Kingshurst Village Centre Regeneration Phase 2 Full Business Case
ApprovedCommittee2 papers
AI summaryWest Midlands Combined Authority Investment Board approves £8,000,000 grant to Solihull Council for Kingshurst Community Health and Retail building, subject to conditions.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedSubject to three conditions on funding and monitoring
Money£8,000,000 grantNon-refundable, 39% of total £20,524,000 cost
What happens nextSolihull Cabinet decisionDue 17 September 2026 before grant signing
Who it affectsSolihull MBC and Kingshurst residentsCommunity health, retail and library services
What was decided
The Board approved the Full Business Case for £8,000,000 of grant funding from the Investment Programme to Solihull Metropolitan Borough Council for the Community Health and Retail building, as a non-refundable grant towards total project costs of £20,524,000. Report P3, P12
Approval is conditional on the project receiving Solihull Cabinet approval to progress to Phase 1 on 17 September 2026, an updated Benefits Realisation Plan with quantified outputs and outcomes, and an updated Monitoring and Evaluation Plan. Report P19
Authority to negotiate the Grant Funding Agreement was delegated to the Executive Director and Investment Programme Senior Responsible Owner.
Why
The scheme is assessed as High Value for Money with a Benefit Cost Ratio of 2.7, provided the current tenant mix is maintained over the 60-year appraisal period and no further public funding is needed for cost increases. Report P9, P22
Officers recommended approval with conditions, finding the scheme likely to deliver place-based regeneration, improved health access, local employment, and net zero carbon building outcomes in a deprived Solihull area. Report P17, P18, P74, P77
The overall business case maturity was rated 73 percent, classed as Green/Amber, indicating successful delivery is probable with constant attention to risks. Report P80
What happens next
Solihull Metropolitan Borough Council Cabinet is due to consider the project on 17 September 2026, and all unsecured funding must be confirmed before the Grant Funding Agreement is signed. Report P19, P50
An updated Benefits Realisation Plan with clear output and outcome targets, and a standalone Monitoring and Evaluation Plan, must be provided to the Investment Programme and Appraisal teams. Report P19, P58, P59
The Grant Funding Agreement is to be drawn down quarterly in arrears at an intervention rate, with a clawback clause and a requirement that the proposed tenant mix is broadly maintained. Report P19
The money
£8,000,000 WMCA Investment Programme grant to Solihull MBC, 39% of total cost, subject of this application Report P3, P12
£3,637,000 Solihull borrowing from revenue budget allocations, 14% of total Report P11, P12
£2,954,000 Solihull borrowing from tenant rental income, 18% of total Report P11, P12
£2,997,000 Solihull Strategic Community Infrastructure Levy, 15% of total Report P12
£1,236,000 Integrated Care Board contribution, 6% of total, secured Report P12
£1,700,000 Birmingham Enterprise Zone contribution, 8% of total, agreed in principle Report P12
£19,723,000 Stated cost of the CHR building within total scheme Report P52
Options considered
Chosen: Approve the Full Business Case with conditions on funding confirmation, Benefits Realisation Plan, and Monitoring and Evaluation Plan. BCR of 2.7 indicates High Value for Money and scheme maturity is 73% Report P9, P17, P19, P80
Rejected: Reject the Full Business Case
Implications
Financial: £8,000,000 of WMCA Investment Programme funding is committed, representing 39% of total scheme cost; significant further funding from Solihull borrowing, tenant rental income, CIL, and other sources remains unsecured. Report P12, P19, P23
Risk: Funding uncertainty is high: SMBC borrowing, CIL, and Birmingham Enterprise Zone contributions are not yet secured, and there is a risk the scheme may not be affordable for Solihull given circa £1.4 million cost increase from RIBA Stage 3 to Stage 4. Report P11, P12, P23
Equalities: Project is expected to support inclusive growth by improving access to local health services, addressing health inequalities, providing local employment, and supporting the local business ecosystem in a deprived Solihull area. Report P74
Climate: New CHR building is planned as net zero carbon in operation, with solar PV, air source heat pumps, MVHR technology, modern methods of construction, and BREEAM Excellent standard for the GP space. Report P77
Legal: Grant Funding Agreement must include a quarterly arrears drawdown, intervention rate calculation, clawback on non-completion, and a clause maintaining the proposed tenant mix to protect value for money. Report P19
Other: Officers noted that project objectives were unclear, inconsistent across the business case, and lacked output and outcome targets, creating risks for benefits realisation and WMCA oversight. Report P8, P21, P25, P37, P59
Who and where
Solihull Metropolitan Borough Council, as recipient of the grant and accountable body Report P3, P11
Kingshurst residents and users of the new community, health and retail building Report P5, P6, P74
Local community groups, voluntary organisations, and public health providers expected to use flexible community space Report P35
Integrated Care Board, contributing £1,236,000 in secured capital funding Report P12
Birmingham Enterprise Zone, contributing £1,700,000 subject to Full Business Case approval Report P12
Timeline
December 2025: Solihull Cabinet previously considered indicative capital funding strategy including Strategic CIL Report P12
08.07.26: Final Willmott Dixon cost package due to allow updating of the Economic Case Report P44, P51, P68
17 September 2026: Solihull Metropolitan Borough Council Cabinet to consider the project before grant signing Report P50
60 years: Appraisal period for the new CHR building, on which the Value for Money assessment depends Report P9, P22
Plain English for the jargon
BCR: Benefit Cost Ratio, used to assess Value for Money. A BCR of 2.7 here places the scheme in the High category.
CHR building: Community Health and Retail building, the main part of Phase 2 and the subject of this Full Business Case.
Phase 2a: Six affordable homes and a vicarage delivered alongside the CHR building but funded separately, including a Homes England grant and Solihull HRA funds.
Single Assurance Framework: WMCA's process for reviewing and appraising business cases for funding decisions.
Benefits Realisation Plan: A document setting out the scheme's outputs, outcomes, benefits, and targets for monitoring delivery.
BREEAM Excellent: A high environmental performance standard for buildings, targeted for the GP space within the CHR building.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item23
Resolved
The Full Business Case for grant funding of £8000,000 towards the capital costs of Phase 2 of the Kingshurst Regeneration: the community, health and retail building be approved subject to: - the project receiving approval to progress to Phase 1 from Solihull Metropolitan Borough Council Cabinet on 17 September 2026; - An updated Benefits Realisation Plan being approved, including clearly defined and quantified outputs, outcomes and benefits. - An updated Monitoring and Evaluation Plan is provided to strengthen assurance around outputs, outcomes, evaluation and value for money. 2. Authority be delegated to the Executive Director/Investment Programme SRO to negotiate the terms of the Grant Funding Agreement.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
The Investment Board are required to make a decision on whether to:
1) Approve the Full Business Case for the delivery of the Community Health and Retail (CHR) building, part of the Kingshurst Village Centre Regeneration scheme in Solihull; 2) Release £8,000,000 from Investment Programme funding to Solihull Metropolitan Borough Council (SMBC) as a non-refundable grant, to fund the above.
The project:
This Full Business Case is not a continuation of the Outline Business Case which covered the entire Kingshurst Village Centre Regeneration scheme in Solihull. It refers only to part of the original Phase 2, which has now been split into the Phase 2 (CHR building) and Phase 2a (6 homes and a vicarage).
This business case relates to the delivery of the CHR building. The rest of Phase 2, not covered by this business case, consists of the delivery of 6 homes and a vicarage on the same site.
Value for Money Summary
Project objectives are broad, unclear and vary across the business case and do not have outputs and outcomes targets, which raises concerns around whether the benefits will be realised and may pose difficulties for WMCA oversight of the scheme.
The BCR for the scheme is 2.7, which places the scheme in the Value for Money category of High. It should be noted that this level of benefits will only be achieved if the current mix of tenants is kept the same (or similar) for the lifetime of the building (60 years) and there will be no further future increase in costs that need to be funded from public sources.
Financial summary:
Table 12 Funder Amount % of Status Details of Funding Status / Timing / Total (Secured / Conditions etc. Not Secured) Borrowing financed by confirmed revenue budget Solihull £3,637,000 14 Not Secured allocations. Amount may vary depending on MBC interest rate at time of borrowing. Borrowing financed by tenant rental income. Will Solihull become confirmed as leases agreed. Amount £2,954,000 18 Not Secured MBC may vary depending on interest rate at time of borrowing. 1|1 9 Risk & Investment Appraisal Single Assurance Framework
Strategic Community Infrastructure Levy. Reported to Cabinet as part of indicative capital Solihull £2,997,000 15 Not Secured funding strategy in December 2025 but subject to MBC final consideration of business case by Solihull MBC Cabinet Integrated ICB contribution to capital project. Sum received £1,236,000 6 Secured Care Board by Solihull MBC Birmingham Enterprise £1,700,000 8 Not Secured Agreed in principle but subject to FBC Zone WMCA £8,000,000 39 Not Secured Subject of this application Total £20,524,000 100%
This FBC has been submitted by Helen Bielby, Project Manager, Solihull Metropolitan Borough Council (SMBC).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Councillor Chris GarghanCommittee Member - Voting, present
LK
Councillor Lynnette KellyCommittee Member - Voting, present
RN
Councillor Ray NockCommittee Member - Voting, present
DP
Councillor Dave PinwellCommittee Member - Voting, present
EW
Councillor Elaine WilliamsCommittee Member - Voting, apologies, sent representative
Hear about the next one first
Follow Investment Board at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.