Strategic Applications Sub Committee, Thursday 29 January 2026

APP/25/00597 - David Lloyd, Bidston Dock, Wallasey Bridge Road, Bidston, Wirral, CH41 1EB

Approved Committee 2 papers

AI summaryWirral Strategic Applications Sub-Committee has unanimously approved a David Lloyd health, fitness and racquets club at Bidston Dock, subject to planning conditions and a Section 106 agreement securing highways, biodiversity and monitoring contributions.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedUnanimous decision, 3 years to begin development
MoneyS106 contributions totalling multiple sums£2,500, £10,000, £20,000, £5,000 plus 15% of fee
What happens nextS106 must be completed within 9 monthsOr application can be refused unless extension agreed
Who it affectsBidston Dock site and surrounding areaFormer 2.8ha filled dock within Wirral Waters Regeneration Area

What was decided

The application was approved, subject to conditions and completion of a Section 106 agreement, with the Chief Planner and Assistant Director of Regeneration and Place given delegated authority to act.

The S106 must secure drainage links, highways contributions, biodiversity net gain monitoring costs, and S106 monitoring costs at 15% of the planning application fee.

Authority was given to refuse the application if a satisfactory Section 106 agreement is not completed within 9 months of the resolution, unless an extension of time is agreed.

Why

Officers found the proposal acceptable in principle under the Wirral Local Plan, including policy RA6 for the Wirral Waters Regeneration Area and the Bidston Dock Masterplan Area, as a leisure use within Use Class E. Report 8.3, P52

The sequential test and impact assessment accepted that the David Lloyd club could not be accommodated in Birkenhead Town Centre or Hind Street, and that impacts on the town centre would be minimal. Report 8.3, P53, P54, P55

Following further information, consultees including the Local Lead Flood Authority, Highways, MEAS, the Environment Agency, Natural England, Environmental Health and United Utilities raised no objections subject to conditions and obligations. Report P16, P17, P18, P19, P20, P21, P22, P24

What happens next

A Section 106 legal agreement must be completed within 9 months of the resolution, securing the listed contributions and a drainage link to the separate off-site drainage scheme being progressed under planning application APP/25/01800. Report 8.7

Conditions require, among other matters, submission of materials, landscaping, lighting, drainage, contamination remediation, a Construction Environmental Management Plan, biodiversity net gain, and pre-commencement ecological surveys before development begins. Report 8.8, P63

A separate Section 278 Highways Act 1980 agreement will be required between the developer and the Council to deliver the listed off-site highway works, paid for entirely by the developer. Report 8.7, P60

The money

  • £2500 Traffic regulations orders on Poulton Bridge Road Report 8.7
  • £10,000 Maintenance of the Wallasey Bridge Road bridge deck Report 8.7
  • £20,000 Scheme to improve pedestrian movements and links at Poulton Bridge Road Report 8.7
  • £5,000 Biodiversity net gain monitoring costs
  • £6,069 Planning application fee on which the 15% S106 monitoring cost is based

Options considered

  • Chosen: Approve subject to conditions and Section 106 agreement. Officers concluded the proposal accords with the development plan and material considerations, with no overriding impacts subject to the listed conditions and obligations Report 8.4, 8.5, 8.7, 8.8
  • Rejected: Refuse the application. No overriding grounds for refusal were identified once further information resolved the flood, drainage, highways and ecological objections Report P19, P20, P16

Implications

  • Financial: The developer must fund the listed Section 106 contributions, Section 278 highway works, drainage infrastructure linking to a second planning application, and Biodiversity Net Gain delivery and monitoring. Report 8.7, 8.8
  • Environmental: Surface water drainage is to be delivered via a linked off-site scheme discharging to West Float, with Sustainable Drainage Systems on-site and betterment on greenfield runoff rates in severe storms.
  • Legal: Completion of a Section 106 agreement within 9 months is a precondition; otherwise the Chief Planner is authorised to refuse. A separate Section 278 agreement is needed for highway works and a highways legal easement for drainage. Report 8.7
  • Equalities: A ward councillor asked whether a local discount would be offered, indicating potential social value interest in access for local residents. Report 3.1

Who and where

  • David Lloyd Leisure Limited, the applicant Report P3
  • Residents in Breck Road and Limekiln Lane, around 150m to the north and north-east Report 8.5
  • Wirral Wildlife Trust, which lodged a holding objection until further survey information was provided Report P12, P16
  • The Liverpool City Region Combined Authority, which objected on drainage grounds relating to the Mersey Tunnels Report P13
  • Existing commercial and employment uses near the Site, including Wallasey Sea Cadets Boathouse and Liverpool Victoria Rowing Club Report 8.5
  • Future users of the wider Bidston Dock Masterplan Area, which the proposal is not expected to sterilise Report 8.3, P52

Timeline

  • January 2000: Planning permission granted for infilling of Bidston Dock Report P7
  • March 2025: Screening opinion issued, concluding an Environmental Impact Assessment is not required Report P8
  • December 2025: Separate planning application APP/25/01800 submitted for drainage proposals serving the Site and wider land Report P9
  • 16 December 2025: Government published consultation on proposed reforms to the National Planning Policy Framework Report 8.2
  • 29th January 2026: Strategic Applications Sub-Committee resolved unanimously to approve the application subject to conditions and Section 106 Report P1
  • Three years from the date of permission: Development must be begun before this deadline
  • Nine months from the Sub-Committee resolution: Section 106 agreement must be completed, or the application may be refused unless an extension is agreed

Plain English for the jargon

  • Section 106 agreement: A legal agreement under section 106 of the Town and Country Planning Act 1990 used to secure planning obligations such as financial contributions and works linked to a permission.
  • Section 278 agreement: An agreement under section 278 of the Highways Act 1980 between a developer and the highway authority for the developer to carry out works on the public highway.
  • Use Class E: A planning use class covering commercial, business and service uses including indoor sport, recreation and fitness.
  • Bidston Dock Masterplan Area: An area designated under Local Plan policy RA6 within the Wirral Waters Regeneration Area, for which a masterplan and design code are required.
  • Sequential test: A test requiring applicants for main town centre uses outside town centres to demonstrate that more central sites are not suitable, available and viable.
  • Biodiversity Net Gain (BNG): A requirement that development delivers a measurable improvement in biodiversity compared with the pre-development baseline, with monitoring to confirm delivery.
  • LLFA: Local Lead Flood Authority, the council team that leads on flood risk and surface water drainage matters.
  • MEAS: Merseyside Environmental Advisory Service, which advises on ecological and environmental planning matters.
  • CEMP: Construction Environmental Management Plan, a document setting out how construction impacts on the environment will be controlled.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9

Resolved

Resolved (unanimously) – That for the reasons set out in the Officers report, and noting the addendum report and suggested amendments: 1. That the Chief Planner, Assistant Director of Regeneration and Place be authorised to approve the application subject to the following conditions set out below and subject to the completion of an agreement under Section 106 of the Town and Country Planning Act 1990 that will secure: · A link between the drainage measures to the development to ensure the drainage measures are completed prior to development taking place that forms completion of the roof of the main building, the tennis dome or the padel courts. · Highways contributions of £2500, £10,000 and £20,000 for traffic regulations orders, maintenance of the bridge deck on Wallasey Bridge Road and a scheme to improve pedestrian movements and links at the Poulton Bridge Road respectively. · BNG monitoring costs of £5,000. · S106 Monitoring costs representing 15% of the planning application fee which is £6,069 2. That delegated authority is given to the Chief Planner, Assistant Director of Regeneration and Place in consultation with the Chair and Spokespersons of the Strategic Applications Sub-Committee to make minor non substantive amendments to the S106 Heads of Terms and planning conditions as necessary. 3. That the Chief Planner, Assistant Director of Regeneration and Place be authorised to refuse the application in the event that a satisfactory section 106 agreement is not received within 9 months of the date on which Strategic Applications Sub Committee resolve to approve the application unless an extension of time is agreed to the satisfaction of the Chief Planner, Assistant Director of Regeneration of Place in consultation with the Chair and Spokespersons of the Strategic Applications Sub Committee. Conditions: 1. The development hereby permitted shall be begun before the expiration of three years from the date of this permission. 2. Except where modified by the conditions attached to this planning permission, the development hereby approved relates to and shall be carried out in accordance with the following approved plan: · Site Location Plan (ref. A-PL-001 P01) · Existing Site Plan (ref. A-PL-002 P01) · Proposed Site Plan (ref. A-PL-003 P01) · Proposed Ground ... view the full minutes text for item 9.
Word for word from the decision Wirral published for this meeting. Source: democracy.wirral.gov.uk

Follow this further

Built from Wirral's papers

What the report saysPro

Report to Strategic Applications Sub Committee

Strategic Applications Sub-Committee 29th January 2026

PS Development Case Reference: Ward: Code Officer: Q06 - Other Major [name removed] and APP/25/00597 Developments Heather St James

Location: Bidston Dock Wallasey Bridge Road, Bidston, Wirral, CH41 1EB Erection of health, fitness and racquets club, including three outdoor tennis courts within an enclosed air dome structure, six outdoor padel courts enclosed within a canopy, indoor and outdoor swimming pools, outdoor multi use court, outdoor battle box exercise facility, two indoor courts within a sports hall, gym and studio facilities, internal spa facilities Proposal: and external spa garden, child activity area, lounge facilities including a business hub and terrace, plant and machinery, together with ancillary facilities, car parking, servicing, landscaping, alteration to existing access onto Wallasey Bridge Road, alteration to existing bund and associated works. Applicant: David Lloyd Leisure Limited Agent: [name removed] (Lichfields)

Reason for referral to Planning Committee Large Scale Major Development

Site Plan: © Crown copyright and database rights 2026 Ordnance Survey 100019803 You are not permitted to copy, sub-licence, distribute or sell any of this data to third parties in any form.

