Investment Board, Monday 20 July 2026 at 10.00am

Update Report City Regions Sustainable Transport Settlement Quarter 4 FY 2025/26

Noted Committee 1 paper

AI summaryWest Midlands Combined Authority Investment Board noted Q4 2025/26 progress on the City Region Sustainable Transport Settlement programme. £639m has been spent of the £1.182bn government grant, with a further £417m forecast by 31 March 2027.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedBoard noted Q4 FY 2025/26 CRSTS progress
Money£639m spent to dateOf £1.182bn CRSTS settlement, as of 31 March 2026
What happens nextContinued delivery to March 2027Further £417m forecast for April 2026 to March 2027
Who it affectsWest Midlands transport projects64 projects across seven local authorities and WMCA

What was decided

The Board noted the progress made on the CRSTS programme during Q4 of financial year 2025/26.

Why

The Investment Board has an enhanced role supporting decision-making, performance management and monitoring of WMCA projects under its delegated authority of £5m to £20m. Report 1.2, 1.3

Monitoring and evaluation of the CRSTS allocation is a funding condition, requiring West Midlands Combined Authority as accountable body to report quarterly to the Department for Transport. Report 4.1, 4.3

What happens next

Spend is forecast to accelerate with a further £417m of expenditure expected from April 2026 to 31 March 2027, after which funding will be contractually committed. Report 5.10

A rebaseline of the programme was approved by WMCA Board on 9 May 2025, with DfT approval received in August 2025 and now actioned in the reported figures. Report 3.7, 3.8

Further updates on the Rosewell Review and Transport for City Regions work were taken to WMCA Board on 17 July 2026. Report 6.3

The money

  • £5.7bn National CRSTS programme grant over five years 2022/23 to 2026/27 Report 3.1
  • £1.182bn West Midlands CRSTS government grant Report 3.2, 5.2
  • £120.1m Local contribution committed to West Midlands programme Report 3.2
  • £1.277bn CRSTS funding approved against the £1.182bn settlement as of 31 March 2026 Report 5.2
  • £1.467bn Overprogrammed level to maximise delivery Report 5.2
  • £639m Expenditure funded from CRSTS capital settlement to 31 March 2026 Report 5.3
  • £1.056Bn Forecast total CRSTS expenditure to 31 March 2027 Report 5.4
  • £417m Forecast expenditure from April 2026 to March 2027 Report 5.4, 5.10
  • £68m Further funding approved since 31 December 2025 Report P36
  • £64m Further spend since 31 December 2025 Report P37
  • £162m Projects rephased into West Midlands CRSTS allocation by May 2025 rebaseline Report 3.7
  • c. £120m Expected local match funding, around 15% of original CRSTS settlement Report 5.14
  • c. £119.7m Local contribution achieved to date, subject to potential re-financing Report 5.15

Options considered

  • Chosen: Note Q4 2025/26 progress on the CRSTS programme. Routine quarterly monitoring and evaluation under funding conditions with DfT Report 4.1, 4.2

Implications

  • Financial: Up to 25% overprogramming is in place to reduce risk of underspend and clawback of grant by DfT before 31 March 2027. Report 5.10
  • Risk: Top five programme risks are clawback of CRSTS grant, skilled personnel shortages, economic pressure, programme and project dependencies, and unclear WMCA governance processes. Report P44
  • Risk: Across schemes, budget risks account for 23% of identified risks, schedule risks 18% and operational risks 12%. Report 5.7
  • Staffing: Skilled personnel shortages in CRSTS projects are flagged as one of the top five programme risks. Report P44
  • Financial: Department for Transport has confirmed in writing that CRSTS Data Scheme Support and Monitoring expenditure may continue beyond March 2027 as evaluation is required for five years after delivery. Report 5.11, 5.12, P49
  • Legal: No legal considerations arise from the recommendations, which are for noting only. Report 7.1, P60
  • Equalities: No equalities considerations arise from the recommendations, which are for noting only. Report 8.1, P62
  • Other: Two CRSTS-funded business cases and four Change Requests were confirmed as Single Assurance Framework compliant through the Programme Assurance and Appraisal process in the period. Report 11.2

Who and where

  • West Midlands Combined Authority as accountable body for the CRSTS allocation Report 4.1
  • Seven West Midlands local authorities: Birmingham, Coventry, Dudley, Sandwell, Solihull, Walsall and Wolverhampton Report P33
  • Department for Transport as funder and approver of the rebaselined programme Report 3.7, 3.8
  • Transport users and residents across the West Midlands Report 5.1, P23, P24, P25
  • Private sector contributors providing Section 106 and other local match funding Report 5.16

Timeline

  • 24th July 2020: Investment Board endorsed enhanced Terms of Reference covering monitoring, evaluation and post-approval controls. Report 1.3
  • 10th June 2022: WMCA Board extended Investment Board remit to cover all WMCA projects including CRSTS, with delegated decisions between £5m and £20m. Report 1.2
  • September 2023: Initial programme re-baseline undertaken at DfT request to reflect inflationary construction cost pressures. Report 3.5
  • July 2024: Further change prioritising projects in construction and development, deferring some projects pending value engineering or wider capital programme review. Report 3.6
  • 9th May 2025: Rebaseline report approved at WMCA Board, rephasing £162m of projects to higher chance of delivery before March 2027. Report 3.7
  • August 2025: Department for Transport approval of the rebaseline received and actioned. Report 3.8
  • 23rd March 2026: Previous CRSTS Q3 update report to Investment Board covering period to 31 December 2026. Report 5.5, P72
  • 29th May 2026: Q4 FY 2025/26 update submitted to Department for Transport. Report 4.2, 5.5
  • 20th July 2026: Investment Board meeting noting Q4 progress on CRSTS programme.
  • 31st March 2027: End of current five-year CRSTS settlement period; funding to be contractually committed by this date. Report 5.10

Plain English for the jargon

  • CRSTS: City Region Sustainable Transport Settlement, a national five-year transport funding programme for England's largest city regions.
  • WMCA: West Midlands Combined Authority, the accountable body for the CRSTS allocation.
  • DfT: Department for Transport, the UK government department providing the CRSTS grant.
  • FBC: Full Business Case, the most detailed stage of project business case approval.
  • OBC: Outline Business Case, an intermediate project business case stage.
  • SOBC: Strategic Outline Case, the earliest project business case stage.
  • BJC: Business Justification Case, a business case format used in the WMCA assurance process.
  • PAA: Programme Assurance and Appraisal, the WMCA process for assuring projects and change requests.
  • SAF: Single Assurance Framework, the WMCA framework governing investment decisions and assurance.
  • LNIP: Local Network Improvement Plan, an element of historic local transport funding now consolidated into CRSTS.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item22

Resolved

The progress made on the City Region Sustainable Settlement (CRSTS) programme during Q4 of financial year 2025/26 be noted.
Word for word from the decision West Midlands Combined Authority published for this meeting. Source: governance.wmca.org.uk

Follow this further

Built from West Midlands Combined Authority's papers

What the report saysPro

Report to Investment Board

Background

1.1The Investment Board was established by the WMCA Board as a key element of the approvals process across the WMCA Investment Programme.

1.2On 10th June 2022, WMCA Board approved extending the role and remit of WMCA Investment Board to cover all WMCA projects (including those within the CRSTS programme), allowing investment decisions to be made for values between £5m and £20m in line with the WMCA Single Assurance Framework.

1.3The Investment Board considered and endorsed an enhanced Terms of Reference at its meeting on 24th July 2020. This set out an enhanced role supporting decision-making, greater post approval controls, performance management and effective delivery of monitoring & evaluation requirements.

1.4The enhanced Terms of Reference included the following: • To add conditions to any funding decision that falls within its delegated authority. Minimum conditions should specify the availability period, conditions to drawdown of funds, conditions for withdrawal of support and terms of clawback, start date and completion date for the project or programme.

• Where oversight of monitoring and evaluation applies to the Investment Board, to consider whether a formal review of project or programme is required, and to consider this review itself or instruct the Investment Panel to do so on its behalf.

3. Overview of CRSTS Programme

3.1The National Infrastructure Strategy committed to investments in local transport networks to improve productivity in our largest cities. The national CRSTS programme aims to deliver transformational change through investments in public and sustainable transport infrastructure in some of England’s largest city regions through grant funding of £5.7bn over five years (2022/23 – 2026/27).

3.2The West Midlands submitted a programme level business case consisting of 50 projects and programmes totalling an investment of over £1bn in transport improvements. This investment includes a government grant of £1.182bn, along with £120.1m as a local contribution from WMCA and Local Authorities.

3.3The CRSTS funding consolidates a number of historic funding sources (including highways maintenance) and provide a very welcome five-year planning and resourcing horizon.

Changes to the West Midlands Region CRSTS Programme

3.4The West Midlands CRSTS programme has continued to evolve following its establishment and subsequent approval by DfT in 2022. As to be expected with a programme of this nature, changes have been required for a number for factors which have included inflationary cost pressures, externally driven scope changes and supply chain issues.

3.5An initial re-baseline of the programme was undertaken in September 2023, which was undertaken across the programme, at the request of DfT, in order to reflect inflationary construction cost pressures.

3.6A further change was made in July 2024, which set out a number of capital and programme pressures to the capital delivery programme, the prioritisation of delivery for projects already in construction and development and the deferral of some projects until funding is available either through the ongoing commercial scrutiny and value engineering to tackle cost increases, or subject to a wider review of the whole capital programme.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Update Report City Regions Sustainable Transport Settlement Quarter 4 FY 2025/26Report 254 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 7 attended
SS
Councillor Stephen SimkinsChair, present
SC
Councillor Steve ClarkVice-Chair, present
CG
Councillor Chris GarghanCommittee Member - Voting, present
LK
Councillor Lynnette KellyCommittee Member - Voting, present
RN
Councillor Ray NockCommittee Member - Voting, present
DP
Councillor Dave PinwellCommittee Member - Voting, present
EW
Councillor Elaine WilliamsCommittee Member - Voting, apologies, sent representative

On this subject at West Midlands Combined Authority

Search all
  1. Update Report City Regions Sustainable Transport Settlement Quarter 4 FY 2025/26This decision
  2. Rosewell Review Phase 2/ Transport for City Regions UpdateNoted
  3. Rosewell Review Phase 2 / Transport for City RegionsNoted
  4. Rosewell Review/Transport for City RegionsNoted

More from West Midlands Combined Authority Investment Board

All decisions
MeetingDecisionOutcome
17 Aug 2026 Minutes - 20 July 2026The minutes of the meeting held on 20 July 2026 were approved as a correct record. Approved Open
17 Aug 2026 Rosewell Review Phase 2/ Transport for City Regions UpdateResolved that: 1. The principles developed to help guide the allocation of the remaining £405m of funding to the Port... Noted Open
17 Aug 2026 Investment Programme UpdateResolved that: 1. Since the previous sitting of the WMCA Investment Board there have been no change requests approved... Approved Open
17 Aug 2026 Investment Programme Dashboard- Red Rated Projects UpdateResolved that: 1. The current position of the eight red-rated projects within the Investment Programme Dashboard, inc... Noted Open
17 Aug 2026 Commercial Investment Fund DashboardResolved that: The report be noted. Noted Open