Treasury Management and Capital Programme Half Yearly Review 25/26

Approved Committee 2 papers

AI summaryWigan Council approved the half year treasury management position and an updated capital programme of £148.196m for 2025/26, with a net £10.346m increase funded mainly by grants and prudential borrowing.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedTreasury position and capital programme adopted
Money£148.196m capital programme 2025/26Revised down by £39.204m, net £10.346m uplift
What happens nextEarly quarter 3 borrowingShort term loans, then longer term refinancing
Who it affectsCouncil finances and capital schemesSchools, housing, leisure, transport, civic centre

What was decided

The Council approved the Treasury Management position for the first half of 2025/26. Report 1.1

The Council adopted the updated Capital Programme, including the £10.346m of net changes set out in the quarter 2 review. Report 11.2, 11.3

The motion was carried on a recorded vote.

Why

The half year review of Treasury Management delegated powers and the capital programme is a routine reporting requirement, and the quarter 2 position has been set out for approval. Report 1.1, 11.1

Officers reported that the Council operated within its prudential and treasury indicators during the quarter and that no compliance difficulties are expected. Report 9.2, 9.3

Interest rates and price inflation continue to pressure the programme, and the report sets out the response. Report 12.1, 12.2

What happens next

Further external borrowing is expected early in quarter 3, taking a minimal short term amount first and refinancing with longer term loans once rates fall. Report 5.7

Officers will mitigate interest rate and inflation risks through borrowing strategy, rephasing, capital strategy work, and financing options. Report P71, 12.2

Cash balances are forecast to reach around £72.21m by 31 March 2026 and will be monitored throughout the year. Report 10.1, 10.2

The money

  • £148.196m Revised 2025/26 capital programme allocation Report 11.3
  • £10.346m Net increase to the capital programme at quarter 2 Report 11.2
  • £39.204m Reduction from the quarter 1 allocation due to slippage reprofiling Report 11.3
  • £40.618m Actual capital spend from April to September 2025 Report 11.4
  • £671.704m Capital Financing Requirement for 2025/26 Report 5.1
  • £459.533m Council external borrowings at 30 September 2025
  • £49.060m Cash and investments balance at 30 September 2025 Report 8.1, 10.1
  • £15.626m Total PWLB interest payable in 2025/26 at quarter 2 Report 5.4, 5.5

Options considered

  • Chosen: Approve the Treasury Management position and the updated Capital Programme. Council has operated within prudential indicators and officers recommend adoption Report 9.2, 9.3

Implications

  • Financial: Base Rate held at 4.00% with further cuts forecast, but 10 year gilt yields remain over 4.70% and PWLB rates stay elevated, keeping borrowing costs under pressure. Report 2.1, 2.2, 2.4, P12
  • Financial: Average investment return of 4.38% slightly outperformed the 90 day SONIA rate of 4.34% during the quarter. Report 8.2
  • Risk: Further external borrowing is expected early in quarter 3 because of the gap between the CFR of £671.704m and current external debt of £459.533m. Report 5.7
  • Staffing: No staff impact is identified in the relevance check. Report P97, P98, P99

Who and where

  • Wigan Council taxpayers, through ongoing capital investment funded by grants, contributions, and borrowing Report P52, 11.5
  • Pupils at Wood Fold Primary and Atherton High, benefiting from a 1FE enlargement and a SEND modular building Report P59, P60
  • Housing Revenue Account tenants, with a £3.782m net increase to the housing capital programme including boiler renewals Report P67
  • Bus passengers, through four CRSTS Quality Bus Transit schemes on Darlington Street, Ince Green Lane, Nel Pan Lane, and Smiths Lane Report P66
  • Leisure centre users at Robin Park and Wigan Leisure Centre, through gym, studio, and café expansion Report P63, P64

Timeline

  • 7th August 2025: Bank of England MPC cut Base Rate by 25 basis points to 4.00% Report 2.1
  • 18th September 2025: Bank of England MPC held Base Rate at 4.00% Report 2.1
  • 30th September 2025: Cash and investments stood at £49.060m and £40.618m of capital spend had been incurred in the half year Report 8.1, 11.4
  • 26th November 2025: Council meeting and UK Autumn Budget, both flagged as influences on interest rate forecasts Report 2.2
  • Early quarter 3 2025/26: Further external borrowing is expected to be taken Report 5.7
  • 19th March 2026: Forecast next Base Rate decrease to 3.75% Report 2.2
  • 31st March 2026: Forecast cash balance of approximately £72.21m Report 10.1

Plain English for the jargon

  • CFR: Capital Financing Requirement, the Council's underlying need to borrow for capital purposes.
  • PWLB: Public Works Loan Board, a government body that lends to local authorities.
  • MPC: Monetary Policy Committee of the Bank of England, which sets the Base Rate.
  • SONIA: Sterling Overnight Index Average Rate, a benchmark for short term sterling interest.
  • HRA: Housing Revenue Account, the ringfenced account for council housing.
  • IFRS16: Accounting standard requiring most leases to be shown on the balance sheet as debt.
  • MMF: Money Market Fund, a pooled short term cash investment.
  • CRSTS: City Region Sustainable Transport Settlement, a transport funding programme.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item32(a)

Resolved

The Council approves:- (1) the Treasury Management position; and (2) the adoption of the updated Capital Programme. (A named vote is attached) Recorded Vote Title Type Recorded Vote text Result Treasury Management and Capital Programme Half Yearly Review 2025/26 Motion Carried View Recorded Vote for this item
Word for word from the decision Wigan published for this meeting. Source: democracy.wigan.gov.uk

Follow this further

Built from Wigan's papers

What the report saysPro

Report to Council

This is an open report Report to: Cabinet Council

Date of Meeting(s): Tuesday, 18 November 2025 Wednesday, 26 November 2025

Subject: Treasury Management and Capital Programme Half Yearly Review 25/26

Report of: Sarah Johnston, Director - Finance and Legal

Contact Officer: John McDonald ([email protected]), Jennifer Quinn ([email protected])

Cabinet Portfolio Holder and area: Councillor Nazia Rehman, Portfolio Holder for Finance, Resources and Transformation

Summary: The report provides an update on the half yearly position on the delegated Treasury Management Activity and Capital Programme as at the end of September 2025.

‘Progress with Unity’ Missions: As residents, businesses, public services and community organisations of this borough we have come together to deliver two key missions:

Mission 1: Create fair opportunities for all children, families, residents & businesses. “Together, we will break down the barriers that create financial, health, education and environmental inequalities in our borough.”

Mission 2: Make all our towns and neighbourhoods flourish for those who live and work in them. “Together, in genuine partnership with our residents and businesses, who know our community best, we will help each town and neighbourhood in the borough celebrate and maintain their identity whilst understanding and helping to achieve what is needed to thrive.”

Outline how this report supports our ‘Progress with Unity’ missions. Effective cash management is key to delivering all of the Council’s functions.

Wards Affected: All Recommendation(s): The Cabinet is requested to endorse to Council for approval:-

(1) the Treasury Management position; and (2) the adoption of the updated Capital Programme.

The Council is requested to approve:-

(1) the Treasury Management position; and (2) the adoption of the updated Capital Programme.

Implications:

What are the financial implications? Effective Treasury Management supports the delivery of the capital programme and manages investments and borrowing in the most optimal way for the revenue budget. The report requests adoption of the Capital Programme which is increased by £10.346m. The change is attached to a combination of grant funding, contributions and receipts and prudential borrowing.

Is budget release necessary (Capital Expenditure Only)? Yes

What are the legal implications? None

What are the staffing implications? None

Equality and Diversity Impact Assessment attached or not required because (please give reason). If not required, then a relevance check needs to be completed. An Equality and Diversity impact assessment is not required as no vulnerable groups are impacted upon by any decision within this report. Relevance Check is attached.

What are the property implications in terms of reduction, addition or change to the council’s asset base or its occupation? None

What are the Corporate Parenting Implications? None

Risks: Interest rates particularly for long term loans remain high and the timing of a fall is difficult to forecast. As such, the timing and term of borrowing is key to managing the revenue implications, with capital schemes profiled wherever possible to align with the optimum time to spend, and pipeline schemes revisited for viability. The Capital Programme contains an inherent risk that inflationary pressures particularly on construction cost affect the viability of schemes. There is also a risk on financing, specifically the realisation of capital receipts. Where schemes are funded from receipts, if these are not realised then plans will be revisited or spend reprofiled.

Sustainability/Environmental/Climate implications: The approach to borrowing is designed to ensure the sustainability of the revenue budget over the medium and long term.

Has the Assistant Director - Legal Governance and Elections (Janet Davies) confirmed that the recommendations within this report are lawful and comply with the Council’s Constitution? Yes

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme and Resourcing 2025/26: 2027/28 (a)Appendix 4 137 KB Download
PDF
Treasury Management and Capital Programme Half Yearly Review 25/26Report 251 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

61 of 79 attended
JB
Councillor Jenny BullenMayor, present
AC
Councillor Anne CollinsDeputy Mayor, present
KA
Councillor Kevin Anderson B.A (Hons)Committee Member, present
DA
Councillor Dane AndertonCommittee Member, present
PJ
Councillor Paul John BlayCommittee Member, present
BB
Councillor Bob BrierleyCommittee Member, present
SB
Councillor Samantha BrownCommittee Member, present
AB
Councillor Andrew BullenCommittee Member, present
MC
Councillor Mary CallaghanCommittee Member, present
BC
Councillor Barbara CarenCommittee Member, present
JC
Councillor Jim ChurtonCommittee Member, present
PA
Councillor Paul Anthony CollinsCommittee Member, present

All 79 on the meeting page

On this subject at Wigan

Search all
  1. Treasury Management and Capital Programme Half Yearly Review 25/26This decision
  2. Revenue and Treasury Management Monitoring - Quarter 1Decided
  3. Treasury Management Annual Review 2025/26Decided
  4. Treasury Management Annual Review 2025/26Approved
  5. Treasury Management Annual Review 2025/26Approved
  6. Treasury Management and Capital Programme Half Yearly Review 25/26Approved

More from Wigan Council

All decisions
MeetingDecisionOutcome
23 Sep 2026 Appointment of Honorary Aldermen of the BoroughThe Council:- (1) approves the recommendation of the Honorary Alderman Nominations Committee, to confer the title of ... Approved Open
23 Sep 2026 Appointment of Honorary Freeman of the BoroughThe Council agrees to hold a special meeting of the Council on an appropriate date during the 2026/27 municipal year,... Agreed Open
23 Sep 2026 Capital Programme Monitoring - Quarter 1The Council approves the adoption of the updated Capital Programme. Approved Open
23 Sep 2026 Anti-Social Behaviour PolicyThe Council:- (1) approves the refreshed (2026); (2) notes the introduction of the four step ASB Resolution Model and... Approved Open
22 Jul 2026 Appointment of the Monitoring OfficerThe Council notes the appointment of Nina Ellement into the Monitoring Officer role. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies