That (1) the spend at Quarter 2 of £16.3 million be noted; (2) additional funding for the schemes referred to in paragraph 3.9 of the report and below be noted: · Hoylake Golf Depot (3110,000) · Landican Crematoria (£280,000) · Williamson Art Gallery creation of an online catalogue (£150,000) · Leasowe Leisure Centre Outdoor 3G Pitches (£323,000) · Access Wirral (£250,000) · Early Voluntary Retirement/Voluntary Severance (£2,000,000) (3) Council be recommended to approve the revised Capital Programme of £60.9 million for 2018/19 as set out in Table 1 of the report and below: £000 Programme agreed by Cabinet on 16 July 2018 86,391 Re-profiling (26,869) Additional requirements 2,989 Reduced requirements (1,563 ) Revised 2018/19 Programme 60,948 Table 1: Capital Programme 2018/19 at 30 September 2018 Capital Strategy June September Actual Spend Sept 2018 £000 £000 £000 £000 Adult Care & Health 7,912 8,543 3,468 381 Business Management 4,990 3,729 5,489 777 Children’s Services 19,099 20,852 18,341 7,542 Delivery Services 25,775 34,280 22,724 7,435 Economic & Housing Growth 16,785 18,987 10,926 157 Total expenditure 74,561 86,391 60,948 16,292 .
Word for word from the decision Wirral published for this meeting.Source: democracy.wirral.gov.uk
1 To note the spend at Quarter 2 of £16.3 million.
2 To approve additional funding for the schemes referred to in paragraph 3.9.
3 To recommend that Council approves the revised Capital Programme of £60.9 million (Table 1) for 2018/19. SUPPORTING INFORMATION
Reasons for recommendations
1.1Regular monitoring and reporting of the Capital Programme enables decisions to be taken faster which may produce revenue benefits and will improve financial control of the Programme.
2.0OTHER OPTIONS CONSIDERED
2.1No other options have been considered.
3.0BACKGROUND INFORMATION
PROPOSED CAPITAL PROGRAMME FOR 2018/19
3.1The Programme for 2018/19 is subject to change. It presently reflects the following changes which are then detailed in Tables 1 and 2.
£000 Programme agreed by Cabinet on 16 July 2018 86,391 Re-profiling (26,869) Additional requirements 2,989 Reduced requirements (1,563) Revised 2018/19 Programme 60,948
Table 1: Capital Programme 2018/19 at 30 September 2018
Capital June September Actual Strategy Spend Sept 2018 £000 £000 £000 £000 Adult Care & Health 7,912 8,543 3,468 381 Business Management 4,990 3,729 5,489 777 Childrens Services 19,099 20,852 18,341 7,542 Delivery Services 25,775 34,280 22,724 7,435 Economic & Housing 16,785 18,987 10,926 157 Growth Total expenditure 74,561 86,391 60,948 16,292
. Table 2: Significant Variations (> £0.5m) to the 2018/19 Programme identified since June
Scheme £000 Adult Care & Health Learning disability extra care housing - re-profiling (3,000) Extra care housing - re-profiling (1,345) Community Intermediate Care - re-profiling (500)
Business Management Digital corporate storage - re-profiling (500)
Childrens Services Schools condition and modernisation - re-profiling (543) School remodelling/primary places - re-profiling (1,642)
Delivery Services Bridges - re-profiling (551) Dock bridges – re-profiling (552) Transport for Growth - re-profiling (515) Street lighting column upgrade/replacement and LED replacement - re-profiling (2,790) West Kirby flood alleviation - re-profiling (2,335) Clearance - reduced requirement (767) Clearance - re-profiling (350) Housing infrastructure fund - re-profiling (1,000) Housing Zones Marginal Viability Fund - re-profiling (979)
Economic & Housing Growth Investment in properties - re-profiling (1,856) Wirral Waters Investment Fund - re-profiling (6,205)
Total (25,430)
3.3Schemes will be subject to an ongoing review to ensure that a deliverable Programme is in place, that they are compatible with the 2020 Vision and to try and identify any savings. Current progress on the more significant areas of spend to date is provided in the following sections.
3.4Adult Care & Health
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring Quarter 1 2020/21That (1) the Cabinet recommends to the Council the approval of additional funding for the schemes referred to in para...
Financial Monitoring Outturn 2019-20That (1) Revenue (a) it be noted that the gross expenditure has been balanced to gross income with the appropriate al...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.