The Cabinet:- (1) approves the proposal to enlarge Golborne High School by increasing its physical capacity so that it can continue to admit 230 pupils into Year 7 with effect from 2022 and subsequent years; (2) authorises budget release of the out-turn figure of £1,200,000; (3) delegates authority to the Assistant Director – Corporate Property, Assets and Greenspaces in consultation with the Assistant Director - Education to approve: a. tender acceptance for the proposed building works to accommodate the additional places, b. authorise the use of the 10% project contingency built into the £1,200,000 as required within the budget release figure; and (4) authorises the Assistant Director – Legal to complete the necessary agreements to give effect to the above.
Word for word from the decision Wigan published for this meeting.Source: democracy.wigan.gov.uk
Subject: Decision: School Organisation - Proposed Permanent Enlargement of Golborne High School
Report of: Catherine Pealing, Assistant Director - Education
Contact Officer: Darren Thomas-Stanley (01942 486027)
Cabinet Portfolio Holder and area: Councillor Jenny Bullen, Portfolio Holder for Children and Families
Summary: The purpose of the report is to inform Cabinet of the responses to the statutory notice on the proposal to permanently expand Golborne High School, request that Cabinet determines the proposal and authorise the budget release.
Link to Corporate Priorities:
Our People: Together we feel happy, safe, included and look out for each other:
• Best start in life for children and young people • Happy healthy people • Communities that care for each other
Our Future: Together we will build a future where everyone has the opportunity to thrive:
• Economic growth that benefits everyone • A well-connected place • Confidently digital • A home for all
Wards Affected: Golborne and Lowton West
Recommendation(s): The Cabinet is recommended to:
1. approve the proposal to enlarge Golborne High School by increasing its physical capacity so that it can continue to admit 230 pupils into year 7 with effect from 2022 and subsequent years; 2. authorise budget release of the out-turn figure of £1,200,000; 3. delegate authority to the Assistant Director – Corporate Property, Assets and Greenspaces in consultation with the Assistant Director - Education to approve: a. tender acceptance for the proposed building works to accommodate the additional places, b. authorise the use of the10% project contingency built into the £1,200,000 as required within the budget release figure; and 4. authorise the Assistant Director – Legal to complete the necessary agreements to give effect to the above.
Implications:
What are the financial implications? A feasibility study with an associated cost plan has been completed indicating an estimated total cost for the construction project of £1,200,000 to meet the need to accommodate the additional places. This capital investment will be met by £500,000 basic need funding/section 106 and a £700,000 contribution from the school. It is assumed that scheme costs will be part funded by the school and from S106 contributions, subject to Housing Developments progressing as per the S106 agreements. Should there be a shortfall in S106 contributions received then Basic Needs funding will be used to gap fund to the value stated above.
Is budget release necessary (Capital Expenditure Only)? Budget release is required, and the LA basic need funding has been confirmed by the Strategic Finance Manager.
What are the legal implications? Local Authorities must ensure that they act in accordance with the relevant legislation: School Organisation (Prescribed Alterations to Maintained Schools) (England) Regulations 2013 and relevant DfE guidance; Making significant changes (‘Prescribed Alterations’) to Maintained Schools October 2018.
In relation to the proposed building project to accommodate the additional places, the Council is subject to a public procurement regime, as set out in the Public Contracts Regulations 2015 (the Regulations). The use of frameworks is compliant with these Regulations and the Council’s Contract Procedure Rules (CPR). It is anticipated that the building contractor will be selected by running a mini competition on the NHS SBS Construction Framework or North-West Construction Hub framework.
Officers shall ensure that the calling-off from the relevant Framework shall be done in a manner that is compliant with the CPR and the Framework.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.