Strategic Applications Sub Committee, Thursday 23 October 2025

APP/25/00792 - Mosslands School, Mosslands Drive, Wallasey Village, Wallasey, Wirral, CH45 8PJ - Application for Demolition of existing school and erection of new Mosslands School .

Approved Committee 1 paper

AI summaryWirral Strategic Applications Sub-Committee unanimously approves demolition of Mosslands School and construction of a new 1,500-pupil school, despite partial loss of Wallacre Local Green Space, with £100,000 council funding for nearby Wallacre Park.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedSubject to conditions, authorised by Chief Planner
Money£100,000Council funding for Wallacre Park improvements
What happens next3-year permissionPractical completion of whole development set for Summer 2028
Who it affectsMosslands School and WallacreApproximately 7.6 hectare site in Wallasey Village

What was decided

The committee approved the application for demolition of the existing school and erection of a new Mosslands School, including a 3-storey main building, two sports halls, playing fields, car park and cycle parking, plus replacement playing fields and pavilion at the Wallacre recreation ground. Report P47, P48

Approval is a departure from the Wirral Local Plan due to a partial loss of the Wallacre Local Green Space of approximately 40%, but officers concluded very special circumstances exist because benefits and mitigation outweigh the harm. Report P76, P119, P123, P175

Why

The existing school is considered unfit for purpose, beyond economic repair in parts, energy inefficient, and partly in Flood Zone 3. The new school would accommodate up to 1,500 pupils including a sixth form, compared with about 1,100 currently, and supports the Government's School Rebuilding Programme. Report P169, P170, P171

Sport England accepted that significant qualitative improvements to pitches, drainage and the new pavilion, together with a Community Use Agreement securing community access, outweigh the approximately 49% reduction in Wallacre playing field area. Report P90, P97, P98, P111

Officers also weighed benefits including 235 replacement trees (above the 172 required), biodiversity net gain over 30 years, addressing flood risk and drainage, and £100,000 of council funding for Wallacre Park, which is unlikely to come forward otherwise. Report P152, P154, P162

What happens next

Conditions require final versions of a Community Use Agreement, Maintenance and Management Plans for school and Wallacre pitches, materials details, and a pre-commencement condition on alternative sports provision during construction. Report P99, P114, P160

The development must begin within 3 years and be carried out in accordance with the approved plans listed in the decision.

The new school is expected to become fully operational at the end of Phase 1 (Summer 2027), with full practical completion of the school and Wallacre works set for Summer 2028. Report P52, P54

The money

  • £100,000 Council funding primarily for improved children's play facilities and other improvements to Wallacre Park Report P154, P162

Options considered

  • Chosen: Approve subject to conditions (officer recommendation). Very special circumstances demonstrated; benefits and mitigation outweigh harm to Local Green Space; Sport England accepts qualitative improvements outweigh loss of playing field land Report P175, P177
  • Rejected: Refuse. Not specifically addressed in report; officers found benefits and very special circumstances sufficient Report P175, P177

Implications

  • Legal: Application is a departure from the Wirral Local Plan; NPPF Green Belt policies applied to Local Green Space and 'very special circumstances' test used to justify approval. Report P76, P123, P127, P128
  • Financial: Council has agreed £100,000 of funding for Wallacre Park improvements, primarily for children's play facilities, secured through Education Department correspondence. Report P154
  • Equalities: Replacement fitness suite at ground-floor level will be DDA compliant, replacing a first-floor facility that was not; new school will include 3 SEMH classrooms with separate external areas. Report P104, P170
  • Climate: Proposal includes ground source heating, energy efficiency improvements, exceeds 10% Biodiversity Net Gain over 30 years, and addresses flood risk with raised ground levels and drainage to make the site resilient to climate change. Report P52, P143, P161
  • Risk: Construction will close the Wallacre to the public for around 36 months; alternative football pitches have been arranged for community teams for 2025/26 and beyond. Report P113, P136, P165
  • Other: Loss of approximately 40% of Wallacre Local Green Space (4.26 hectares reduced to about 2.5 hectares) and removal of a community woodland planted by local volunteers. Report P119, P137, P158

Who and where

  • Mosslands School pupils and staff (current ~1,100, future up to 1,500) Report P170
  • Local community users of Wallacre recreation ground and Wallacre Park Report P44, P132, P154
  • Local football teams currently using the Wallacre pitches Report P113, P114
  • Ward Member Cllr Lewis (full supporter of new school) Report 3.1
  • Neighbouring residents to Mosslands Drive and School Lane (257 neighbour notifications sent) Report 3.2, P44
  • Three objectors (loss of green space, overdevelopment, traffic, maintenance, antisocial behaviour concerns) Report P22, P23

Timeline

  • 23rd October 2025: Strategic Applications Sub-Committee approves application Report P1
  • Within 3 years of decision: Development must begin
  • Weeks 1-90 (Phase 1): Site establishment, construction of new school, works to retained Wallacre; new school fully operational by end of Phase 1 Report P52
  • Summer 2027: Community access expected to completed Wallacre pitches (11v11 and 9v9) and new pavilion Report P52, P113
  • Phase 2: Demolition of old school; formation of new car park, permanent cycle parking and plaza Report P53
  • Approximately weeks 139-144 (Phase 3): Formation of new school pitches, removal of temporary car park, completion of final Wallacre pitch Report P54
  • Summer 2028: Practical completion of whole development (school and Wallacre) Report P54

Plain English for the jargon

  • Local Green Space (LGS): A designation under the National Planning Policy Framework protecting green areas of particular importance to local communities; NPPF policies for Green Belt apply to development in LGS.
  • Very special circumstances: The test used for inappropriate development in the Green Belt (applied here to LGS): the harm must be clearly outweighed by other considerations.
  • Community Use Agreement (CUA): A legally binding agreement requiring the school to allow community access to its sports and other facilities during term-time, non-term time and weekends.
  • Type 5 pitch: A pipe-drained sand-slitted grass pitch with sand topdressing, allowing up to 6 hours of use per week including in winter.
  • Biodiversity Net Gain (BNG): A measurable improvement in biodiversity resulting from a development, secured here over 30 years and exceeding the 10% requirement.
  • MUGA: Multi-Use Games Area, a fenced outdoor surface for sports such as basketball or 5-a-side football.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5

Resolved

Resolved (unanimously) – That for the reasons set out in the Officers’ report: That the Chief Planner, Assistant Director of Regeneration and Place be authorised to approve the application subject to the conditions set out below. 1. The development hereby permitted shall begin not later than 3 years from the date of this decision. 2. The development hereby permitted shall be carried out in accordance with the approved plans listed as follows: SRP1152-OOB-00-AA-D-L-9105 Rev P02 (Site Location Plan) SRP1152-OOB-00-XX-D-L-9110 Rev P17 (Whole Site Plan – Masterplan) SRP1152-OOB-00-XX-D-L-9101 Rev P02 (Demolition Plan) SRP1152-EWA-ZZ-00-D-A-0450 Rev P02 (Ground Floor Plan Sheet 1) SRP1152-EWA-ZZ-00-D-A-0451 Rev P02 (Ground Floor Plan Sheet 2) SRP1152-EWA-ZZ-01-D-A-0452 Rev P02 (First Floor Plan) SRP1152-EWA-ZZ-02-D-A-0453 Rev P02 (Second Floor Plan) SRP1152-EWA-ZZ-RF-D-A-0406 Rev P09 (Roof Plan Sheet 1) SRP1152-EWA-ZZ-RF-D-A-0407 Rev P09 (Roof Plan Sheet 2) SRP1152-EWA-ZZ-ZZ-D-A-0460 Rev P05 (Changing Pavilion GA) SRP1152-EWA-ZZ-ZZ-D-A-0470 Rev P03 (External Services Compound) SRP1152-EWA-ZZ-ZZ-D-A-0470 Rev P03 (External Services Compound) SRP1152-EWA-ZZ-ZZ-D-A-0471 Rev P00 (Proposed Sub-Station) SRP1152-EWA-ZZ-ZZ-D-A-0550 Rev P01 (Proposed Elevations Sheet 1) SRP1152-EWA-ZZ-ZZ-D-A-0551 Rev P01 (Proposed Elevations Sheet 2) SRP1152-EWA-ZZ-ZZ-D-A-0650 Rev P01 (Proposed Sections) SRP1152-EWA-ZZ-ZZ-D-A-0660 Rev P02 (Changing Pavilion Sections) SRP1152-EWA-ZZ-00-D-A-2750 Rev P03 (Proposed Canopy Roof Plan – Dining) SRP1152-EWA-ZZ-00-D-A-2751 Rev P03 (Proposed Canopy Roof Plan – Teaching) SRP1152-EWA-ZZ-00-D-A-2752 Rev P03 (Proposed Canopy Roof Plan – External Cycle Parking) SRP1152-EWA-ZZ-00-D-A-2753 Rev P03 (Proposed Elevations – Teaching) SRP1152-EWA-ZZ-00-D-A-2754 Rev P03 (Proposed Elevations – External Cycle Parking) SRP1152-TAC-ZZ-XX-D-E-9006 Rev P02 (Proposed Specialist Systems Strategy Layout) SRP1152-OOB-00-XX-D-L-9102 Rev P11 (Site Landscaping Plan) SRP1152-OOB-00-XX-D-L-9122 Rev P12 (GA Landscape Plan) SRP1152-OOB-00-XX-D-L-9132 Rev P01 (Proposed Sports Areas) SRP1152-OOB-00-XX-D-L-9133 Rev P01 (Proposed External Sports Pitches) SRP1152-OOB-00-XX-D-L-9310 Rev P05 (Site Elevations Sheet 1 – External Structures) SRP1152-OOB-ZZ-XX-D-L-9400 Rev P10 (Boundary Treatment Plan) SRP1152-OOB-00-XX-D-L-9501 Rev P07 (Tree Retention and Removal Plan) SRP1152-OOB-00-XX-D-L-9502 Rev P06 (General Arrangement Planting Plan) SRP1152-OOB-00-XX-D-L-9503 Rev P01 (Proposed Planting Sheet 1) SRP1152-OOB-00-XX-D-L-9504 Rev P01 (Proposed Planting Sheet 2) SRP1152-OOB-00-XX-D-L-9505 Rev P03 (Proposed Planting Sheet 3) SRP1152-ROS-00-XX-D-C-0500 Rev P10 (Drainage Plan Sheet 1) SRP1152-ROS-00-XX-D-C-0501 Rev P08 (Drainage Plan Sheet 2) SRP1152-ROS-00-XX-D-C-0600 Rev P09 (Proposed Finished Levels 1) SRP1152-ROS-00-XX-D-C-0601 Rev P06 (Proposed Finished Levels 2) SRP1152-BLA-ZZ-00-D-X-0001 Rev P01 (Sports Surfaces Construction Sections) SRP1152-BLA-ZZ-00-D-X-0002 Rev P01 (Sports surfaces Masterplan) SRP1152-BLA-ZZ-00-D-X-0003 Rev P01 (Type 5 Northern Playing Field Arrangements) SRP1152-BLA-ZZ-00-D-X-0004 Rev P01 (Type 5 Southern Playing Field Arrangements) SRP1152-BLA-ZZ-00-D-X-0005 Rev P01 (Type 1 MUGA and 5v5 AWP Arrangement) SRP1152-BLA-ZZ-00-D-X-0006 Rev P01 (Drainage Masterplan – Sports Surfaces) SRP1152-BLA-ZZ-00-D-X-0007 Rev P01 (Fencing Arrangement – MUGA and AWP) B250103 Rev A (Mosslands Pitch Specification & Phasing, Blakedown) 3. No development involving the use of any facing materials shall take place until full details (including samples, where required) of the materials to be used in the construction ... view the full minutes text for item 5.
Word for word from the decision Wirral published for this meeting. Source: democracy.wirral.gov.uk

Follow this further

Built from Wirral's papers

What the report saysPro

Report to Strategic Applications Sub Committee

Strategic Applications Sub-Committee 23rd October 2025

PS Development Case Reference: Ward: Code Officer: Q06 - Other Major [name removed]/25/00792 Liscard Developments Bechka

Mosslands School Mosslands Drive, Wallasey Village, Wallasey, Wirral, Location: CH45 8PJ Demolition of existing school and erection of new Mosslands School including 3-storey main building, 2no. sports halls; formation of new and replacement playing fields and sports facilities; provision of new car park, Proposal: cycle parking; and ancillary works. Replacement playing fields and pitches at Wallacre recreation ground, including ground remodelling, drainage installation, replacement pavilion, new footpaths, and ancillary work. Applicant: [name removed] (Willmot Dixon) Agent: [name removed] (Plan Red)

Reason for referral to Planning Committee Large Scale Major Development

Site Plan:

© Crown copyright and database rights 2023 Ordnance Survey 100019803 You are not permitted to copy, sub-licence, distribute or sell any of this data to third parties in any form. 1. Development Plan Local Green Space designation: Urban Open Space Primarily Residential Area Flood Zone 2 and 3 Wirral Local Plan Settlement Area - WP1

2. Planning History: SCR/24/00841 EIA Screening Request for outline planning application (with all matters reserved save for access) for the redevelopment of existing school, relocation, reprovision and improvement of playing pitches, car parking, sustainable urban drainage, landscaping, new vehicular and pedestrian access, and other associated infrastructure. Screening Reply

DPP3/14/00643 Proposal to replace existing low roof to school corridor with new roof construction at a raised height Approve

DPP3/14/01045 Erection of a new lightweight steel frame pitch roof over the existing flat roof at pavilion Approve

APP/07/05827 Construction of 2 No. Multi Use Games Areas with fencing and floodlighting Approve

APP/05/06278 Erection of an extension to sixth form centre, new canopy and entrance doors Approve

APP/03/07574 Erection of a single storey extension to include additional classrooms, support rooms, staff room, plant room and link to existing school with new entrance Approve

APP/02/06890 Creation of a cycle route link from Mosslands Drive to new bridge link onto Bidston Moss Restoration scheme Approve

APP/01/07414 Erection of a dining room extension Approve

APP/01/05782 Erection of three storey classroom extension with additional playground Approve

APP/97/06761 Resurfacing of existing footpath, construction of new cycleway/footpath, motorcycle barriers, fencing & hedgerow planting. Approve

APP/95/06616 Erection of a three storey educational block, sports hall, extensions to ground, first and second floors of existing building and car parking. Approve

Additional planning history exists across the wider school site; however, it is not of direct relevance to this application and as such has not been listed above.

3. Summary Of Representations and Consultations Received:

3.1Ward Member Cllr Lewis has given his full support for the building of a new school. That Comments the design should remedy the lack of on-site parking, causing traffic issues in the vicinity. Particularly interested in the proposed mitigations to the impact on the environment and immediate community - including work to improve Wallacre Playing Fields (post construction) and the rebuild of the football pavilion.

3.2Summary of REPRESENTATIONS Representations Having regard to the Council Guidance on Publicity for Applications and the Statement of Community Involvement, a total of 257 no. neighbour notifications were sent out to neighbouring properties on 04-06- 2025. Site notice was posted outside on 08-09-2025. A press notice was published on 09-06-2025.

In response 3 representations objecting to the application were received. Comments made within submitted representations are summarised below:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
APP/25/00792: Mosslands School, Mosslands Drive, Wallasey Village, Wallasey, Wirral, CH45 8PJ: Application for Demolition of existing school and erection of new Mosslands School .Report 1 MB DownloadRead as text

At this meeting

Whole meeting
4MINUTESApproved
5APP/25/00792 - Mosslands School, Mosslands Drive, Wallasey Village, Wallasey, Wirral, CH45 8PJ - Application for Demolition of existing school and erection of new Mosslands School .This decision

Who was there

6 of 12 attended
SF
Councillor Steve FoulkesVice-Chair, present
AG
Councillor Andrew GardnerSpokesperson, present
SK
Councillor Stuart KellyChair, present
HG
Councillor Harry GormanSpokesperson, present
MN
Matthew NealOfficer, expected
FF
Felicity FlemingOfficer, expected
RE
Rhys EdwardsCommittee Officer, expected
NF
Nicky FolanOfficer, expected
LL
Councillor Louise Luxon-KewleyCommittee Member, present
PS
Councillor Paul StuartCommittee Member, present
SL
Steven LaceyOfficer, expected
ML
Mandy LewisOfficer, expected

More from Wirral Strategic Applications Sub Committee

All decisions
MeetingDecisionOutcome
25 Jun 2026 MINUTESResolved – That the minutes of the meeting held on 29 th January 2026 be approved as a correct record. Approved Open
25 Jun 2026 APP/25/01454 - MEA Park, Land to the east of Wallasey Bridge Road, Birkenhead, Wirral, CH41 1EBResolved (unanimous) – That for the reasons set out in the Officers report: 1. The Chief Planner, Assistant Director ... Approved Open
25 Jun 2026 Adoption of Supplementary Planning DocumentsResolved – That Members’ noted the Householder Development SPD for adoption (Appendix 1) and Designing for Residentia... Noted Open
29 Jan 2026 APP/25/00597 - David Lloyd, Bidston Dock, Wallasey Bridge Road, Bidston, Wirral, CH41 1EBResolved (unanimously) – That for the reasons set out in the Officers report, and noting the addendum report and sugg... Approved Open
23 Oct 2025 MINUTESResolved – That the minutes of the meetings held on 16 January 2025 and 6 February 2025 be approved as an accurate re... Approved Open