Resolved
Resolved Forum noted the report
Wirral Early Years and Schools Forum noted this item on Wednesday 18 January 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved Forum noted the report
This paper provides a brief update on the procurement of electricity and natural gas on behalf of Schools and describes changes for the 2017/18 financial year.
2. PURCHASING OVERVIEW
The energy supply arrangement many Schools are part of procures Electricity and Natural Gas using a Managed Service provided by Crown Commercial Service (CCS). CCS, as a trading fund and an executive agency of the Cabinet Office, delivers commercial savings for central government and the wider public sector. It is the largest not-for-profit energy buying consortium in the UK which enables it to exert much greater pressure on suppliers than the Council could alone. This managed service type of arrangement was identified as best practice by the Pan- Government Energy Project. The arrangement is compliant with Corporate Procurement and EU Regulations.
The purchasing arrangement includes PFI schools and is available to Academy Schools. A total of 118 schools listed in the Primary and Secondary Education Booklets are part of the managed service. 8 Schools make their own arrangements. The total projected expenditure for all schools in the managed service is approximately £3.28 million.
Electricity and Natural Gas is currently purchased on the wholesale markets on Wirral’s behalf by CCS over the six months prior to the start of the supply year. The individual energy suppliers (contracted by CCS under separate framework agreements through an OJEU compliant process) then provide a team to supply and administer a particular contract.
Energy prices change extremely quickly and the risks involved in selecting the right day to switch are huge. Purchasing the energy over a six month period, allows the CCS traders to purchase parts of our total requirement when the markets are low and to avoid periods of high prices.
It should be noted that there are individual tariff structures within the Electricity and Gas contracts are based on operational profiles, transportation and metering costs, meaning that each point of supply is priced individually.
3. BENEFITS OF THIS APPROACH
In 2014/15 the CCS purchasing baskets we were part of were 150 times larger than our total portfolio which includes Schools as well as Council buildings. Aggregation is used as leverage, providing access to the generators. Generators want to sell outputs in a small number of large portions rather than having to make an increased number of smaller sales. The market price achieved reflects this preference. A small basket reduces market leverage and increases the risk of higher prices.
It has previously been identified that the savings identified by approved Government Benefits Methodologies show that the Wirral Portfolio would have cost approximately 10.4% more than actual spend if the current arrangement with CCS had not been in place.
CCS provides a team of expert traders whose activities are constantly monitored by a separate risk management team and are subject to regular review by central Government. Delegating purchasing to expert traders spreads the risks of purchasing energy on a spot price basis and the final prices we pay are built up from the energy purchased over a six-monthly period.
This proposal supports Pledge Fourteen of the Wirral 2020 Plan by enhancing the Council’s ability to keep running costs associated with use of gas and electricity in council buildings to a minimum whilst adhering to purchasing rules.
4. MARKET TRENDS
Up to April 2016 the price of energy had been reducing. This trend has reversed since then. Although we are, to an extent, insulated from market volatility, a sustained rise in prices will eventually work its way through to the prices we pay.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Energy UpdateReport | 72 KB | DownloadRead as text |
Follow Wirral Early Years and Schools Forum at Wirral and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jun 2026 | Minutes of the Meeting Held on 20 January 2026Resolved – That the minutes of the meeting held on 20 January 2026 be approved as an accurate record. | Approved | Open |
| 16 Jun 2026 | MyHappyMind Funding RequestResolved (unanimous) – That the Forum agrees to contribute funding from the High Needs Block to a joint commission to... | Agreed | Open |
| 16 Jun 2026 | High Needs Funding Subgroup UpdateResolved – That the Forum notes the contents of the report. | Decided | Open |
| 16 Jun 2026 | Early years Working Group UpdateResolved (unanimous) – That the Wirral Early Years and Schools Forum notes the report and approves the recommendation... | Approved | Open |
| 16 Jun 2026 | School Balances UpdateResolved – That 1. The Forum notes the report, and; 2. Notes that Schools’ balances continue to be monitored. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.