The progress update for Barley Homes and steps outlined in Report number: CAB/WS/23/059 to secure its medium-term pipeline of sites, be noted. 2. The Barley Homes Business Plan 2023, covering 2024 to 2028, attached at Appendix A to Report number: CAB/WS/23/059, be approved. That: 1. The progress update for Barley Homes and steps outlined in Report number: CAB/WS/23/059 to secure its medium-term pipeline of sites, be noted. 2. The Barley Homes Business Plan 2023, covering 2024 to 2028, attached at Appendix A to Report number: CAB/WS/23/059, be approved.
Word for word from the decision West Suffolk published for this meeting.Source: democracy.westsuffolk.gov.uk
Barley Homes Business Plan 2023 Report number: CAB/WS/23/059 Report to and date: Cabinet 5 December 2023
Cabinet member: Councillor Richard O’Driscoll Portfolio Holder for Housing Email: richard.o'[email protected]
Lead officers: Julie Baird Director (Planning and Growth) Tel: 01234 757613 Email: [email protected]
Rachael Mann Director (Resources and Property) Tel: 01234 751245 Email: [email protected]
Decisions Plan: The decisions made as a result of this report will usually be published within 48 hours and cannot be actioned until five clear working days of the publication of the decision have elapsed. This item is included on the Decisions Plan but no longer constitutes a Key Decision. Wards impacted: All wards Recommendations: It is recommended that Cabinet:
1. Notes the progress update for Barley Homes and steps outlined in this report to secure its medium-term pipeline of sites.
2. Approves the Barley Homes Business Plan 2023, covering 2024 to 2028, attached at Appendix A to Report number: CAB/WS/23/059. Cabinet – 5 December 2023 – CAB/WS/23/059
1. Context to this report 1.1 Each year Barley Homes Ltd, the Council’s wholly owned Housing Company, produces its annual business plan. This Barley Homes Business Plan is presented in a revised structure and one which focusses on the overall business activity, and ambitions for building a high performing portfolio.
1.2The business plan contains a review of the previous year; an overview of the operating conditions for the company; a summary of the planned development programme, including aspirations around current and medium-term delivery rates; and an overview of the financial underpinnings to the future development strategy, all to demonstrate prudent resource planning.
1.3The total investment facility already available to support Barley Homes Ltd is a £14.25 million revolving facility (available for loans to, equity in and land purchases to support, our wholly owned housing company) funded through a mixture of capital receipts (which supports the equity element) and the Investing in our Growth Agenda fund.
1.4Since the previous business plan was approved by Council in December 2022 (report CAB/WS/22/072 refers) and as reported via the Annual Report 2023 the company has made good progress in achieving its aims. This has included completing the sites set out in its business plan at Stonemill Park and Westmill Place in Haverhill. At these two sites Barley Homes Ltd have delivered 63 homes, of which 19 were affordable.
1.5Following the agreement of the 2022 Business Plan, significant progress has also been made on purchasing and submitting a planning application for a site in Rougham.
1.6Further progress includes Barley Homes purchasing the College Heath Road site in Mildenhall (One Public Estate assembled site) and working with a local registered provider in delivering a scheme that will help address local housing need.
1.7Progress has also been made with the Great Barton draft development brief in preparation for a future application.
1.8Overall, Barley Homes through this business plan will be facilitating the delivery of 93 homes of which 56 will be affordable. This ongoing viable development pipeline enables Barley Homes to continue to utilise the agreed £14.25 million investment fund which then provides financial returns to the Council through loan interest receipts and dividend payments. Cabinet – 5 December 2023 – CAB/WS/23/059
1.9The annual business planning process has not highlighted a need to revise the total investment fund, considering known cash flow forecasts across the medium term. As there is no change required to the investment fund for Barley Homes, the approval of the 2023 Business Plan sits as an executive function of the Cabinet.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.