Capital Monitoring 2016/17 (Quarter 2)

Decided Executive 1 paper

Cabinet decided this item on Thursday 8 December 2016. Below is the council's own wording, with the papers it was decided on.

Item69

Resolved

That the Cabinet (1) notes the spend to date at Month 6 of £10.6 million, with 50% of the financial year ... view the full minutes text for item 69.
Word for word from the decision Wirral published for this meeting. Source: democracy.wirral.gov.uk

Follow this further

Built from Wirral's papers

What the report saysPro

Report to Cabinet

Recommendations

1. Note the spend to date at Month 6 of £10.6 million, with 50% of the financial year having elapsed;

2. Agree and refer to Council the revised Capital Programme of £38.1 million (Table 1) which also includes a number of recommended virements as outlined in paragraph 3.5 of the report. SUPPORTING INFORMATION

Reasons for recommendations

1.1Regular monitoring and reporting of the Capital Programme enables decisions to be taken more efficiently and effectively, which may produce revenue benefits and will improve the financial control of the Programme.

2.0OTHER OPTIONS CONSIDERED

2.1No other options have been considered.

3.0BACKGROUND INFORMATION

OVERALL POSITION AT END OF SEPTEMBER 2016

3.1The actual spend against the Capital Programme is summarised in Table 1.

Chart 1: Capital Programme spend below line of best fit

Capital Programme 2016/17

70 60 50 40 £m

Re vise d Prog ramme Actua l spen d

30 20 10 0 P0 P3 P6 P9 P12

Months

ORIGINAL AND PROPOSED CAPITAL PROGRAMME FOR 2016/17

3.2The Programme for 2016/17 is subject to change. Presently it reflects;

£000 Programme agreed by Cabinet on 22 February 2016 48,107 Year end re-profiling 6,364 Additional grant funding 1,750 Variations identified March 2016 2,750 Variations identified since June 2016 (see Table 2) -20,885 Revised 2016/17 Programme 38,086 Table 1: Capital Programme 2016/17 at 30 September 2016

Capital Revisions Revised Actual Strategy Since Capital Spend Budget Programme Sept 2016 £000 £000 £000 £000 Transformation Resources 7,863 1,237 9,100 2,634 Families – Children 9,185 -282 8,903 3,133 Families – Adults 10,255 -7,706 2,549 164 Families – Sport & Rec 2,871 -1,111 1,760 570 R&E– Env & Regulation 10,016 844 10,860 2,881 R&E– Hsg & Comm Safety 7,317 -2,945 4,372 1,106 R& E – Regeneration 600 -58 542 90 Total expenditure 48,107 -10,021 38,086 10,578

3.3PROGRESS TO DATE

3.3.1 Transformation and Resources

The investment in IT is focussed on migrating all servers and applications to the core domain and, where possible, upgrading applications to the latest version; upgrading all Windows Server operating systems to a supported operating system and reducing the server footprint by virtualising all servers where possible.

Works to increase building occupancy have mainly focused on Wallasey Town Hall, Moreton Municipal, and Solar Campus. These schemes enable the existing buildings to operate more efficiently with a higher level of occupancy.

Works continue with improvements to Parks Depots with the service road to Warren Farm Depot having been re-surfaced, the vehicle entrance widened, and new security cameras installed. The main site accommodation is being refurbished with a new heating system and new double glazed windows. Improvements to staff welfare areas, kitchen and toilets are being undertaken.

3.3.2 Families and Wellbeing - Children

A new classroom has been constructed at Elleray Park School to meet capacity needs. This includes improved external accessibility and play areas.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Monitoring 2016/17 (Quarter 2)Report 134 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 9 attended
PD
Councillor Phil DaviesChair, present
GD
Councillor George DaviesCommittee Member, present
CJ
Councillor Chris JonesCommittee Member, present
AM
Councillor Ann McLachlanCommittee Member, present
BM
Councillor Bernie MooneyCommittee Member, present
MP
Councillor Matthew PatrickCommittee Member, present
TS
Councillor Tony SmithCommittee Member, present
SW
Councillor Stuart WhittinghamCommittee Member, present
JW
Councillor Janette WilliamsonCommittee Member, present

On this subject at Wirral

Search all
  1. Capital Monitoring 2016/17 (Quarter 2)This decision
  2. Capital Monitoring Quarter 1 (2026/27)Approved
  3. Capital Monitoring Quarter 3 2025/26Approved
  4. Capital Monitoring Quarter 3 2025/26Approved
  5. 2025-26 capital monitoring quarter 2Approved
  6. 2025-26 Capital Monitoring Quarter 2Approved

More from Wirral Cabinet

All decisions
MeetingDecisionOutcome
27 Jul 2020 MinutesThat the Minutes of the meetings of the Cabinet held on 17 and 24 February 2020 be confirmed as a correct record. Decided Open
27 Jul 2020 Executive Key Decisions Taken Under Delegated PowersThat the following Key Decisions taken under delegated authority for the period 21 February 2020 to the date of publi... Noted Open
27 Jul 2020 Capital Monitoring Quarter 1 2020/21That (1) the Cabinet recommends to the Council the approval of additional funding for the schemes referred to in para... Approved Open
27 Jul 2020 Financial Monitoring Outturn 2019-20That (1) Revenue (a) it be noted that the gross expenditure has been balanced to gross income with the appropriate al... Noted Open
27 Jul 2020 Treasury Management Annual Report 2019/20That (1) the 2019/20 Treasury Management Annual Report be agreed and recommended to the Council for approval at its m... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies