PROPOSED PHASING OUT OF PAY AND DISPLAY MACHINES

Approved Committee 1 paper

AI summaryWirral's Environment, Climate Emergency and Transport Committee has approved phasing out pay and display parking machines by the end of 2029-30, ending a contract worth about £120,000 a year and avoiding around £1 million in capital costs.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedPhased decommissioning by end of 2029-30
MoneyUp to £1 millionCapital cost avoidance over coming years
What happens nextPhased removal from 2026/27Complete by end of 2029-30
Who it affectsWirral parking usersEspecially those without smartphone access

What was decided

Approved the principle of decommissioning pay and display machines in a rolling programme, with the aim to complete the whole process by the end of financial year 2029-30. Report P1, P2, 3.6

Authorised the Director of Neighbourhoods to take all necessary steps to implement the decommissioning. Report P2

Decision carried by 7 votes to 2.

Why

Pay and display machines are around nine years old, increasingly expensive to maintain, and many rely on 3G connectivity that is being phased out nationwide. Report 1.1, 1.2, 1.3, 3.2

Cashless payments have grown steadily and now make up the majority of transactions; app and telephone payments are around 13 per cent of transactions and rising. Report 1.4, 3.3, P14, P15

Removing machines saves on staffing, the supplier contract and maintenance, and avoids significant capital outlay on replacements. Report 1.1, 4.1, 4.2, 4.4

What happens next

Year 1, 2026/27: new parking locations use relocated machines from low-use areas; no new machines introduced in new charged areas. Report 3.6, P19

Year 2, 2027/28: reduce to a maximum of one machine per car park or street; Year 3, 2028/29: reduce to one machine per area; Year 4, 2029/30: complete removal. Report 3.6, P20, P21, P22

The Director of Neighbourhoods will lead implementation, with the existing supplier contract ended in line with the proposed timescales. Report P2, 4.5, 5.1

The money

  • £5,000 Approximate cost to procure and install one new pay and display machine Report 2.3, 4.4
  • £700,000 Estimated capital cost of replacing existing pay and display stock Report 2.3
  • £120,000 Current annual value of pay and display contract Report 3.2, 4.2
  • £50,000 Anticipated annual staffing saving from deleting one FTE post Report 4.2
  • £120,000 Anticipated annual saving from ending the pay and display contract Report 4.2
  • £10,000 Anticipated annual maintenance and repair saving Report 4.2
  • £1 million Possible cost avoidance over coming years depending on other parking charge decisions Report 4.4

Options considered

  • Rejected: Do nothing. Machines are aging, maintenance costs and failure risk will rise, with potential loss of parking revenue. Report 2.2
  • Rejected: Replace existing pay and display machines. Capital cost around £700,000 plus ongoing contract, servicing and maintenance costs; does not address long-term challenges. Report 2.3
  • Chosen: Phase out pay and display machines and move to cashless only. Saves on staffing, contract and maintenance; aligns with the trend away from pay and display; reduces street clutter. Report P1, P2, 1.1, 4.2

Implications

  • Financial: Annual savings of around £50,000 (staffing), £120,000 (contract) and £10,000 (maintenance), plus possible capital cost avoidance of up to £1 million. Report 4.2, 4.4
  • Staffing: One full-time equivalent post in Neighbourhood Services is expected to be deleted as machine numbers reduce. Report 4.2, 6.1
  • Equalities: Risk of excluding older drivers or those without smartphones; mitigations include a phone payment line, clear signage, in-person payment points where appropriate, pre-registered accounts, community workshops and a four-year transition. Report 5.2, 7.3, P38, 9.3, 9.4
  • Legal: No contractual issues expected; the existing supplier contract can be ended in line with the proposed phasing. Report 5.1
  • Climate: Removal reduces emissions from maintenance vehicles, paper tickets and machine components such as batteries. Report 10.1
  • Risk: Mitigation planned for mobile signal and connectivity issues, confusion from multiple parking apps, and possible reputational or community backlash. Report 7.3, P38

Who and where

  • Motorists using Wirral's 140 on-street and off-street pay and display parking places Report 3.0, 3.5
  • Older drivers and people without access to a smartphone or cashless payment methods Report 5.2, 7.3, P38
  • One full-time equivalent maintenance post within Neighbourhood Services Report 4.2, 6.1
  • Users of the Grange and Pyramids multi-storey car parks in Birkenhead, where cash payment will remain Report 3.8
  • The supplier of pay and display machines, spare parts and back-office payment systems Report 3.2, 5.1

Timeline

  • 2026-03-10: Environment, Climate Emergency and Transport Committee approves the phased decommissioning by 7 votes to 2.
  • 2026/27 (Year 1): No new pay and display machines introduced; new locations served by relocated machines from low-use areas. Report 3.6, P19
  • 2027/28 (Year 2): Maximum of one machine retained per car park or street. Report 3.6, P20
  • 2028/29 (Year 3): Maximum of one machine retained per area, for example one across West Kirby or one at Pye Road, Heswall. Report 3.6, P21
  • 2029/30 (Year 4): All remaining pay and display machines removed by the end of the financial year. Report 3.6, P22

Plain English for the jargon

  • Pay and display: Parking payment machines where users buy a printed ticket to display in their vehicle.
  • Cashless parking: Payment for parking by app, phone or contactless card rather than cash at a machine.
  • JustPark: The digital phone payment provider used by Wirral for cashless parking; a 6p booking fee applies.
  • FTE: Full-time equivalent staff post.
  • Equality Impact Assessment (EIA): A tool used by the council to check whether a policy or decision could discriminate against protected groups.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item79

Resolved

Resolved (7:2) – That the Environment Climate Emergency and Transport Committee approves: (1) the principle of the de-commissioning of pay and display parking payment machines in a rolling programme with the aim to complete the whole process by the end of the financial year 2029-30 with a view to providing alternative payment methods in accordance with the sequence referred to in Section 3.6 of the report; and (2) authorises the Director of Neighbourhoods to take all necessary steps to implement the de-commissioning of pay and display parking payment machines as referred to in recommendation 1.
Word for word from the decision Wirral published for this meeting. Source: democracy.wirral.gov.uk

Follow this further

Built from Wirral's papers

What the report saysPro

Report to Environment, Climate Emergency and Transport Committee

Recommendations

The Environment Climate Emergency and Transport Committee is recommended to approve:

(1) the principle of the de-commissioning of pay and display parking payment machines in a rolling programme with the aim to complete the whole process by the end of the financial year 2029-30 with a view to providing alternative payment methods in accordance with the sequence referred to in Section 3.6 of the report; and (2) authorise the Director of Neighbourhoods to take all necessary steps to implement the de commissioning of pay and display parking payment machines as referred to in recommendation 1. SUPPORTING INFORMATION

Reasons for recommendations

1.1Pay-and-display machines are becoming increasingly more expensive to run, technically outdated, subject to occasional vandalism, and less aligned with modern payment preferences. The council can save money, reduce street clutter, and modernise parking services by transitioning to cashless and digital-only options.

1.2Many older pay‑and‑display parking machines rely on 3G connectivity, which is now being phased out nationwide. Upgrading these machines to 4G or 5G is costly and, in many cases, not financially viable. As a result, local authorities that have not already invested heavily in upgrades have either removed their machines or are planning to withdraw them over the coming years.

1.3Pay-and-display machines require regular maintenance and repairs due to wear or damage. This increases repair costs and service downtime. Removing machines reduces this expenditure significantly.

1.4There has been a steady increase in App-based payments. 1.5 Reducing physical street furniture will improve pavement accessibility, streetscape appearance and pedestrian mobility. Pay-and-display machines add clutter and maintenance burdens.

2.0OTHER OPTIONS CONSIDERED

2.1As part of this proposal a number of alternative options have been considered to enhance service delivery and reduce costs.

2.2Option 1 – Do Nothing – This option is not recommended. The current stock of Pay and Display machines is now around nine years old, approaching the end of their typical 15-year operational lifespan. As the machines continue to age, maintenance requirements are expected to increase year-on-year, resulting in higher operational costs, a greater risk of equipment failure, and potential loss of parking revenue.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
PROPOSED PHASING OUT OF PAY AND DISPLAY MACHINESReport 182 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 14 attended
EG
Councillor Elizabeth GreyChair, present
MB
Councillor Max BoothVice-Chair, present
GJ
Councillor Gail JenkinsonSpokesperson, apologies
AB
Councillor Allan BrameSpokesperson, present
SF
Councillor Steve FoulkesCommittee Member, present
PM
Councillor Paul MartinCommittee Member, apologies
AA
Councillor Ann AinsworthCommittee Member, apologies
JJ
Councillor Jennifer JohnsonCommittee Member, present
HG
Councillor Harry GormanCommittee Member, present
GD
Councillor Graham DaviesSpokesperson, absent
CW
Councillor Craig Walsh - McDonaldDeputy, present as substitute
DC
Daphne CourtenageOfficer, expected

All 14 on the meeting page

More from Wirral Environment, Climate Emergency and Transport Committee

All decisions
MeetingDecisionOutcome
8 Jul 2026 2026-27 budget monitoring report quarter 1Resolved – That the Environment, Climate Emergency and Transport Committee notes: 1. the forecast revenue position fo... Decided Open
8 Jul 2026 Carbon Budget Performance Report 2025-26It was agreed that the following two agenda items, “” and “Environment and Climate Emergency Action Plan Progress Rep... Agreed Open
8 Jul 2026 Environment and Climate Emergency Action Plan Progress Report 2025-26It was agreed that the two agenda items, “Carbon Budget Performance Report 2025-26” and “Environment and Climate Emer... Agreed Open
8 Jul 2026 Environment, climate emergency and transport performance reportResolved – That the Environment, Climate Emergency and Transport Committee notes the content of the report and highli... Decided Open
8 Jul 2026 Work ProgrammeIt was agreed that items requested on weed treatment provisions would be a part of the Hot House briefings. Briefing ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies