BIRKENHEAD WATERFRONT AND SURROUNDS SCHEME DELIVERY IMPLEMENTATION
ApprovedCommittee4 papers
AI summaryWirral's Environment, Climate Emergency and Transport Committee approved updated proposals for the Birkenhead Waterfront and Surrounds scheme, total funding £25,654,543, subject to the final tender being within budget.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedFinal tender and contract award must fit budget
Money£25,654,543 totalTwo central government funding streams
What happens nextSeparate committee decision on contract awardAfter redesign completes in March 2026
Who it affectsBirkenhead residents, visitors and businessesFrom Conway Street roundabout to Woodside Ferry Terminal
What was decided
The committee approved the updated proposals for the Birkenhead Waterfront and Surrounds project as set out in Appendix 1 of the report.
The committee approved implementation of the scheme.
Approval is subject to the final tender submission and contract award being within the allocated budgetary provision.
Why
The scheme supports increased sustainable movement and connectivity and aligns with the Council Plan 2023 to 2027, the Cool Wirral Strategy, the Places for People strategy and the Birkenhead 2040 Framework. Report 1.1
Funding is ringfenced for active travel and cannot be used for any other purpose, and the funding partners have already approved the project. Report 3.6
An earlier cost plan came in significantly over budget because of inflation, sub-contractor costs and risks from utilities and ground conditions, prompting a redesign and re-scoping with the contractor John Sisk and Sons. Report 3.7
What happens next
Redesign work that began on 5th January 2026 is due to complete in March 2026, with the updated design frozen after internal and stakeholder feedback.
An updated cost plan will be produced and reviewed against contract options, then confirmed with the supply chain.
A separate decision will be sought from this committee on entering into a construction contract, ahead of a collective opening of the area agreed with partners for Spring 2028. Report 3.1
The money
£12,953,543 Local Regeneration Fund from MHCLG, successor to Pathfinder Report 4.1, P20
£12,701,000 Levelling Up Fund Active Travel administered by LCRCA Report 4.1, P20
£25,654,543 Total of the two funding streams for the project Report 4.1, P20
Options considered
Rejected: Reallocate the funding to a different scheme in the borough and not deliver the project. Could harm the council's reputation on regeneration and active travel, reduce future funding, and affect related schemes such as the Woodside Ferry and Battle of the Atlantic attraction. Report 2.1
Rejected: Deliver only part of the proposed project instead of a full redesign. Would reduce impact and effectiveness, require funding to be returned to the Liverpool City Region Combined Authority, and damage the council's reputation. Report 2.2
Chosen: Approve the updated full scheme, as set out in Appendix 1. Brings project costs within budget while retaining active travel, public realm and public transport benefits. Report 2.2
Implications
Financial: The construction contract value will be lower than the £25,654,543 total once PCSA, internal and external staff costs, and risk and contingency are deducted, and must be within the allocated budgetary provision. Report 4.2, 4.3
Financial: Some original funding outputs may have to be altered; any changes will need endorsement by the S151 officer.
Legal: The council has duties under the Highways Act 1980, Road Traffic Regulations Act 1984, Road Traffic Act 1988, Local Government Act 1972 and Traffic Management Act 2004, and Traffic Regulation Orders may be required for changes to waiting and loading restrictions. Report 5.1
Equalities: An Equality Impact Assessment titled 'EIA Birkenhead Waterfront and Surrounds Scheme Phase 3 Consultation' is in place and is still valid. Report 9.3
Climate: The scheme aims to plant at least 66 new trees, with thousands more plants and shrubs, and is expected to help reduce greenhouse gas emissions by enabling walking, wheeling and public transport use. Report 10.4, 10.5, 10.9
Climate: Tree losses have been reduced from 56 to 21 since the previous update to the committee on 16th June 2025, and a line of nine Liquidambars on Bridge Street will now be retained. Report 10.6
Risk: Construction contract risk is set out in the exempt Appendix 3, which is withheld under Schedule 12A of the Local Government Act 1972. Report 7.6, P66, P68
Risk: Cumulative traffic management from this and other regeneration projects could add pressure on the local highway network, with some disruption considered unavoidable. Report 7.7, 7.8
Staffing: An NEC4 accredited Project Manager and Site Supervisor will be appointed through a separate procurement exercise, with resources shifting from design to implementation. Report 6.1
Who and where
Residents and visitors in central Birkenhead, including the 40% of households in Central Birkenhead and Tranmere who do not own a car Report 3.5
Users of Hamilton Square Station, Woodside Ferry Terminal and the new Battle of the Atlantic visitor attraction Report 3.1, 3.4, P16, P18
Local businesses along Argyle Street including Future Yard, Make CIC and the Joy project, and the Start Yard business incubator Report 3.2
Visitors to Birkenhead Priory Report 3.2
Pedestrians, cyclists, wheelers, public transport users and motorists using the scheme area Report 3.5, 3.6
Timeline
Spring 2023: First formal consultation on the scheme Report 8.1
Winter 2024: Second formal consultation on the scheme Report 8.1
2 April to 27 April 2025: Phase 3 consultation on proposed Traffic Regulation Orders via the council's Have Your Say website Report 8.3
16 June 2025: Previous update on the scheme to this committee Report 10.6, P88
October 2025: Contractor released a project cost plan that was significantly over budget Report 3.7
24 December 2025: PCSA extension with John Sisk and Sons approved by officer decision Report P89
5th January 2026: Redesign of the scheme began
March 2026: Redesign is due to complete
10 March 2026: Committee approved updated proposals, subject to budget
Spring 2028: Agreed collective opening of the area including ferry services, in line with the funding deadline Report 3.1
Plain English for the jargon
PCSA: Pre Construction Services Agreement, a contract for design and pricing work before the main construction contract is awarded
LRF: Local Regeneration Fund, the successor to Pathfinder, awarded by the Ministry of Housing, Communities and Local Government
MHCLG: Ministry of Housing, Communities and Local Government
LCRCA: Liverpool City Region Combined Authority
RIBA Stage 4: Detailed design stage of the Royal Institute of British Architects work stages
TRO: Traffic Regulation Order, a legal order used to control or restrict traffic on a road
EIA: Equality Impact Assessment, an assessment of how a policy or scheme affects people with protected characteristics
CATN: Core Active Travel Network adopted by the council in January 2024
LTN 1/20: Local Transport Note 1/20, the government's cycle infrastructure design guidance
NEC4: A standard form of construction contract published by the Institution of Civil Engineers
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item82
Resolved
Resolved – That the Environment, Climate Emergency and Transport Committee approves the updated proposals for Birkenhead Waterfront and Surrounds project, as set out in Appendix 1 of the report, and the implementation of the scheme, subject to final tender submission and contract award being within allocated budgetary provision.
Word for word from the decision Wirral published for this meeting.Source: democracy.wirral.gov.uk
Report to Environment, Climate Emergency and Transport Committee
Reasons for recommendation
1.1The Birkenhead Waterfront and Surrounds scheme supports increased levels of sustainable movement and connectivity within the wider context of sustainable economic growth and regeneration, delivery of the Council Plan 2023-2027, the Cool Wirral Strategy and the Places for People strategy, as well as other strategies to reduce health inequalities and improve health and wellbeing, air quality and sustainable economic growth and regeneration of the borough, including the Birkenhead 2040 Framework , the Environment and Climate Emergency Declaration and the Local Plan.
2.0OTHER OPTIONS CONSIDERED
2.1Allocate the funding to a different scheme in the Borough and decide to not deliver the Birkenhead Waterfront and Surrounds project. This is not considered appropriate as failure to deliver against the approved programme could result in reputational issues for the Council in terms of its commitment to regeneration, active travel and improved public transport which could result in future funding allocations being reduced. Also, this would have implications on the wider programme if works weren’t delivered i.e. impact visitor numbers for the improved Woodside Ferry or the new Battle of the Atlantic attraction.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Climate Emergency and Transport Committee at Wirral and we tell you when its next papers are published, before the meeting rather than after it.
Carbon Budget Performance Report 2025-26It was agreed that the following two agenda items, “” and “Environment and Climate Emergency Action Plan Progress Rep...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.