CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Wirral Borough Council
Wirral Early Years and Schools Forum, Wednesday 18 January 2017

PFI Support

Noted Committee 1 paper

Wirral Early Years and Schools Forum noted this item on Wednesday 18 January 2017. Below is the council's own wording, with the papers it was decided on.

Item465

Resolved

Resolved Forum noted the report
Word for word from the decision Wirral published for this meeting. Source: democracy.wirral.gov.uk

Follow this further

Built from Wirral's papers

What the report saysPro

Report to Wirral Early Years and Schools Forum

WIRRAL COUNCIL

WIRRAL SCHOOLS FORUM 18TH JANUARY 2017

REPORT OF THE DIRECTOR BUSINESS SERVICES

Private Finance Initiative Support Costs

EXECUTIVE SUMMARY This report describes the work of the PFI team within Asset Management and the support provided to monitor the PFI contract on behalf of the Council and Schools.

BACKGROUND The Wirral Schools PFI project agreement was signed by the Council, school governing bodies, and the PFI contractor in March 2001. The scheme involved the rebuild / refurbishment of one primary and eight secondary schools in Wirral. Variations were subsequently agreed for the construction of two City Learning Centres (CLC’s) located on PFI sites.

The contract was originally for 25 years to July 2029, but in September 2004 it was extended by 2 years and will expire in July 2031. Construction works were completed in August 2006. The PFI contract also provides for facilities management (FM) support services in schools. These services include building and grounds maintenance, catering, cleaning and caretaking, security, waste, minibuses, utilities and telecommunications.

An annual sum is paid to the PFI contractor Wirral Schools Services Ltd. for the cost of PFI. This “unitary charge” represents the repayment of capital costs for rebuilding / refurbishing the schools and a payment for the cost of providing facilities management services. The contract makes provision for the total costs to increase each year by the December Retail Prices Index, less 10% of that RPI.

In 2016 -17 the annual PFI contract cost (excluding CLC’s) will be £12.3m. PFI is the Council’s biggest contract and is funded by: £m PFI grant 5.5 Individual school contributions 3.9 Schools Budget (central) 2.3 Council Contribution 0.6 Total 12.3

PFI SUPPORT The role of the PFI team is to manage the contract by offering day to day support on all contractual aspects of the various legal agreements which define the scheme. In addition to this the PFI Team offer services which are tailored to accommodate the obligations of the PFI Scheme including:

Finance To verify and agree contract payments –on a monthly basis To collect contributions from schools. Checking financial data to ensure accuracy Forecasting future budget requirements for the PFI scheme overall

Contractual To ensure contract performance and compliance in terms of service delivery against service standards and Project Agreement schedules. This includes change orders, Benchmarking / Value for Money Testing, Summer works, Planned Preventative Maintenance, Life Cycle Works, Utility targets and reconciliation, Catering and profit sharing, management of Loose Furniture Budgets (FF&E) and Service Provider Operational Reports

There is a detailed service specification for PFI support that has been developed with the 9 schools this includes: - Regular meetings with the individual schools at each site with the, PFI Authority Representative , PFI provider, Facilities Management Company and Catering Services Provider - Regular Contract wide meetings between the Authority, the PFI Provider, Facilities Management Company and Catering Company to ensure the PFI partners meet the requirements of the Contract, both on a day to day and strategic level - Monthly dissemination of utility data and forecast of financial implications for each individual school - Regular discussions re performance and financial deductions

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
PFI SupportReport 65 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

16 of 45 attended
NL
Nicola LightwingCommittee Member, present
TT
Tony TaylorCommittee Member, apologies
AB
Andre BairdCommittee Member, expected
JG
Jane GoalenCommittee Member, present
DM
Deborah MarchantCommittee Member, present
JB
Jill BillingeCommittee Member, present
TQ
Tom QuinnCommittee Member, apologies
MB
Mary BulmerCommittee Member, present
LA
Lisa AylingCommittee Member, present
NP
Nicky PranceCommittee Member, present
JP
Jill PearsonCommittee Member, apologies, sent representative
EC
Elaine CoganCommittee Member, apologies

All 45 on the meeting page

More from Wirral Wirral Early Years and Schools Forum

All decisions
MeetingDecisionOutcome
16 Jun 2026 Minutes of the Meeting Held on 20 January 2026Resolved – That the minutes of the meeting held on 20 January 2026 be approved as an accurate record. Approved Open
16 Jun 2026 MyHappyMind Funding RequestResolved (unanimous) – That the Forum agrees to contribute funding from the High Needs Block to a joint commission to... Agreed Open
16 Jun 2026 High Needs Funding Subgroup UpdateResolved – That the Forum notes the contents of the report. Decided Open
16 Jun 2026 Early years Working Group UpdateResolved (unanimous) – That the Wirral Early Years and Schools Forum notes the report and approves the recommendation... Approved Open
16 Jun 2026 School Balances UpdateResolved – That 1. The Forum notes the report, and; 2. Notes that Schools’ balances continue to be monitored. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies