CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Wirral Borough Council

APP/25/01454 - MEA Park, Land to the east of Wallasey Bridge Road, Birkenhead, Wirral, CH41 1EB

Approved Committee 1 paper

AI summaryWirral Strategic Applications Sub Committee unanimously approves a new B2/B8 employment unit on land east of Wallasey Bridge Road, Birkenhead, subject to planning conditions and a Section 106 agreement.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedSubject to conditions and a Section 106 agreement
Money£5,000 BNG monitoring feeSecured via Section 106 legal agreement
What happens nextS106 agreement must be completedWithin 6 months or application may be refused
Who it affectsMEA Park, Wallasey Bridge Road, BirkenheadLand within Wirral Waters Regeneration Area

What was decided

The Sub Committee unanimously resolved to authorise the Chief Planner, Assistant Director of Regeneration and Place to approve the application, subject to the conditions listed and to the completion of a Section 106 agreement. Report P74

Delegated authority was given to the Chief Planner, in consultation with the Sub Committee Chair, to make minor non-substantive amendments to the S106 heads of terms and planning conditions. Report P75

The Chief Planner was authorised to refuse the application if a satisfactory S106 agreement is not received within 6 months of the resolution, unless an extension is agreed. Report P76

Why

The site is allocated for B2 and B8 employment uses within the Wirral Waters Regeneration Area and the MEA Park West Employment Allocation, making the proposed commercial use acceptable in principle. Report 8.3, P55, P36

The design, scale and appearance of the building are considered acceptable in the context of nearby commercial buildings, with conditions securing materials, landscaping and energy efficiency measures. Report 8.4, 8.10, 8.16

Flood risk, drainage, highways, ecology, biodiversity, contamination, archaeology and impacts on neighbouring uses are all considered manageable through conditions, with a 10 percent Biodiversity Net Gain required including 12.49 off-site habitat units. Report 8.6, 8.7, 8.8, P65, 8.12

What happens next

A Section 106 legal agreement must be completed to secure a £5,000 Biodiversity Net Gain monitoring fee and any other obligations set out in section 8.14 of the report. Report 8.14, P74

If the S106 agreement is not completed within 6 months of the resolution, the Chief Planner is authorised to refuse the application unless an extension is agreed. Report P76

The development must begin within three years of the permission date, with conditions requiring submission of a servicing and waste management strategy, cycle storage details and a Construction Environment Management Plan before occupation or commencement of relevant works. Report P78, P83, 8.8

The money

  • £5,000 Monitoring fee for Biodiversity Net Gain, secured via Section 106 legal agreement Report 8.14

Options considered

  • Chosen: Approve the application subject to conditions and a Section 106 agreement. The proposal accords with the development plan and is acceptable on design, highways, ecology, flood risk, contamination and amenity grounds, with conditions making any remaining issues manageable. Report P74, 8.16, P73
  • Rejected: Refuse the application if a satisfactory Section 106 agreement is not received within 6 months. Held in reserve as a contingency to be used only if the S106 agreement is not completed in time. Report P76
  • Rejected: Require a fully worked-up masterplan and design code across the whole Masterplan Area. Considered disproportionate given the limited existing context on the site and the substantial area of land some distance away that may not come forward for some time. Report 8.3
  • Rejected: Require a Section 106 contribution towards maintenance of Penny Bridge on Wallasey Bridge Road. Not considered reasonable given the applicant's traffic assessment showed no significant impact on the highway network and a ghost island was not required. Report 8.7

Implications

  • Financial: A £5,000 monitoring fee for Biodiversity Net Gain will be secured through a Section 106 legal agreement. Report 8.14
  • Legal: The application must be determined in accordance with the development plan; a Section 106 agreement under the Town and Country Planning Act 1990 is required before approval is issued. Report 8.16, P74
  • Equalities: A condition will secure social value measures including training and employment targets, as requested by Economic Development. Report 8.13, P34
  • Climate: The development includes photovoltaic panels on the roof, LED lighting, heat recovery and other measures delivering a 7 percent CO2 saving and 8.9 percent primary energy saving compared to Building Regulations, with a BREEAM score of nearly 61.5 percent. Report 8.10
  • Risk: Conditions address land contamination, flood risk, surface water drainage, construction management and protected species, including a Construction Environment Management Plan to mitigate construction impacts. Report 8.6, 8.8
  • Other: The site lies within the Liverpool City Region Free Port and several regeneration and employment designations, supporting its use for B2 and B8 employment. Report P37, P36

Who and where

  • The applicant, Wirral Waters No.1 Limited, seeking to develop the site Report P3
  • Future occupiers of the B2/B8 employment unit and their employees Report 8.13
  • Sasol, operators of the industrial facility to the south, and the Mobil Building to the east
  • Household Waste Recycling Facility to the west across Wallasey Bridge Road
  • Residents of Limekiln Lane approximately 300m to the north
  • Wallasey Sea Cadets Boathouse and Liverpool Victoria Rowing Club over 100m from the proposed building
  • Users of West Float, Mersey Narrows and North Wirral Foreshore SPA and Ramsar and other designated nature sites Report 8.8
  • Road and bus users on Wallasey Bridge Road, including those using the nearby bus stop Report 8.7

Timeline

  • September 2025: Three planning applications submitted on adjacent sites, including this one Report P7
  • October 2025: Nine notifications sent to adjoining properties and site and press notices published; no public representations received Report 3.1
  • 16 December 2025: Government published consultation on proposed reforms to the National Planning Policy Framework
  • 8 January 2026: Recent appeal decision elsewhere in Wirral referenced in considering weight to be given to NPPF reforms
  • March 2026: Related applications APP/25/01450 (Mobil Building) and APP/25/01452 (Greenway footway/cycleway) granted planning permission, and nearby applications APP/25/00597 and APP/25/01800 also granted Report P9, P11, P20, P21
  • 25th June 2026: Strategic Applications Sub Committee resolves unanimously to approve application APP/25/01454 subject to conditions and Section 106 agreement Report P1
  • Within 6 months of 25th June 2026: Section 106 agreement must be completed or the Chief Planner is authorised to refuse the application Report P76

Plain English for the jargon

  • B2 use: General industrial use under the Town and Country Planning Act Use Classes Order.
  • B8 use: Storage and distribution use, including warehouses.
  • Section 106 agreement: A legal agreement under Section 106 of the Town and Country Planning Act 1990 used to secure planning obligations from a developer.
  • Biodiversity Net Gain (BNG): A requirement that development delivers a measurable improvement in habitat value, here a 10 percent gain.
  • BREEAM: Building Research Establishment Environmental Assessment Method, a sustainability rating for buildings.
  • MEAS: Merseyside Environmental Advisory Service, which provides ecological advice to councils.
  • HRA: Habitats Regulations Assessment, assessing impacts on protected European nature sites.
  • CEMP: Construction Environment Management Plan, setting out measures to manage environmental impacts during construction.
  • Penny Bridge: The bridge on Wallasey Bridge Road referenced in relation to highways contributions.
  • Wirral Waters Regeneration Area: A designated regeneration area focused on a residential-led mixed use development around the Wirral Waters waterfront.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5

Resolved

Resolved (unanimous) – That for the reasons set out in the Officers report: 1. The Chief Planner, Assistant Director of Regeneration and Place be authorised to approve the application subject to the conditions set out below and subject to the satisfactory completion of an agreement under Section 106 of the Town and Country Planning Act 1990 that will secure the planning obligations set out at section 8.14 of this report. 2. Delegated authority is given to the Chief Planner, Assistant Director of Regeneration and Place in consultation with the Chair of the Strategic Applications Sub-Committee to make minor non substantive amendments to the S106 Heads of Terms and planning conditions as necessary 3. The Chief Planner, Assistant Director of Regeneration and Place be authorised to refuse the application in the event that a satisfactory section 106 agreement is not received within 6 months of the date on which Strategic Applications Sub Committee resolve to approve the application unless an extension of time is agreed to the satisfaction of the Chief Planner, Assistant Director of Regeneration of Place in consultation with the Chair and Spokespersons of the Strategic Applications Sub Committee. Conditions: 1. The development hereby permitted shall be begun before the expiration of three years from the date of this permission. 2. Except where modified by the conditions attached to this planning permission, the development hereby approved relates to and shall be carried out in accordance with the following approved plan: · DR-A-03-200 Revision B · DR-A-05-200 Revision E · DR-05-301 Revision B · DR-A-03-201 Revision D · DR-90-200 Revision E · MEAP-BCAL-ZZ-00-DR-L-9024 Revision P-04 · MEAP-BCAL-ZZ-00-DR-L-9034 Revision P-03 · MEAP-BCAL-ZZ-00-DR-L-9020 Revision P-06 3. Prior to first occupation of the building hereby approved (labelled as ‘Plot 4’ on drawing DR 90-200 Rev. C) a servicing and waste management strategy shall be submitted to and approved in writing by the Local Planning Authority. For the avoidance of doubt the strategy shall set out operational proposals for servicing and the storage, transfer and collection of waste ensuring that appropriate arrangements are made and that logistical requirements are appropriately considered and addressed. The strategy shall be subsequently implemented in accordance with the approved details prior to the first use of the development hereby approved and adhered to thereafter. 4. The building hereby approved (labelled as ‘Plot 4’ on drawing DR-90-200 Rev. C) shall not be occupied until details of the cycle storage shown on approved drawing MEAP-BCAL-ZZ-00-DR L-9024 Rev. P-04 have been submitted to and approved in writing by the Local Planning Authority. This shall include details showing the appearance ... view the full minutes text for item 5.
Word for word from the decision Wirral published for this meeting. Source: democracy.wirral.gov.uk

Follow this further

Built from Wirral's papers

What the report saysPro

Report to Strategic Applications Sub Committee

Strategic Applications Sub-Committee 25th June 2026

PS Development Case Reference: Ward: Code Officer: Q06 - Other Major [name removed] and APP/25/01454 Developments Heather St James

Land to the east of Wallasey Bridge Road, Birkenhead, Wirral, CH41 Location: 1EB Construction of 1 no. employment unit (B2/B8), construction and enhancement of estate roads, installation of substation, demolition of Proposal: existing structure, site remediation, landscaping, parking and servicing areas and associated works. Applicant: Wirral Waters No.1 Limited Agent: [name removed] (Eden Planning and Development)

Reason for referral to Strategic Applications Large Scale Major Development Sub Committee

Site Plan:

© Crown copyright and database rights 2026 Ordnance Survey 100019803 You are not permitted to copy, sub-licence, distribute or sell any of this data to third parties in any form. 1. Development Plan MEA Park West Employment Allocation (EMP-RA6.2) designation: District Heat Network Demand Assessment Area (DHNA-1) Birkenhead 2040 Framework Area - Birkenhead Regeneration Framework Area Wirral Waters Regeneration Area (RA6) MEA Park Masterplan Area (MPA-RA6.2) Viability Zone 1 (VZ-1) Settlement Area 2 - Birkenhead Commercial Core

2. Planning History: This planning application was submitted alongside two others in September 2025 on adjacent sites, which have been determined:

Former Mobil Building Beaufort Road, Birkenhead, Wirral, CH41 1EB:

March 2026: Full Planning Permission (ref: APP/25/01450) granted for “Change of Use to manufacturing unit with minor works including alterations to the roof, new opening and painting, and associated works”

Footway Adjacent To Wallasey Bridge Road, Birkenhead, Wirral, CH41 1EB:

March 2026: Full Planning Permission (ref: APP/25/01452) granted for “Demolition of existing substation and the carrying out of public realm works to create a footway / cycleway, associated remediation, and landscape works and associated works on land along Wallasey Bridge Road.”

There has been an extensive planning history on the site and nearby. Those records from earlier than 2000 have been excluded leaving the following (which are common to all three applications submitted in September 2025):

March 2012: Outline Planning Permission (ref: OUT/11/00645) granted for “Outline planning application with all matters reserved for the demolition of existing buildings and the construction of: Two buildings providing an overall maximum of 111,780 sq m of floor space to be used as an International Trade Centre (Sui Generis Use) (comprising trade showrooms, storage, distribution and product assembly space, exhibition space, ancillary food and drink facilities, ancillary office and management accommodation, security facilities, and associated car parking, access points, servicing areas and landscaping), on land north of Beaufort Road and east of Graving Dock No. 3, West Float, Wirral Waters, Wirral; and. †¢ Two buildings providing an overall maximum of 116,529 sq m of floorspace to be used as one or a combination of, an International Trade Centre (as defined), B2 General Industry and B8 Warehouse/Distribution (with associated car parking, access points, servicing areas and landscaping) on land east of Wallasey Bridge Road and west of Graving Dock No. 3, West Float, Wirral Waters, Wirral. equating to a total combined floorspace of 228,300 sq m of mixed employment floorspace” February 2015: Full Planning Permission (ref: APP/14/01578) granted for “Variation of condition 3 on OUT11/00645”.

February 2015: Reserved Matters (ref: DLS/14/01579) granted for “Erection of a building for manufacturing use”

June 2021: Full Planning Permission (ref: APP/20/01298) granted for “The carrying out of public realm works to create a footway / cycleway, associated remediation, removal of sub stations and landscape works on land between Beaufort Road and Wallasey Bridge Road, south of West Float, Wirral Waters.”

May 2022: Screening Opinion for EIA (ref: SCR/14/01599) issued.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
APP/25/01454: MEA Park, Land to the east of Wallasey Bridge Road, Birkenhead, Wirral, CH41 1EBReport 427 KB DownloadRead as text

At this meeting

Whole meeting
4MINUTESApproved
5APP/25/01454 - MEA Park, Land to the east of Wallasey Bridge Road, Birkenhead, Wirral, CH41 1EBThis decision
6Adoption of Supplementary Planning DocumentsNoted

Who was there

6 of 12 attended
SK
Councillor Stuart KellyChair, present
SF
Councillor Steve FoulkesVice-Chair, present
JW
Councillor Jason Walsh - McDonaldSpokesperson, present
AG
Councillor Andrew GardnerSpokesperson, present
LL
Councillor Louise Luxon-KewleyCommittee Member, present
BK
Councillor Brian KennyCommittee Member, present
MN
Matthew NealOfficer, expected
FF
Felicity FlemingOfficer, expected
RE
Rhys EdwardsCommittee Officer, expected
SL
Steven LaceyOfficer, expected
NF
Nicky FolanOfficer, expected
ML
Mandy LewisOfficer, expected

On this subject at Wirral

Search all
  1. APP/25/01454 - MEA Park, Land to the east of Wallasey Bridge Road, Birkenhead, Wirral, CH41 1EBThis decision
  2. APP/25/00915 - Kingsmead Swimming Pool, Carlton Lane, Hoylake, CH47 0LLDeferred
  3. APP-24-00816 - WEST KIRBY GRAMMAR SCHOOL FOR GIRLS, GRAHAM ROAD, WEST KIRBY, WIRRAL, CH48 5DP - Proposed (isolated) demolition to enable the erection of a Sports Hall, 6th Form Centre with dining facilities and associated re-modelling works to facade, means of access, parking and landscapingApproved
  4. APP/21/00963; Sandiways, 46 HOYLE ROAD, HOYLAKE, CH47 3AQ Proposal: Full planning application for demolition of existing building and the erection of a residential development with associated means of access, site infrastructure, car parking and landscaping at 46 Hoyle Road, Hoylake CH47 3AQ.Approved
  5. APP/19/00014: Kingsmead School, BERTRAM DRIVE, MEOLS, CH47 0LL, erection of a new sixth form block and full planning permission for the erection of 25 residential dwellingsApproved
  6. APP/17/01295: Land at ACRE LANE AND MEADOWSIDE ROAD, BROMBOROUGH, CH62 7BX - Detailed application for the erection of 217 dwellings, with associated access (off Acre Lane and Meadowside Road) and landscaping and other ancillary works.Approved

More from Wirral Strategic Applications Sub Committee

All decisions
MeetingDecisionOutcome
25 Jun 2026 MINUTESResolved – That the minutes of the meeting held on 29 th January 2026 be approved as a correct record. Approved Open
25 Jun 2026 Adoption of Supplementary Planning DocumentsResolved – That Members’ noted the Householder Development SPD for adoption (Appendix 1) and Designing for Residentia... Noted Open
29 Jan 2026 APP/25/00597 - David Lloyd, Bidston Dock, Wallasey Bridge Road, Bidston, Wirral, CH41 1EBResolved (unanimously) – That for the reasons set out in the Officers report, and noting the addendum report and sugg... Approved Open
23 Oct 2025 MINUTESResolved – That the minutes of the meetings held on 16 January 2025 and 6 February 2025 be approved as an accurate re... Approved Open
23 Oct 2025 APP/25/00792 - Mosslands School, Mosslands Drive, Wallasey Village, Wallasey, Wirral, CH45 8PJ - Application for Demolition of existing school and erection of new Mosslands School .Resolved (unanimously) – That for the reasons set out in the Officers’ report: That the Chief Planner, Assistant Dire... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies