That (1) the terms of the sale as set out in the report be noted; (2) Cabinet authorises officers to accept a guaranteed minimum figure or any other higher figure achieved through negotiation with the developer to reach the final figure depending on the affordable homes outcome; (3) it be noted that as part of the Wirral Plan the proposal in the report supports the pledges to ensure to Council makes better use of its assets and to meet the Council’s target of 3,500 new homes. Councillors Bernie Mooney and Stuart Whittingham left the meeting whilst the next item of business was considered.
Word for word from the decision Wirral published for this meeting.Source: democracy.wirral.gov.uk
SALE OF SITE OF THE FORMER ACRE LANE PROFESSIONAL EXCELLENCE CENTRE
Councillor George Davies, Cabinet Member – Housing and Community Safety and Deputy Leader of the Council, said:
‘The sale of the Acre Lane site demonstrates our commitment to the Wirral Plan. Rather than an under-used, expensive council office building, the Acre Lane site will now soon contain new, high-quality homes for Wirral residents.
“This supports our Pledge to deliver more housing, and it supports the council’s financial position through generating significant income from the sale of the site.’
REPORT SUMMARY
The purpose of this report is to advise Members of the terms for disposal of the site of the former Acre Lane Professional Excellence Centre, Eastham.
As part of the Council’s five year plan, the proposals in the report support the following pledges contained in the plan:
- Council making better use of its assets. - To build 3,500 new homes
The sale of this asset affects the Eastham Ward.
The report is a key decision due to the financial implications.
Details of the minimum offer are appended. This appendix is exempt from publication under Schedule 12A of the Local Government Act 1972 due to the commercial sensitivities of that information.
1 RECOMMENDATION/S
1. That the terms of the sale as set out in the report be noted.
2. That Cabinet authorises officers to accept a guaranteed minimum figure or any other higher figure achieved through negotiation with the developer to reach the final figure depending on the affordable homes outcome.
3. That it be noted that as part of the Wirral Plan the proposal in this report supports the pledges to ensure the Council makes better use of its assets and to meet the Council’s target of 3,500 new homes.
2 SUPPORTING INFORMATION
1.0REASON/S FOR RECOMMENDATION/S
1.1To enable the sale of the Council’s interest to proceed.
2.0OTHER OPTIONS CONSIDERED
2.1The proposed disposal follows the instruction of Cabinet and so no other options have been considered at this stage.
3.0BACKGROUND INFORMATION
3.1Cabinet at its meeting of 7 November 2013 declared the Acre Lane Professional Excellence Centre a surplus asset and resolved that the property should be sold in accordance with section 123 of the Local Government Act 1972. Since then, all activities at the centre were relocated to alternative Council buildings and, once vacant, the building was demolished earlier this year.
3.2Lambert Smith Hampton (LSH), the Council’s appointed property consultants, has marketed the site on the Council’s behalf. The marketing exercise resulted initially in 7 bids from housing developers. LSH compared these bids on a ‘green field’ basis, which assumes that the site is fully developable and that no special conditions or abnormal ground conditions exist and allows all bids to be evaluated on the same basis. An exclusivity agreement was entered into which enabled them to undertake further investigations and arrive at a net figure for the land.
3.3Morris Homes has finished its investigations and has provided a final net offer. The offer is based on a scheme of 219 residential units (this may vary for the purposes of the sale contract) and reflects deductions for abnormal costs associated with matters such as ground conditions, sewerage capacity and loss of developable area. These deductions have been assessed by LSH with the assistance of an appointed Quantity Surveyor and are considered to be reasonable.
3.4In order to meet the requirements of S123 of the Local government act 1972 the net sale price offered is considered to be the best price obtainable through the negotiations. The offer is based on Morris Homes entering a contract to purchase the site, which is conditional on them securing full planning permission. The disposal will only complete once planning consent has been secured.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring Quarter 1 2020/21That (1) the Cabinet recommends to the Council the approval of additional funding for the schemes referred to in para...
Financial Monitoring Outturn 2019-20That (1) Revenue (a) it be noted that the gross expenditure has been balanced to gross income with the appropriate al...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.