CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Wirral Borough Council
Policy and Resources Committee, Wednesday 22 July 2026

Capital Monitoring Quarter 1 (2026/27)

Approved Committee 6 papers

AI summaryWirral Policy and Resources Committee recommends Council approval of a revised £122.920 million Capital Programme for 2026/27, plus two new scheme bids and an aids and adaptations grant.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedRevised Capital Programme and new scheme funding
Money£122.920 millionRevised Capital Programme 2026/27
What happens nextCouncil to decideFinal approval at a later Council meeting
Who it affectsWirral Council and capital schemesRegeneration, neighbourhoods and services

What was decided

The Committee agreed to recommend to Council the revised Capital Programme of £122.920 million for 2026/27. Report P2

The Committee also agreed to recommend additional funding for the schemes set out in section 3.8 of the report. Report P3

Why

Regular monitoring and reporting of the Capital Programme allow timely decisions that can produce revenue benefits and improve financial control. Report 1.1

Several budget lines have been reprofiled into future years, and a new grant for aids and adaptations has been added, requiring a revised programme. Report 3.1, 3.4

What happens next

The recommendations will be referred to Full Council for final approval under the Constitution. Report P84, P85, P86

The Council's Contract Procedure Rules will be followed for any procurement needed for the schemes. Report P33

Future capital monitoring reports will continue to be brought to the relevant committees each quarter. Report 2.1, 4.1

The money

  • £122.920 million Revised Capital Programme for 2026/27 Report P2
  • £0.320 million Eastham Day Care Centre enabling works, Regeneration and Place Report P34
  • £0.075 million Cremated Remains Section extensions at Landican and Wallasey Cemeteries, Neighbourhoods Report P35
  • £6.071 million Aids, Adaptations and Disabled Facility Grant from MHCLG for 2026/27 Report P21, P22
  • £5.100 million Already in the Capital Programme as pipeline funding for the Disabled Facility Grant Report P22
  • £53.511 million Estimated Council borrowing required to finance 2026/27 capital schemes Report 4.2
  • £2.7000 million Regeneration Delivery Support funding, originally approved March 2024 Report P37
  • £13.757m LCRCA PSDS Decarbonisation grant removed from the Council's programme Report P38
  • £2.361m Remaining PSDS Decarbonisation scheme value in the Council's programme (participant contribution) Report P38

Options considered

  • Chosen: Quarterly capital monitoring reports. Standard practice; other reporting frequencies are possible but quarterly is normal. Report 2.1
  • Rejected: Not approving additional scheme funding under section 3.8. The Committee agreed to recommend approval to Council. Report P33

Implications

  • Financial: Borrowing of £53.511 million will create MRP and interest charges to the revenue budget from 2027/28, totalling £5.092 million in 2028/29 and peaking at £2.972 million of MRP in 2034/35. Report 4.2, P41, 4.3, 4.4, P48
  • Legal: Members must consider their fiduciary duty and the statutory duties to set and monitor a balanced budget under the Local Government Finance Act 1992 and the Local Government Act 2003. Report 5.1, 5.2, 5.6
  • Equalities: Both the public sector equality duty and the fiduciary duty to council taxpayers must be considered in budget decisions. Report 9.1, 9.2
  • Climate: The Capital Programme includes projects that support the Council's Climate Emergency Plan, such as energy efficient buildings and sustainable travel infrastructure. Report 10.1, 10.2
  • Risk: If a capital scheme is abandoned, any capitalised costs would have to be written off to the revenue budget as abortive costs. Report 7.3
  • Risk: Failure to deliver the Capital Programme is being mitigated through regular reviews by the Change Advisory Board and the Corporate Change Portfolio Board. Report 7.1, 7.5
  • Staffing: There are no additional staffing, ICT or asset resource requirements arising directly from this report. Report 6.1
  • Other: Community Wealth Building benefits are expected through regeneration projects that aim to create jobs, training and improved transport links. Report 11.1

Who and where

  • Wirral Council taxpayers Report 5.2
  • Directorates delivering the Capital Programme, including Regeneration and Place and Neighbourhoods Report P21, P34, P35
  • Day services users in Eastham Report P34
  • Users of Landican and Wallasey (Rake Lane) Cemeteries Report P35
  • Recipients of aids, adaptations and disabled facilities grants Report P21
  • Areas covered by the Birkenhead 2040 Framework regeneration work, including Seacombe, Liscard and New Ferry Report P37

Timeline

  • 2026/27: Capital Programme spending year covered by this report Report P2
  • Quarter 1 2026/27: New Disabled Facility Grant allocation of £6.071 million received from MHCLG Report P21
  • 2034/35: MRP cost on 2026/27 borrowing expected to peak at £2.972 million Report 4.3

Plain English for the jargon

  • MRP: Minimum Revenue Provision, the amount the Council charges to its revenue budget each year to repay capital borrowing.
  • Reprofiling: Moving capital budget from one financial year to another, usually because a scheme will not be completed in time.
  • Virement: Moving budget from one spending line to another within the Council's approved budget.
  • Annuity Method: A way of repaying borrowing that starts low and increases each year to reflect the time value of money; adopted by the Council on 19 December 2016.
  • PSDS: Public Sector Decarbonisation Scheme, a government programme for reducing carbon emissions in public buildings.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item29

Resolved

Resolved – That the Policy and Resources Committee recommends to Council the approval of: 1. the revised Capital Programme of £122.920 million for 2026/27. 2. additional funding for the schemes referred to in section 3.8 of the report.
Word for word from the decision Wirral published for this meeting. Source: democracy.wirral.gov.uk

Follow this further

Built from Wirral's papers

What the report saysPro

Report to Policy and Resources Committee

Recommendations

The Policy and Resources Committee is requested to recommend to Council the approval of:

1 the revised Capital Programme of £122.920 million for 2026/27.

2 additional funding for the schemes referred to in section 3.8 of this report. SUPPORTING INFORMATION

1.0REASON/S FOR RECOMMENDATION/S

1.1Regular monitoring and reporting of the Capital Programme enable decisions to be taken in a timely manner, which may produce revenue benefits and will improve financial control in Wirral Borough Council.

2.0OTHER OPTIONS CONSIDERED

2.1Other reporting frequencies could be considered, but quarterly reporting is a standard practice.

3.0BACKGROUND INFORMATION

3.1Tables 1 and 2 provide an update on the 2026/27 Capital Programme analysed on a Directorate and then Committee basis. A number of variations have arisen since the original Programme was agreed in March 2026. These include the reprofiling of expenditure into and out of financial years and the inclusion of additional grant funding. Appendix A of this report provides further analysis of the movement of the forecast programme across directorates during the year to date.

Table 1: Capital Programme 2026/27 Position by Directorate

Table 2: Capital Programme 2026/27 Position by Committee

3.1.2 As noted above, the main movements in this year’s Programme are in respect of reprofiling of budget into future years along with the inclusion of new funding and schemes into the Programme. A full breakdown can be found in Appendix A. 3.1.3 Such re-profiling reduces the borrowing costs incurred during the year (2026/27) and also delays the resultant Minimum Revenue Provision (MRP) charges into future years. Any delay in outputs will be monitored by project managers and practical implications reported to the appropriate committee.

3.2Reprofiling of expenditure

3.2.1 Regular meetings are held with officers who are responsible for capital projects contained within the Programme. During these meetings assessments are made regarding the deliverability of the schemes and their budgetary requirement for the year. These assessments are reflected in the forecast Capital outturn provided through the quarterly update reports to Members. Should it be assessed that a scheme will continue into the next financial year, or beyond, budget is reprofiled as deemed appropriate at that time.

3.2.2 A scheme should not be paused or deferred into a future year if this action were to lead to avoidable detrimental effects on the Council. The project lead officers determine if a scheme is appropriate for reprofiling and manage any risks or negative impacts associated with this decision. Schemes that are part or fully funded from grant require additional consideration before reprofiling, so as not to compromise the conditions of the grant agreements, which may jeopardise the scheme funding.

3.2.3 Within Quarter 1 several schemes had funding reprofiled to reflect project delivery expectations for this financial year, with the majority of schemes changes profiled into 2027/28. Should a scheme encounter a significant change then the future options for that scheme will be reported via the relevant committee and subject to the appropriate governance routes for ratification.

3.3Scheme Updates

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme MovementsAppendix A 53 KB Download
PDF
Capital Bid Seeking Approval for FundingAppendix B 66 KB Download
PDF
Capital Receipts Generated 202627Appendix C 43 KB Download
PDF
Prudential Indicators 202627Appendix D 112 KB Download
PDF
Revised Capital Programme at Quarter 1 202627Appendix E 155 KB Download
PDF
Capital Monitoring Quarter 1 (2026/27)Report 196 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

20 of 20 attended
PB
Councillor Paula BasnettChair, present
JM
Councillor Julie McManusVice-Chair, apologies, sent representative
RM
Councillor Ruth MolyneuxSpokesperson, present
SR
Councillor Simon R MountneySpokesperson, present
CC
Councillor Chris CarubiaSpokesperson, present
KH
Councillor Kathy HodsonSpokesperson, present
SB
Councillor Stephen BennettCommittee Member, present
AD
Councillor Angela DaviesCommittee Member, present
SF
Councillor Steve FoulkesCommittee Member, present
TM
Councillor Tony MurphyCommittee Member, present
SP
Councillor Sue Powell-WildeCommittee Member, present
MS
Councillor Mark SkillicornCommittee Member, present

All 20 on the meeting page

On this subject at Wirral

Search all
  1. Capital Monitoring Quarter 1 (2026/27)This decision
  2. Capital Monitoring Quarter 3 2025/26Approved
  3. Capital Monitoring Quarter 3 2025/26Approved
  4. 2025-26 capital monitoring quarter 2Approved
  5. 2025-26 Capital Monitoring Quarter 2Approved
  6. Capital Monitoring Quarter 1 2025/26Approved

More from Wirral Policy and Resources Committee

All decisions
MeetingDecisionOutcome
22 Jul 2026 New Wirral PlanResolved – That the Policy and Resources Committee endorsed the new Wirral Plan for 2027 to 2031 and recommended it f... Approved Open
22 Jul 2026 Strategic Land Disposals for Affordable HousingResolved – that 1. the disposal of Council-owned land through a Strategic Housing Partnership, under the Wirral Affor... Approved Open
22 Jul 2026 Network Strategic Partner for Wide Area Network delivery and supportDecision affecting all wards. Resolved – That Policy and Resources Committee authorises the award of a contract to Th... Decided Open
22 Jul 2026 Transport for the City Region Resource FundingResolved – that, 1. the request that had been submitted to the Liverpool City Region to support the delivery of the T... Noted Open
22 Jul 2026 Parking Strategy RefreshResolved – that the Policy & Resources Committee, 1. Notes the resolution of the Environment, Climate Change and Tran... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies