AI summaryWest Midlands Combined Authority Investment Board noted the Investment Programme update: approved grant funding totals £844.3 million against an £871 million affordable limit, with £720.9 million spent by 30 September 2025. No new business case approvals were made under delegated authority since the previous meeting.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedNo new delegated approvals, status and Q2 performance noted
Money£844.3m approved of £871m limit£720.9m drawn down to 30 September 2025
What happens nextChange requests progressingProgramme team working on RED status projects
Who it affects84 WMCA Investment Programme projectsSix schemes currently RED status
What was decided
The Board noted that no business cases had been approved under delegated authority by WMCA officers since the previous Board sitting.
The Board noted the Investment Programme funding status and the current £871 million affordable limit set out in section 4 of the report. Report 4.5
The Board noted the Regional Investment Programme delivery update, the project-level dashboard at Appendix 2, and the Quarter 2 performance overview at Appendix 3. Report 4.11, 4.13, 4.18
Why
The Investment Board is the body set up by the WMCA Board to oversee and monitor all investments made through the Investment Programme and to consider funding decisions between £5 million and £20 million under the Single Assurance Framework. Report 4.1, 4.3, 4.4
The report is part of a regular series of updates to give the Board assurance on the funding position, delivery and performance of the Investment Programme. Report P31, 4.10, 4.11
Officers have flagged six schemes as RED status for completion dates and are working with project sponsors and the Programme Assurance and Appraisal team to bring forward change requests to the relevant approval body. Report 4.17, P27
What happens next
The Programme Assurance and Appraisal team will work with sponsors to bring forward requests to extend completion dates for the six RED status schemes, including UKC Infrastructure projects, Accelerated Housing Delivery, Playing Pitch Implementation, Middlewood House, Rowood Drive, Balsall Common and Solihull Town Centre Public Realm. Report 4.17, P26, P27
A Project Change Request has been prepared to extend the Balsall Common Multimodal Transport Package completion from 31 December 2025 to 31 December 2029, to align with the implementation of the Local Plan scheduled for 2029. Report P27
WMCA officers will review the UK Government Autumn Budget statement to ascertain any impact on the region's Investment Programme and report back as needed. Report P50
The money
£871 million Current WMCA Investment Programme affordable limit of grant funding Report 4.5, P10
£844.3 million Total approved grant funding awarded and administered by WMCA to programmes within the Regional Investment Programme as at 30th September 2025 Report 4.6
£720.9 million WMCA Investment Programme funding used to fund Eligible Expenditure of projects against funding commitments, to 30th September 2025 Report 4.10
£12.16m Significant expenditure April to September 2025: Rail, Walsall to Wolverhampton Local Enhancements, Package 1 Report P20
£4.75m Significant expenditure April to September 2025: Coventry City Centre South Regeneration Report P20
£3.87m Significant expenditure April to September 2025: Rail, Camp Hill Line Local Enhancements, Package 2 Report P20
Options considered
Chosen: Not applicable - this is a regular update report with no decision options presented Report P31, P32
Implications
Financial: Approved commitments of £844.3 million sit within the £871 million affordable limit, with £720.9 million drawn down to 30 September 2025. Report 4.5, 4.6, 4.10
Legal: The Investment Programme is underpinned by the Annual Devolution Deal grant from the Department for Levelling Up, Housing and Communities; funding must be used in line with grant terms, with legal support obtained as appropriate. Report 11.1, 11.2
Risk: Project delivery is subject to macro and local economic risks, but funding awarded is capped and project sponsors must manage and mitigate cost escalations. Six schemes are currently RED status for completion dates. Report 4.17, P27, P49
Risk: Officers are reviewing the UK Government Autumn Budget statement to assess any impact on the region's Investment Programme. Report P50
Equalities: Officers confirm there are no equalities implications arising from this report. Report P52
Who and where
Project sponsors and delivery partners across 84 schemes that have passed the Assurance Process and received a financial commitment
Sponsors of the six RED status schemes, including UKC Infrastructure, Accelerated Housing Delivery, Playing Pitch Implementation, Middlewood House, Rowood Drive, Balsall Common Multimodal Transport and Solihull Town Centre Public Realm Report 4.17, P26, P27
Programme Assurance and Appraisal team at WMCA Report 4.17
Constituent and non-constituent local authority members of the WMCA Report 9.1, P54
Timeline
20th April 2020: Investment Board endorsed enhanced Terms of Reference (approved by WMCA Board 24th July 2020) Report 4.2
19th March 2021: WMCA Board approved increase to affordable limit from £801 million to £871 million Report 4.5, P10
10th June 2022: WMCA Board extended Investment Board remit to cover all WMCA projects including CRSTS, with delegated decisions between £5 million and £20 million Report 4.4
27th January 2025: Change Request for UKC Infrastructure Programme approved Report P26
28th March 2025: Solihull Town Centre Public Realm Improvement OBC submitted requesting further funding Report P27
30th September 2025: Data cut-off: £844.3 million approved, £720.9 million drawn down Report 4.6, 4.10
20th October 2025: Previous full meeting of WMCA Investment Board Report 4.8
17th November 2025: Current Investment Board meeting
31 March 2026: Requested extension date for Accelerated Housing Delivery Project Change Request to submit OBCs for viable sites Report P27
31 December 2029: Proposed new completion date for Balsall Common Multimodal Transport Package, aligned with Local Plan implementation Report P27
Plain English for the jargon
WMCA: West Midlands Combined Authority
Investment Programme: The WMCA's programme of grant-funded capital and revenue projects, subject to an affordable limit
Affordable limit: The maximum amount of grant funding that can be provided by WMCA from the Investment Programme, currently £871 million
CRSTS: City Region Sustainable Transport Settlement
Single Assurance Framework: WMCA's framework governing how funding decisions are made, including delegated authority for values between £5 million and £20 million
RED status: A project where the original completion date has passed without conclusion or where a time extension is required
OBC: Outline Business Case
Change Request: A formal request to alter an approved project's scope, funding, or timetable
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item87
Resolved
Resolved that: 1. Since the previous sitting of WMCA Investment Board there has been no approvals of any business cases under delegated authority by WMCA Officers be noted. 2. The WMC Investment Programme funding status and current affordable limit as outlined in section 4 of the report be noted. 3. The Regional Investment Programme delivery update detailed within this report and appendices (including the project-level summary within the WMCA Investment Programme dashboard at Appendix 2, and the Quarter 2 performance overview at Appendix 3) be noted.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
4.1The Investment Board was established by the WMCA Board as a key element of the approvals process across the Investment Programme.
4.2The Investment Board considered and endorsed an enhanced Terms of Reference at its meeting on 20th April 2020 (approved by WMCA Board 24th July 2020). This set out an enhanced role supporting decision-making, greater post approval controls, performance management and effective delivery of monitoring & evaluation requirements.
4.3The enhanced Terms of Reference included the following:
• To oversee and monitor all investments made through the Investment Programme.
• To add conditions to any funding decision that falls within its delegated authority. Minimum conditions should specify the availability period, conditions to drawdown of funds, conditions for withdrawal of support and terms of clawback, start date and completion date for the project or programme.
• Where oversight of monitoring and evaluation applies to the Investment Board, to consider whether a formal review of project or programme is required, and to consider this review itself or instruct the Investment Panel to do so on its behalf.
4.4On the 10th of June 2022, WMCA Board approved extending the role and remit of WMCA Investment Board to cover all WMCA projects (including the CRSTS programme), allowing investment decisions to be made for values between £5 million and £20 million in line with the Single Assurance Framework.
Investment Programme Affordable Limit & Gateway Status
4.5At the WMCA Board meeting on 19th March 2021, WMCA Board approved an increase to the current WMCA Investment Programme affordable limit of £70 million, from £801 million to £871 million. This remains the current limit of grant funding1 that can be provided by WMCA from the Investment Programme.
1 Excluding part of the anticipated recoverable/recyclable commitment to the West Midlands Co-Invest Equity
fund approved by WMCA Board on 23rd July 2021. Investment Programme Assurance Summary
4.6Approved grant funding awarded and administered by the WMCA to programmes within the Regional Investment Programme totals £844.3 million as 30th September 2025. which is unchanged from the amount reported at the previous sitting of Board.
4.7These commitment values above exclude the provisional ‘ear-marked’ allocations agreed by WMCA Board in March 2021 that are yet to obtain formal approval. Commitments for some of these ear-marked items will be confirmed via the approval of further reports to WMCA Board.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Investment Board at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.