Audit and Risk Management Committee, Tuesday 4 November 2025

Corporate Risk Management Update

Decided Finance 4 papers

AI summaryWirral's Audit and Risk Management Committee noted the Corporate Risk Management Update and received assurance that the Corporate Risk Register was endorsed by the Policy and Resources Committee on 22 October 2025, with a workshop to follow.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCorporate Risk Register endorsed by Policy and Resources Committee
MoneyNot stated
What happens nextWorkshop to be convenedTo consider risk register alignment to Wirral Plan
Who it affectsCouncil risk management frameworkProvides independent assurance on risk management

What was decided

The committee noted the Corporate Risk Management Update report.

The committee noted its own terms of reference, which require it to provide independent assurance on the adequacy of the risk management framework. Report P21

The committee received assurance that the Policy and Resources Committee endorsed the Corporate Risk Register on 22 October 2025 and that a workshop will consider the register and its alignment to the Wirral Plan. Report P25

Why

The committee's terms of reference require it to consider the effectiveness of risk management arrangements and provide assurance on them. Report P21

The Council has a statutory responsibility under the Accounts and Audit Regulations (England) 2015 to have arrangements in place for the management of risk. Report 5.2

The report says that without robust risk management there is a danger the Council will fail to identify, understand and monitor key risks, leading to missed opportunities and ineffective assurance. Report 7.1

What happens next

A workshop is to be convened to consider the Corporate Risk Register and its alignment to the Wirral Plan.

The committee will continue to receive quarterly risk management reports under its terms of reference. Report P21

Options considered

  • Chosen: Note the report
  • Chosen: Note the committee's terms of reference on risk management assurance
  • Chosen: Receive assurance on the Corporate Risk Register endorsement and forthcoming workshop Report P25

Implications

  • Financial: No direct financial implications, but failure to manage risks effectively could put the Council's financial resilience at risk. Report 4.1
  • Legal: The Council has a statutory duty under the Accounts and Audit Regulations (England) 2015 to have risk management arrangements in place. Report 5.2
  • Risk: Without robust risk management, key strategic and operational risks may not be identified or considered in decision-making. Report 7.1
  • Equalities: The Council has a legal requirement not to discriminate; Equality Impact Assessments are used to identify steps to promote equality. Report 9.1
  • Climate: The report is expected to have no impact on emissions of greenhouse gases. Report 10.1, P12
  • Other: No direct community wealth implications, but effective risk management will support economic, social and environmental justice for residents. Report 11.1
  • Other: No direct crime and disorder implications. Report 12.1

Who and where

  • Wirral Council's risk management framework and decision-making Report P21, 7.1
  • Wirral residents, through protection of finances and service provision Report 11.1

Timeline

  • 25 March 2025: Previous Risk Management Assurance and Corporate Risk Update considered. Report P24
  • 22 October 2025: Policy and Resources Committee endorsed the Corporate Risk Register. Report P25
  • 2025-11-04: Audit and Risk Management Committee noted the update.
  • To be convened: Workshop to consider the risk register and its alignment to the Wirral Plan.

Plain English for the jargon

  • CRR: Corporate Risk Register, the council's record of key strategic and operational risks.
  • CIPFA: Chartered Institute of Public Finance and Accountancy, a professional accountancy body.
  • SOLACE: Society of Local Authority Chief Executives.
  • EIA: Equality Impact Assessment, a tool to identify steps to promote equality.
  • Wirral Plan: The council's corporate plan setting out its priorities.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item31

Resolved

Resolved – That the Audit and Risk Management Committee 1. notes the report; 2. notes that the terms of reference of the Audit and Risk Management Committee is to provide independent assurance on the adequacy of the risk management framework; and 3. receives assurance from the fact that the Policy & Resources Committee reviewed and endorsed the Corporate Risk Register on 22 October 2025 and a workshop is to be convened to consider the risk register and its alignment to the Wirral Plan.
Word for word from the decision Wirral published for this meeting. Source: democracy.wirral.gov.uk

Follow this further

Built from Wirral's papers

What the report saysPro

Report to Audit and Risk Management Committee

AUDIT AND RISK MANAGEMENT COMMITTEE Tuesday, 4 November 2025

REPORT TITLE: CORPORATE RISK MANAGEMENT UPDATE REPORT OF: DIRECTOR OF FINANCE

REPORT SUMMARY

This report provides an update on risk management activity including the quarterly update of the Corporate Risk Register.

This matter affects all Wards within the Borough. It is not a key decision.

The risk management activity detailed within the report supports the following priority or delivery theme from Wirral Council’s Plan 2023-27:

 Working together to create a more efficient, effective and accessible council.

RECOMMENDATION/S

The Audit and Risk Management Committee is recommended to note the report. SUPPORTING INFORMATION

1.0REASON/S FOR RECOMMENDATION/S

1.1To enable the committee to gain assurance that the Council understands it’s most significant risks, and they are recorded, reported and managed in line with the arrangements outlined in the Council’s Risk Management (RM) Framework.

2.0OTHER OPTIONS CONSIDERED

2.1No other options considered appropriate as failure to report this information would demonstrate ineffective governance and non-compliance with professional best practice.

3.0BACKGROUND INFORMATION

3.1Risk management forms part of many of the seven core principles within the best practice guidance, ‘Delivering Corporate Governance in Local Government: Framework.

3.2The Council’s RM Framework outlines the Council’s commitment to maintaining effective governance arrangements which includes a clear understanding of the risks it faces, how they are managed and monitored, and their potential impact on the ability to deliver the Council Plan.

3.3The RM Framework articulates the risk hierarchy and ownership of risk through the organisation includes the roles and responsibilities of committee, management levels and individual employees.

3.4A key component of risk management across the Council is the Corporate Risk Register (CRR) and the hierarchy of risk registers below it. As outlined in the RM Framework the CRR is owned by the Senior Leadership Team (SLT) with risk owners identified for each risk. As such the CRR is subject to a regular review by the SLT with strategic overview by Policy and Resources (P&R) Committee linking with its position of whole council view of budget and performance, as per the committee terms of reference.

3.5The regular review of all levels of risk register helps to support and demonstrate risk- based sound decision making as well as allowing for them to be dynamic and reflect the changing situation the Council operates within. As a result of these reviews risks can be escalated or devolved up and down the risk hierarchy. A diagram of the relationships and flow of risks taken from the Risk Management Framework is available in Appendix 3.

3.6The CRR was reviewed and discussed at SLT on the 8th of October and subsequently reported to P&R Committee on the 22nd of October.

Corporate Risk Register Update

3.7The CRR consists of potential risks that may be from a variety of sources including:  Strategic or large-scale operational risks which have the potential to impact on the service delivery of the Council’s priorities as laid out in the Council Plan; due to financial, reputational, or other resource impacts and requirements.  Require input or support from SLT to assist in the mitigating controls.  Have cross directorate impacts and treatments therefore need a “sponsor” to support and monitor.  Any risks to be escalated from Directorate or Programme Risk Registers following discussion at DMTs or Boards.  The Corporate Risk Register does not include specific or general risks around the large-scale projects and programmes; these are managed and monitored through the Programme Office and reported to the respective programme board and/or Investment and Change Board. These risks can be escalated to SLT at any time for consideration and inclusion in the CRR.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Corporate Risk RegisterAppendix 1 465 KB Download
PDF
Glossary of Terms used within the CRRAppendix 2 45 KB Download
PDF
Risk relationships and Reporting LinesAppendix 3 435 KB Download
PDF
Corporate Risk Management UpdateReport 145 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 9 attended
HC
Councillor Helen CameronChair, present
MS
Councillor Mike SullivanVice-Chair, present
JB
Councillor Jo BirdSpokesperson, present
SK
Councillor Stuart KellySpokesperson, present
JW
Councillor Jerry WilliamsCommittee Member, apologies, sent representative
JJ
Councillor Jennifer JohnsonCommittee Member, present
JB
Joanne ByrneIndependent Persons, absent
JS
Councillor James Stewart LaingDeputy, present
GM
Councillor Grahame McManusDeputy, present as substitute

On this subject at Wirral

Search all
  1. Corporate Risk Management UpdateThis decision
  2. Assurance Mapping Against the Corporate Risk RegisterNoted
  3. Risk Management Assurance and Corporate Risk UpdateNoted
  4. Corporate risk management updateNoted
  5. Corporate Risk Management UpdateNoted
  6. Corporate Risk Management UpdateNoted

More from Wirral Audit and Risk Management Committee

All decisions
MeetingDecisionOutcome
24 Jun 2026 External Audit Plan for Wirral Council 2025-26Resolved – That the external audit plan for Wirral Council’s Statutory financial statements for 2025/26 as prepared b... Noted Open
24 Jun 2026 External Audit Plan for Merseyside Pension Fund 2025-26Resolved – That the external audit plan for the Merseyside Pension Fund’s Statutory financial statements for 2025/26 ... Noted Open
24 Jun 2026 Annual governance statement 2025/26Resolved – That the draft Annual Governance Statement for 2025/26, including the actions planned in 2026/27 to addres... Approved Open
24 Jun 2026 Birkenhead town centre management action plan updateResolved – That 1. The progress made to date in implementing the Birkenhead Town Centre Management Action Plan recomm... Noted Open
24 Jun 2026 Annual cctv surveillance activity reportResolved – That the report be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies