That: 1. the progress update for Barley Homes and steps outlined in Report number: CAB/WS/21/062, to secure its medium term pipeline of sites, be noted. 2. The Barley Homes Business Plan 2021, attached as Exempt Appendix A to Report number: CAB/WS/21/062, be approved. That: 1. the progress update for Barley Homes and steps outlined in Report number: CAB/WS/21/062, to secure its medium term pipeline of sites, be noted. 2. The Barley Homes Business Plan 2021, attached as Exempt Appendix A to Report number: CAB/WS/21/062, be approved.
Word for word from the decision West Suffolk published for this meeting.Source: democracy.westsuffolk.gov.uk
Barley Homes: Business Plan 2021 Report number: CAB/WS/21/062 Report to and date: Cabinet 7 December 2021
Cabinet member: Councillor Sara Mildmay-White Portfolio Holder for Housing and Strategic Health Telephone: 01359 270580 Email: [email protected]
Lead officer: Julie Baird Director (Planning and Growth) Telephone: 01284 757613 Email: [email protected]
Decisions Plan: The decision made as a result of this report will usually be published within 48 hours and cannot be actioned until five clear working days of the publication of the decision have elapsed. This item is included on the Decisions Plan.
Wards impacted: All wards
Recommendations: It is recommended that Cabinet:
1. notes the progress update for Barley Homes and steps outlined in this report to secure its medium term pipeline of sites.
2. Approves the Barley Homes Business Plan 2021, attached as Exempt Appendix A to Report number: CAB/WS/21/062. Cabinet – 7 December 2021 – CAB/WS/21/062
1. Context to this report 1.1 Each year Barley Homes Limited, the Council’s wholly owned Housing Company, produces its annual business plan setting out its development plans for the forthcoming year and medium term against the investment facility made available to it. The total investment facility now available to Barley Homes Limited is a £14.25 million revolving loan/equity facility funded through a mixture of capital receipts (which supports the equity element) and the Investing in our Growth Agenda fund.
1.2Since the Business Plan was approved by Council in December 2020, as reported via the Annual Report 2020 (on the Barley Homes website) the company has made good progress in achieving its aims and progressed the sites set out in its Business Plan at Stonemill Park (formerly Castle Hill) and Westmill Place (formerly Westfield), Haverhill, for the delivery of 63 homes, of which 19 are affordable. All homes at Westmill Place were completed during the summer of 2021 and sold with residents moving in shortly afterwards and throughout September and October. Stonemill Park has progressed well with homes being available on the market in early 2022.
1.4Following the agreement of the 2020 business plan, progress has been made on the two new sites identified at that time, at School Lane, Great Barton and Kingshall Street, Rougham. We are also continuing to explore options to deliver at College Heath Road at Mildenhall.
1.5A number of future sites are being explored by Barley Homes and the Council as part of the ongoing process of supplying Barley Homes with a viable development pipeline. A viable development pipeline will enable Barley Homes to continue to utilise the agreed £14.25m investment fund which then provides financial returns to the Council through loan interest receipts and dividend payments. The annual business planning process has not highlighted a need to revise the total investment fund. As there is no further funding required for the investment fund for Barley Homes, the approval of the 2021 business plan sits as an executive function of the Cabinet.
1.6The purpose of this report
1.6.1 The propose of this report is to present the 2021 Business Plan to Cabinet for agreement. The Business Plan outlines the progress with the committed sites and associated financial implications. Cabinet – 7 December 2021 – CAB/WS/21/062
2. Proposals within this report 2.1 The development of the Business Plan 2021
2.1.1 The proposed business plan (Exempt Appendix A) focuses on Barley Homes’ completion of the development of Stonemill Park, Haverhill as well as work to bring forward the site at Kingshall Street, Rougham. It also outlines the work the Council and Barley Homes is engaged with to progress the sites at School Lane, Great Barton and College Heath Road, Mildenhall.
2.1.2 This work has been set in the context of the Council’s strategic framework and Medium-Term Financial Strategy (MTFS).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.