme under the WMCA Single Assurance Framework be approved. 2. The allocation of this funding across four defined funding be approved as follows: a. WMCA to retain and utilise for programme delivery revenue-ised capital - £953,199.20 b. To enter into grant agreements with local authorities for the Development Award Allocation- £2,677,373.43 c. To enter into grant agreements with local authorities subject to business case approval, for the Delivery Award Allocation- £5,979,142.30. d. To enter into grant agreements with local authorities for Delivery Only (Shovel- Ready) Schemes -£2,731.529.07 3. Authority be delegated to the Executive Director of Transport for West Midlands, in consultation with the WMCA’s Finance, Legal and Procurement leads, to finalise and issue grant agreements with local authorities. 4. All expenditure must be completed by 31 st March 2027, unless approved change control process is undertaken be noted.
Word for word from the decision West Midlands Combined Authority published for this meeting. Source: governance.wmca.org.uk

Follow this further

Built from West Midlands Combined Authority's papers

What the report saysPro

Report to Investment Board

Name of meeting: WMCA Investment Board

Meeting date: 17 November 2025 Annualised Integrated Settlement (IS) Active Travel Report title: Allocation Anne Shaw - Executive Director, Transport for West Responsible Director: Midlands Report author: Elliott Hill [email removed]

Key Decision? Yes

Is the ability for the Combined Authority to make a decision internally reliant on Constituent or Non-Constituent Councils making a formal decision first?

☐Yes ☒No

(If Yes – please contact the Member Relationship Manager to manage this process)

Recommendations That the WMCA Investment Board:

(1) Approves a change to the Active Travel Programme Business Case (PBC) to incorporate £12,341,244 of 2025/2026 Annualised Integrated Settlement (IS) Active Travel funding within the existing programme under the WMCA Single Assurance Framework.

(2) Approves the allocation of this funding across four defined funding pots as follows:

a. WMCA to retain and utilise for programme delivery Revenu-ised Capital - £953,199.20 b. To enter into grant agreements with local authorities for the Development Award Allocation - £2,677,373.43 c. To enter into grant agreements with local authorities, subject to business case approval, for the Delivery Award Allocation - £5,979,142.30 d. To enter into grant agreements with local authorities for Delivery Only (Shovel- Ready) Schemes - £2,731,529.07

(3) Delegates authority to the Executive Director of Transport for West Midlands, in consultation with WMCA’s Finance, Legal, and Procurement leads, to finalise and issue grant agreements with Local Authorities. (4) Note that all expenditure must be completed by 31st March 2027, unless approved change control process is undertaken.

Voting Requirements A majority of voting members, in attendance in the meeting room and indicating their preference, are required to vote in favour of any recommendations for it to become a decision of the board.

1. Executive Summary 1.1 This report seeks approval for a change to the approved Active Travel Programme Business Case (PBC) to incorporate the newly confirmed 2025/2026 Annualised Integrated Settlement (IS) Active Travel Funding. The change request adds £12.34m of capital funding to the existing programme to enable continued delivery of walking, wheeling and cycling schemes across the region, without altering the programme’s approved scope, objectives or delivery timescales.

1.2The decision will ensure seamless programme continuity, value for money, and alignment with regional priorities for sustainable transport and decarbonisation.

2. Matters for Consideration

2.1The WMCA has received confirmation of its 2025/2026 Integrated Settlement Active Travel capital allocation, totalling £12.34m. The funding will extend the existing Active Travel Programme without altering its objectives or timescales.

2.2The funding supports four complementary areas:

a. Revenu-ised Capital – WMCA programme management, design assurance, technical support. b. Development Awards – early-stage scheme design and feasibility by Local Authorities. c. Delivery Awards – construction and monitoring of approved schemes. d. Delivery-Only Schemes – shovel-ready schemes ready for immediate construction. 2.3 This approach:

a. Maintains governance under the Single Assurance Framework (SAF). b. Prevents delivery gaps between funding years. c. Ensures LTN 1/20-compliant design and robust value-for-money assurance.

3. What options have been considered and what is the evidence telling us about them?

3.1Option 1: Do Nothing - would result in reputational damage with funding providers and local authority partners, lost funding and delay delivery.

3.2Option 2: Manage as a separate funding - administratively inefficient and inconsistent with SAF.

3.3Preferred Option: Integrate funding into approved PBC - provides efficiency, assurance, and transparency.

4. Reasons for recommending preferred option

4.1Integrating IS funding within the existing Active Travel Programme:

4.2Maintains consistent governance, assurance, and monitoring.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Annualised Integrated Settlement (IS) Active Travel AllocationReport 192 KB DownloadRead as text
PDF
Change Request (IS) Active Travel AllocationAppendix 1 277 KB Download
PDF
Scheme List and Funding AllocationAppendix A 108 KB Download
PDF
Scheme Output and Value for Money OverviewAppendix B 112 KB Download
PDF
AT Programme Risk RegisterAppendix C 211 KB Download

At this meeting

Whole meeting

Who was there

7 of 8 attended
PH
Councillor Peter HughesChair, present
BS
Councillor Bob SleighVice-Chair, present
MB
Councillor Mike BirdCommittee Member - Voting, apologies, sent representative
CB
Councillor Christopher BurdenCommittee Member - Voting, present
SC
Councillor Steve ClarkCommittee Member - Voting, present
MM
Councillor Majid MahmoodCommittee Member - Voting, present
JO
Councillor Jim O'BoyleCommittee Member - Voting, present
SS
Sue SummersCommittee Member - Non-Voting, apologies

More from West Midlands Combined Authority Investment Board

All decisions
MeetingDecisionOutcome
17 Aug 2026 Minutes - 20 July 2026The minutes of the meeting held on 20 July 2026 were approved as a correct record. Approved Open
17 Aug 2026 Rosewell Review Phase 2/ Transport for City Regions UpdateResolved that: 1. The principles developed to help guide the allocation of the remaining £405m of funding to the Port... Noted Open
17 Aug 2026 Investment Programme UpdateResolved that: 1. Since the previous sitting of the WMCA Investment Board there have been no change requests approved... Approved Open
17 Aug 2026 Investment Programme Dashboard- Red Rated Projects UpdateResolved that: 1. The current position of the eight red-rated projects within the Investment Programme Dashboard, inc... Noted Open
17 Aug 2026 Commercial Investment Fund DashboardResolved that: The report be noted. Noted Open