AI summaryWirral Council approved a revised 2025/26 Capital Programme of £81.585 million and additional funding for four new schemes, including £3.000 million for Haymarket Tunnel works.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedRevised Capital Programme and four new scheme bids
Money£81.585 millionRevised 2025/26 Capital Programme total
What happens nextNot stated
Who it affectsWirral residents and Council TaxpayersSchemes across regeneration, transport, housing and parks
What was decided
Approved the revised 2025/26 Capital Programme of £81.585 million, including the virements listed in Appendix D of the report. Report P2
Approved additional funding for the four capital schemes set out in section 3.8 of the report: Network Rail land acquisition at Dock Branch South, Haymarket Tunnel works, wall structures restoration and Balls Road temporary accommodation. Report P3, P56, P58, P60, P63
Why
Regular quarterly monitoring and reporting of the Capital Programme enable timely decisions, which may produce revenue benefits and improve financial control for the council. Report 1.1
What happens next
The full revised Capital Programme is set out in Appendix I, with virements listed in Appendix D and an indicative future programme in Appendix F. Report 4.6, P46, P106
The money
£81.585 million Revised 2025/26 Capital Programme total Report P2, P12
£3.000 million Haymarket Tunnel potential works within the Borough Yard programme Report P58
£1.000 million Restoration of wall structures across Wirral parks, cemeteries and open spaces Report P60
£0.245 million Acquisition of Network Rail land at Dock Branch South for Borough Yard Report P56
£0.200 million Balls Road temporary accommodation refurbishment Report P63
£12.701 million Strategic Investment Fund Levelling Up grant for Birkenhead Gateway transport schemes Report P28
£20.464 million Estimated borrowing required to finance 2025/26 capital schemes Report 4.2
£0.800 million per annum Estimated reduction in council subsidy loss from Balls Road accommodation Report P65
Options considered
Rejected: Other reporting frequencies. Quarterly reporting is standard practice Report 2.1
Implications
Financial: Borrowing of £20.464 million is estimated for 2025/26; Minimum Revenue Provision repayments to revenue begin in 2026/27 at £0.502 million. Report 4.2, P70, P71
Financial: Under the Annuity Method of repayment, MRP costs on 2025/26 borrowing are projected to peak in 2075/76 at £0.722 million. Report 4.3
Legal: The Council must set a balanced budget each year under the Local Government Finance Act 1992 and Local Government Act 2003, and members must consider their fiduciary duty to Council Taxpayers. Report 5.1, 5.2
Risk: Capital Programme delivery risk is mitigated through regular review by the Corporate Change Portfolio Board and the Change Advisory Board. Report 7.1, 7.5
Equalities: The Council must consider its fiduciary duty and the public sector equality duty when making its decision. Report 9.0, 9.2
Climate: Existing Capital Programme includes projects supporting the Council's Climate Emergency Plan, such as energy efficient buildings and active travel infrastructure. Report 10.1, 10.2
Other: Community Wealth Building Strategy is supported by regeneration projects within the programme that look to improve economic outcomes in the borough. Report 11.1
Staffing: No additional staffing or resource requirements arise directly from this report; the Capital Programme is managed within existing directorate structures. Report 6.1
Who and where
Wirral Council Taxpayers Report 5.2
Residents and businesses in the Borough Yard (Hind Street Urban Village) regeneration area Report P57
Homeless households to be placed in Balls Road temporary accommodation Report P64, P65
Active travel and road safety users in Birkenhead and across Wirral Report P35, P39
Users of Wirral parks, cemeteries and open spaces affected by wall structure conditions Report P60, P62
Service directorates including Adult Care and Health, Children Families and Education, Neighbourhoods, Regeneration and Place, and Finance Report P12
Timeline
2025/26 financial year: Revised Capital Programme of £81.585 million applies Report P2
2026/27: First Minimum Revenue Provision repayments of £0.502 million on 2025/26 borrowing are charged to the revenue budget Report P70, P71
2075/76: MRP cost on 2025/26 borrowing projected to peak at £0.722 million under the Annuity Method Report 4.3
Initial two year period from 2026/27: Balls Road management agreement between the Council and Riverside Housing Association, with phased subsidy benefit Report P65
Plain English for the jargon
MRP: Minimum Revenue Provision, the amount charged each year to the revenue budget to repay capital debt
Virement: A transfer of budget from one scheme or heading to another
S106: Section 106 planning obligation contributions from developers
Annuity Method: Method of repaying debt in which principal repayments start low and increase each year
CCPB: Corporate Change Portfolio Board
CAB: Change Advisory Board
ATF: Active Travel Fund grant programme
LCWIP: Local Cycling and Walking Infrastructure Plan
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item50g
Resolved
Resolved – that, 1 the revised Capital Programme of £81.585 million for 2025/26, including the virements of budget referred to in Appendix D of the report be approved 2 additional funding for the schemes referred to in section 3.8 of the report be approved.
Word for word from the decision Wirral published for this meeting.Source: democracy.wirral.gov.uk
The Policy and Resources Committee is requested to recommend to Council the approval of:
1 the revised Capital Programme of £81.585 million for 2025/26, including the virements of budget referred to in Appendix D of this report.
2 additional funding for the schemes referred to in section 3.8 in this report. SUPPORTING INFORMATION
1.0REASON/S FOR RECOMMENDATION/S
1.1Regular monitoring and reporting of the Capital Programme enable decisions to be taken in a timely manner, which may produce revenue benefits and will improve financial control in Wirral Borough Council.
2.0OTHER OPTIONS CONSIDERED
2.1Other reporting frequencies could be considered, but quarterly reporting is a standard practice.
3.0BACKGROUND INFORMATION
3.1Tables 1 and 2 provide an update on the 2025/26 Capital Programme analysed on a Directorate and then Committee basis. A number of variations have arisen since the original Programme was agreed in March 2025. These include the reprofiling of expenditure into and out of financial years, inclusion of additional grant funded schemes and variations to spend forecasts. Appendix A of this report provides further analysis of the movement of the forecast programme across directorates during the year to date.
Table 1: Capital Programme 2025/26 Position by Directorate
Wirral Borough Council 2025/26 Forecast Position
Budget Budget Actuals Variance Programme 1 Apr 25 31 Dec 25 31 Dec 25 £m £m £m £m Adult Care & Health 1.675 0.283 -1.392 0.190 Children, Families & Education 13.992 9.341 -4.651 4.996 Finance 5.883 5.365 -0.518 0.912 Neighbourhoods 18.100 22.695 4.595 11.930 Regeneration & Place 87.722 43.901 -43.821 33.697 Total 127.372 81.585 -45.787 51.726
Table 2: Capital Programme 2025/26 Position by Committee
Wirral Borough Council 2025/26 Forecast Position Budget Budget Actuals Variance Programme 1 Apr 25 31 Dec 25 31 Dec 25 £m £m £m £m Adult Social Care & Health 1.675 0.283 -1.392 0.190 Children, Young People & Education 13.992 9.341 -4.651 4.996 Economy, Regeneration & Housing 83.601 43.536 -40.065 33.578 Environment, Climate Emergency & Transport 21.382 22.551 1.169 11.887 Policy & Resources 5.883 5.365 -0.518 0.912 Tourism, Communities, Culture & Leisure 0.839 0.509 -0.330 0.162 Total 127.372 81.585 -45.787 51.726
3.1.2 As noted above, the main movements in this year’s Programme are in respect of reprofiling of budget into future years along with the inclusion of new funding and schemes into the Programme. A full breakdown can be found in Appendix A.
3.1.3 Such reprofiling reduces the borrowing costs incurred during the year (2025/26) and also delays the resultant Minimum Revenue Provision (MRP) charges into future years. Any delay in outputs will be monitored by project managers and practical implications reported to the appropriate committee.
3.1.4 Within Quarter 3 there was a £15.123m reduction in the forecast for 2025/26. As can be seen in Appendix A, the movements in Quarter 3 relate to:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Appointment of Independent PersonsResolved – That the appointment of the following Independent Persons of the Constitution and Standards Committee be a...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.