1. Development Plan District Heat Network Demand Assessment Area designation: Birkenhead 2040 Framework Area - Birkenhead Regeneration Framework Area Wirral Waters Regeneration Area Viability Zone 1 Master Plan Area – Bidston Dock Settlement Area 2 - Birkenhead Commercial Core

2. Planning History: January 2000: Planning permission (ref: APP/99/05998) granted for “Infilling of dock”.

March 2025: Screening opinion (ref: SCR/25/00271) issued. This concluded that an Environmental Impact Assessment is not required.

December 2025: Planning application (ref: APP/25/01800) submitted for “Drainage Proposals to serve David Lloyd and wider land at Bidston Docks”. This includes land to the south of the Site that is the subject of this committee report. At the time of writing this planning application remains undetermined.

3. Summary Of Representations and Consultations Received:

3.1Ward Member A letter of support was received from Councillor Grey noting the benefits Comments of exercise and asking if there would be a discount for local people. 3.2 Summary of REPRESENTATIONS Representations Having regard to the Council Guidance on Publicity for Applications and the Statement of Community Involvement 3 notifications were sent to adjoining properties in May 2026. A notice was also displayed on site and published in the press. No representations were received from the public.

Wirral Wildlife Trust lodged a holding objection until further information was provided on botanical, invertebrate and reptile surveys and Biodiversity Net Gain (BNG).

A response was received from the Combined Authority of the Liverpool City Region. This raised an objection based on potential drainage impacts that could affect the Mersey Tunnels.

Merseyside Fire and Rescue responded. They did not raise an objection but made a request for some information on access for firefighting and water provision to be passed to the applicant.

CONSULTATIONS

Merseyside Environmental Advisory Service (MEAS) – Initial comment raised a concern about a lack of surveys that the applicant has indicated were required. Following submission of these surveys there are no objections to the ecological impacts. Comments were also received on Archaeology, and with additional information submitted, no objections were made.

Environment Agency – No objection subject to conditions relating to contaminated land. Advice was also provided on a range of issues including dealing with waste on and off the Site, and the need for an Environmental Permit.

Natural England – No objection subject to conditions requiring a Construction Environment Management Plan (CEMP), and details of surface water drainage.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
APP.25.00597 David Lloyd AddendumAddendum 404 KB Download
PDF
APP/25/00597: David Lloyd, Bidston Dock, Wallasey Bridge Road, Bidston, Wirral, CH41 1EBReport 761 KB DownloadRead as text

At this meeting

Whole meeting
9APP/25/00597 - David Lloyd, Bidston Dock, Wallasey Bridge Road, Bidston, Wirral, CH41 1EBThis decision

Who was there

6 of 12 attended
SF
Councillor Steve FoulkesVice-Chair, present
AG
Councillor Andrew GardnerSpokesperson, present
SK
Councillor Stuart KellyChair, present
HG
Councillor Harry GormanSpokesperson, present
MN
Matthew NealOfficer, expected
FF
Felicity FlemingOfficer, expected
RE
Rhys EdwardsCommittee Officer, expected
NF
Nicky FolanOfficer, expected
LL
Councillor Louise Luxon-KewleyCommittee Member, present
PS
Councillor Paul StuartCommittee Member, present
SL
Steven LaceyOfficer, expected
ML
Mandy LewisOfficer, expected

More from Wirral Strategic Applications Sub Committee

All decisions
MeetingDecisionOutcome
25 Jun 2026 MINUTESResolved – That the minutes of the meeting held on 29 th January 2026 be approved as a correct record. Approved Open
25 Jun 2026 APP/25/01454 - MEA Park, Land to the east of Wallasey Bridge Road, Birkenhead, Wirral, CH41 1EBResolved (unanimous) – That for the reasons set out in the Officers report: 1. The Chief Planner, Assistant Director ... Approved Open
25 Jun 2026 Adoption of Supplementary Planning DocumentsResolved – That Members’ noted the Householder Development SPD for adoption (Appendix 1) and Designing for Residentia... Noted Open
23 Oct 2025 MINUTESResolved – That the minutes of the meetings held on 16 January 2025 and 6 February 2025 be approved as an accurate re... Approved Open
23 Oct 2025 APP/25/00792 - Mosslands School, Mosslands Drive, Wallasey Village, Wallasey, Wirral, CH45 8PJ - Application for Demolition of existing school and erection of new Mosslands School .Resolved (unanimously) – That for the reasons set out in the Officers’ report: That the Chief Planner, Assistant Dire... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies