Wigan Metropolitan Borough Council
Cabinet, Tuesday 18 November 2025 at 10.30am

Treasury Management and Capital Programme Half Yearly Review 25/26

Approved Executive 2 papers

AI summaryCabinet endorsed the council's half year treasury management position and an updated capital programme showing a net £10.346m increase, with 2025/26 spend revised down £39.204m to £148.196m.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedTreasury Management position and updated Capital Programme
Money£148.196mRevised 2025/26 capital programme allocation
What happens nextFull Council approvalCabinet endorsed, Council to formally approve
Who it affectsCouncil-wide finances and capital schemesBorrowing, investments, and directorate projects

What was decided

Cabinet endorsed to Council for approval the Treasury Management position for the first half of 2025/26. Report 1.1

Cabinet endorsed to Council for approval the adoption of the updated Capital Programme, which shows a net increase of £10.346m overall but a 2025/26 allocation reduced by £39.204m to £148.196m after reprofiling. Report 11.2, 11.3

Cash balances of £49.060m were held at 30 September 2025, with investments returning 4.38% against a SONIA benchmark of 4.34%. Report 8.1, 8.2

Why

The report reviews Treasury Management activity for the first six months of 2025/26 and sets out prospects for the remainder of the year, in line with statutory duties. Report 1.1, 9.1

The capital programme has been revised to reflect known slippage and new approvals since the Quarter 1 review submitted to Cabinet on 31 July 2025. Report 11.1, 11.3

Officers note that interest rates and price inflation continue to put pressure on the programme and associated revenue costs. Report 12.1

What happens next

The matter goes to full Council for formal approval of the Treasury Management position and the updated Capital Programme.

Further borrowing is anticipated early in Quarter 3 of 2025/26, with rates lower at the short end of the curve, refinancing with longer term borrowing when rates fall. Report 5.7

Officers will mitigate risks through an optimal borrowing strategy, rephasing, capital strategy review, and consideration of financing options. Report 12.2, P71

The money

  • £10.346m Net overall increase to the capital programme at Quarter 2 Report 11.2, 11.5
  • £148.196m Revised 2025/26 total capital programme allocation Report 11.3, P92
  • £187.400m Previous 2025/26 allocation at Quarter 1 Report 11.3
  • £40.618m Actual capital spend April to September 2025 Report 11.4, P85
  • £49.060m Cash and investment balances at 30 September 2025 Report 8.1, 10.1, P15
  • £72.21m Forecast cash balances by 31 March 2026 Report 10.1
  • £671.704m Capital Financing Requirement for 2025/26 Report 5.1, 5.3, P19
  • £459.533m Council borrowings as at Quarter 2 Report 5.3, P19
  • £386.352m PWLB loans held as at 1 April 2025 Report 5.4
  • £15.626m Total interest payable on PWLB loans in 2025/26 Report 5.4, 5.5

Implications

  • Financial: Council operated within its treasury and prudential indicators during the quarter ended 30 September 2025, with no difficulties envisaged. Report 9.2, 9.3
  • Financial: Average investment return of 4.38% outperformed the 90 day average SONIA rate of 4.34% by 0.04%. Report 8.2
  • Financial: Capital programme changes include £6.600m for Wood Fold Primary School, £1.348m uplift to Civic Centre Redevelopment, £0.379m for Wigan Leisure Centre gym and studio, and £2.855m for IFRS16 lease reclassifications. Report P59, P62, P64, P68, 11.5
  • Financial: Adults programme reduced by £2.145m and HRA programme increased by a net £3.782m, largely due to boiler renewal forecasts. Report P61, P67
  • Financial: No new PWLB borrowing in the first half of 2025/26; £10m of short term borrowing was taken for two weeks in Quarter 1. Report 5.6
  • Risk: No debt rescheduling has taken place in 2025/26; officers continue to monitor credit ratings and counterparty risk. Report 6.1, 7.4, 7.5
  • Other: Base Rate is forecast to fall to 3.75% on 19 March 2026, subject to inflation data and the Autumn Budget on 26 November 2025. Report 2.1, 2.2

Who and where

  • Wigan Council directorates delivering the capital programme (People, Places, Resources) Report P85, P86, P87, P88, P89, P90, P91
  • Schools benefiting from CYPS additions (Abram Bryn Gates, Wood Fold, Atherton High) Report P58, P59, P60
  • Housing Revenue Account tenants, via an increased boiler renewal and main programme allocation Report P67, 11.5
  • Bus users on Quality Bus Transit routes in Darlington Street, Ince Green Lane, Nel Pan Lane and Smiths Lane Report P66
  • Users of Robin Park Leisure Centre, Wigan Leisure Centre, and Haigh Hall Report P63, P64, P65
  • Treasury Management counterparties including clearing banks, building societies, money market funds, and local authorities Report P40, P41, P42, P43, P44

Timeline

  • 5 March 2025: Treasury Management Policy Statement for 2025/26 approved by Council Report 7.1
  • 1 April 2025: Start of 2025/26 financial year; PWLB loans of £386.352m held Report 5.4
  • 31 July 2025: Quarter 1 capital programme review submitted to Cabinet Report 11.1
  • 7 August 2025: Bank of England MPC cut Base Rate by 25 basis points to 4.00% Report 2.1
  • 11 August 2025: Latest interest rate forecast issued by MUFG Corporate Markets Report 3.3
  • 18 September 2025: MPC held Base Rate at 4.00% Report 2.1
  • 30 September 2025: Quarter 2 data cut-off; cash balances of £49.060m Report 8.1, 10.1, P15
  • 3 November 2025: Relevance Check dated Report P95
  • 18 November 2025: Cabinet decision to endorse Treasury Management position and updated Capital Programme to Council
  • 26 November 2025: Upcoming Autumn Budget noted as a risk to forecasts Report 2.2
  • Early Quarter 3 2025/26: Further borrowing anticipated from PWLB or market Report 5.7
  • 19 March 2026: Expected next Base Rate cut to 3.75% Report 2.2
  • 31 March 2026: Forecast year end cash balance of approximately £72.21m Report 10.1

Plain English for the jargon

  • Treasury Management: Management of the Council's cash flows, borrowing, lending, and debt.
  • Capital Financing Requirement (CFR): The amount of capital spending not yet financed from capital receipts, grants, or contributions from revenue, indicating underlying borrowing need.
  • Public Works Loan Board (PWLB): A government body that lends money to local authorities for capital projects.
  • SONIA: Sterling Overnight Index Average, a benchmark overnight interest rate used to compare investment performance.
  • Housing Revenue Account (HRA): The ringfenced account that records income and expenditure relating to council housing.
  • Credit Default Swap (CDS): A financial derivative used as a proxy for counterparty credit risk; higher values indicate higher risk.
  • CRSTS: City Region Sustainable Transport Settlement, government funding for transport infrastructure.
  • IFRS16: Accounting standard requiring most leases to be recognised on the balance sheet as assets and liabilities.
  • OLTL: Other Long Term Liabilities, including PFI and lease liabilities counted as part of the Council's debt.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item57

Resolved

The Cabinet endorses to Council for approval:- (1) the Treasury Management position; and (2) the adoption of the updated Capital Programme.
Word for word from the decision Wigan published for this meeting. Source: democracy.wigan.gov.uk

Follow this further

Built from Wigan's papers

What the report saysPro

Report to Cabinet

This is an open report Report to: Cabinet Council

Date of Meeting(s): Tuesday, 18 November 2025 Wednesday, 26 November 2025

Subject: Treasury Management and Capital Programme Half Yearly Review 25/26

Report of: Sarah Johnston, Director - Finance and Legal

Contact Officer: John McDonald ([email protected]), Jennifer Quinn ([email protected])

Cabinet Portfolio Holder and area: Councillor Nazia Rehman, Portfolio Holder for Finance, Resources and Transformation

Summary: The report provides an update on the half yearly position on the delegated Treasury Management Activity and Capital Programme as at the end of September 2025.

‘Progress with Unity’ Missions: As residents, businesses, public services and community organisations of this borough we have come together to deliver two key missions:

Mission 1: Create fair opportunities for all children, families, residents & businesses. “Together, we will break down the barriers that create financial, health, education and environmental inequalities in our borough.”

Mission 2: Make all our towns and neighbourhoods flourish for those who live and work in them. “Together, in genuine partnership with our residents and businesses, who know our community best, we will help each town and neighbourhood in the borough celebrate and maintain their identity whilst understanding and helping to achieve what is needed to thrive.”

Outline how this report supports our ‘Progress with Unity’ missions. Effective cash management is key to delivering all of the Council’s functions.

Wards Affected: All Recommendation(s): The Cabinet is requested to endorse to Council for approval:-

(1) the Treasury Management position; and (2) the adoption of the updated Capital Programme.

The Council is requested to approve:-

(1) the Treasury Management position; and (2) the adoption of the updated Capital Programme.

Implications:

What are the financial implications? Effective Treasury Management supports the delivery of the capital programme and manages investments and borrowing in the most optimal way for the revenue budget. The report requests adoption of the Capital Programme which is increased by £10.346m. The change is attached to a combination of grant funding, contributions and receipts and prudential borrowing.

Is budget release necessary (Capital Expenditure Only)? Yes

What are the legal implications? None

What are the staffing implications? None

Equality and Diversity Impact Assessment attached or not required because (please give reason). If not required, then a relevance check needs to be completed. An Equality and Diversity impact assessment is not required as no vulnerable groups are impacted upon by any decision within this report. Relevance Check is attached.

What are the property implications in terms of reduction, addition or change to the council’s asset base or its occupation? None

What are the Corporate Parenting Implications? None

Risks: Interest rates particularly for long term loans remain high and the timing of a fall is difficult to forecast. As such, the timing and term of borrowing is key to managing the revenue implications, with capital schemes profiled wherever possible to align with the optimum time to spend, and pipeline schemes revisited for viability. The Capital Programme contains an inherent risk that inflationary pressures particularly on construction cost affect the viability of schemes. There is also a risk on financing, specifically the realisation of capital receipts. Where schemes are funded from receipts, if these are not realised then plans will be revisited or spend reprofiled.

Sustainability/Environmental/Climate implications: The approach to borrowing is designed to ensure the sustainability of the revenue budget over the medium and long term.

Has the Assistant Director - Legal Governance and Elections (Janet Davies) confirmed that the recommendations within this report are lawful and comply with the Council’s Constitution? Yes

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme and Resourcing 2025/26: 2027/28Appendix 4 137 KB Download
PDF
Treasury Management and Capital Programme Half Yearly Review 25/26Report 251 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 21 attended
DT
Councillor David Trevor Molyneux MBEExecutive Leader, present
KC
Councillor Keith CunliffeDeputy Leader, present
KA
Councillor Kevin Anderson B.A (Hons)Committee Member, present
DA
Councillor Dane AndertonCommittee Member, present
PP
Councillor Paul PrescottCommittee Member, present
CR
Councillor Christopher ReadyCommittee Member, present
NR
Councillor Nazia RehmanCommittee Member, present
SC
Stuart CowleyOfficer, in attendance
JD
Janet DaviesOfficer, in attendance
LD
Lucy DownhamOfficer, in attendance
LG
Lewis GreenwoodOfficer, in attendance
SH
Sonia HalliwellOfficer, in attendance

All 21 on the meeting page

On this subject at Wigan

Search all
  1. Treasury Management and Capital Programme Half Yearly Review 25/26This decision
  2. Revenue and Treasury Management Monitoring - Quarter 1Decided
  3. Treasury Management Annual Review 2025/26Decided
  4. Treasury Management Annual Review 2025/26Approved
  5. Treasury Management Annual Review 2025/26Approved
  6. Treasury Management and Capital Programme Half Yearly Review 25/26Approved

More from Wigan Cabinet

All decisions
MeetingDecisionOutcome
24 Sep 2026 Exclusion of the PublicThat the public is excluded from the meeting when the Cabinet discusses the following item for the reason set out bel... Decided Open
24 Sep 2026 Medium Term Financial Plan 2027/28 - 2029/30The Cabinet:- (1) notes the updated Medium-Term Financial Plan forecast; (2) notes the forecast budget gap for 2027/2... Approved Open
24 Sep 2026 Annual Standards Report 2025/26The Cabinet approves the . Approved Open
24 Sep 2026 Task and Finish (Cabinet Response) - CLA and PCLA Support in SchoolsThe Cabinet:- (1) notes the Director – Children and Family Services’ response to the Task and Finish Outcome Report; ... Approved Open
27 Aug 2026 Exclusion of the PublicThat the public is excluded from the meeting when the Cabinet discusses the following item for the reason set out bel... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies