Executive, Thursday 13 November 2025 at 7.00pm

Budget Monitoring Q2 2025-26 EXE25-039

Noted Executive 2 papers

AI summaryWoking Borough Council Executive noted the 2025/26 Quarter 2 forecast showing a General Fund underspend of £0.905m, with the Corporate Leadership Team to keep finding mitigations to stay within the budget set on 3 March 2025.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedGeneral Fund and Housing Revenue Account outturn noted
Money£0.905m General Fund underspend forecastHRA forecast reserves of £6.366m at year-end
What happens nextCLT to identify further mitigationsQuarterly monitoring continues to Executive
Who it affectsCouncil-wide General Fund and HRA budgetsIncludes group companies under debt standstill

What was decided

The Executive noted the 2025/26 Quarter 2 revenue and capital outturn forecasts for the General Fund and Housing Revenue Account, and noted that the Corporate Leadership Team will continue to identify mitigations so net 2025/26 expenditure stays within the budget approved by Full Council on 3 March 2025. Report P4, P5

The reason given is that containing outturn within budget is essential to maintain financial control and to support the journey to financial sustainability. Report 2.2

Why

The report sets out material financial issues identified since the 2025/26 budget was set, based on income and expenditure to the end of September 2025 and discussions with directorate budget managers. Report 1.1, 3.3

Service budgets are forecast to overspend by £2.197m, offset by a £3.102m underspend within corporate items, mainly from lower net interest costs, giving a net General Fund underspend of £0.905m. Report 6.1, 6.2, P22

What happens next

The Corporate Leadership Team will keep identifying measures to mitigate forecast overspends and find in-year savings, with particular risks around parking income, homelessness, benefits and investment income. Report P26, P5

Budget monitoring, including the capital programme, will be reported to the Executive on a quarterly basis, with monthly summary reports to the Corporate Leadership Team. Report 5.1

Forecasts will continue to be refined using the latest available information from budget managers. Report 4.5

The money

  • £0.905m Projected net General Fund underspend for 2025/26 Report 4.1, 6.1, P40
  • £2.197m Forecast service budget overspend against net service budgets of £13.740m Report 6.2
  • £3.102m Forecast underspend within Corporate Items, mainly treasury net interest Report P22
  • £1.049m Revenue and Benefit Services overspend Report P13
  • £0.701m Parking Services overspend Report P14
  • £0.388m Financial Services overspend from interim staffing during transition to permanent recruitment Report P15
  • £0.224m Environmental Health and Housing Standards overspend due to slippage in the new HMO licensing scheme Report P16
  • £0.187m Legal Services overspend, including costs for expert advice on complex historical matters Report P17
  • £0.174m Support Services overspend linked to Community Asset Transfers at St Mary's and Park View Report P18
  • £0.435m Leisure Service underspend from the new contract Report P23
  • £0.213m Election Services underspend Report P24
  • £2.6m Recovered from group companies in 2025/26 through cash sweeps, applied to mitigate debt increases Report 4.3
  • £6.366m Forecast closing HRA reserves at end of 2025/26, including £4.491m HRA forensic review adjustment Report 4.4, P29, 10.2, P133
  • £3.608m Total General Fund and HRA capital spend to date against full year budget of £22.982m Report 4.6, P67
  • £0.109m Forecast underspend on the General Fund capital programme for 2025/26 Report 9.1
  • £3.450m Approved budgeted spend expected to slip from 2025/26 into future years across capital programmes Report 9.1, P67
  • £6.902m Flexible use of capital receipts approved to fund the Improvement and Recovery Programme, with forecast £0.382m under the allocation Report 8.1, P61, P62

Options considered

  • Chosen: Note the 2025/26 Quarter 2 revenue and capital outturn forecasts for the General Fund and Housing Revenue Account. Recommended in the officer report to keep the Executive informed of the financial position Report P4
  • Chosen: Note that the Corporate Leadership Team will continue to identify mitigations to contain net 2025/26 expenditure within the approved budget. To maintain financial control and support the journey to financial sustainability Report P5, 2.2

Implications

  • Financial: General Fund forecast net underspend of £0.905m, with service overspends of £2.197m offset by £3.102m underspend in Corporate Items, mainly from lower net interest costs. Report 4.1, 6.1, 6.2, P22
  • Financial: HRA forecast adverse variance of £0.728m, with planned contribution to reserves reduced from £0.966m to £0.238m and forecast closing reserves of £6.366m after the £4.491m HRA forensic review adjustment. Report 4.4, 10.2, P29, P133
  • Risk: Risks remain around parking income, demand-led homelessness pressures, benefit services and investment income, with forecasts expected to change over the remainder of the year. Report P26
  • Financial: Debt standstill with group companies remains in place alongside a debt sweep, with £1.8m paid in July 2025 and a further £0.8m in August 2025, applied to reduce borrowing under the capitalisation direction. Report 4.3, 7.3
  • Other: Local government reorganisation implications will be considered in due course. Report 12.6

Who and where

  • Woking Borough Council General Fund services and directorate budget managers Report 1.1, 3.3
  • Housing Revenue Account tenants and leaseholders, with forecast adverse variance on heating and service charges of £483k and repairs and improvements overspend of £501k Report 10.3, 10.6, P125
  • Council-owned group companies, subject to the ongoing debt standstill and cash sweep arrangements Report 4.3, 7.3
  • Residents and businesses in the borough affected by ongoing financial sustainability measures Report 12.5, 2.2

Timeline

  • 27 February 2025: Housing Revenue Account and Capital Programmes for 2025/26 approved by Council Report 3.1
  • 3 March 2025: 2025/26 revenue budget for Woking Borough Council approved by Council Report 3.1, P5
  • July 2025: Group companies cash sweep payment of £1.8 million to the Council Report 7.3
  • August 2025: Further group companies cash sweep payment of £0.8 million to the Council Report 7.3
  • End of September 2025 (Quarter 2): Position used for the Q2 outturn forecast in this report Report 1.1, 3.3
  • 13 November 2025: Executive considered and noted the Q2 2025/26 budget monitoring report Report P143
  • End of 2025/26: Forecast closing HRA reserves of £6.366m, including forensic review adjustment Report 4.4, P29, P133

Plain English for the jargon

  • General Fund: The main revenue account for a council's day to day services other than council housing
  • Housing Revenue Account (HRA): A ringfenced account that records income and spending on council housing
  • Outturn: The actual or forecast end of year financial position compared to budget
  • Capitalisation direction: Approval allowing a council to treat certain revenue spending as capital, often linked to exceptional financial support
  • Debt standstill: An arrangement suspending debt repayments from the Council's group companies to the Council
  • Cash sweep: Mechanism to recover cash from group companies to reduce the Council's borrowing
  • Improvement and Recovery Programme (IRP): A programme of work to improve the Council's financial position, funded by the flexible use of capital receipts
  • Flexible use of capital receipts: Government flexibility allowing councils to use proceeds from asset sales to fund revenue transformation costs
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

The Executive Resolved That ( i ) the Council’s 2025/26 Quarter 2 revenue and capital outturn forecasts for the General Fund and Housing Revenue Account be noted; and (ii) it be noted that the Corporate Leadership Team will continue to identify mitigations to enable net expenditure for 2025/26 to be contained within the budget approved at Full Council on 3 March 2025. Reason: Controlling the outturn within budget is essential to maintain financial control and to support the journey to financial sustainability.
Word for word from the decision Woking published for this meeting. Source: moderngov.woking.gov.uk

Follow this further

Built from Woking's papers

What the report saysPro

Report to Executive

Purpose of report

1.1This report sets out the 2025/26 budget monitoring position and presents outturn forecasts as at the end of September 2025. The report has been prepared in consultation with the Council’s budget managers.

Recommendations

2.1The Executive is requested to:

Resolve that

(i) The Council’s 2025/26 Quarter 2 revenue and capital outturn forecasts for the General Fund and Housing Revenue Account be noted; and

(ii) It be noted that the Corporate Leadership Team will continue to identify mitigations to enable net expenditure for 2025/26 to be contained within the budget approved at Full Council on 3 March 2025.

Reason for decision

2.2Controlling the outturn within budget is essential to maintain financial control and to support the journey to financial sustainability.

EXE25-039 Budget Monitoring Q2 2025-26

Background

3.1The 2025/26 revenue budget for Woking Borough Council was approved by Council at its meeting on 3rd March 2025. The Housing Revenue Account and Capital Programmes for 2025/26 had previously been approved by Council on 27th February 2025.

3.2The purpose of this report is to set out the latest forecast outturn position for 2025/26 for the Council’s General Fund and the Housing Revenue Account (HRA) and the actual spend to date for capital budgets.

3.3This monitoring report sets out the material financial issues identified since the 2025/26 budget was set based on the income and expenditure as at end of September 2025 (Quarter 2) and reflects discussions with directorate budget managers.

Executive summary

4.1This report provides commentary on the Council’s forecast revenue outturn position for 2025/26, which for the General Fund, indicates a projected underspend of £0.905m.

4.2The material forecast outturn variances are:

• Revenue and Benefit Services overspend of £1.049m. The adverse budget variance comprises two elements: a historical budget pressure of £707k, reflecting a net surplus of reimbursements, and a current imbalance of £354k between payments made and reimbursements received. This pressure has been partially offset by positive variance in other areas (£12k). The favourable monthly movement is primarily due to a revised forecast of payments out.

• Parking Services overspend of £0.701m due to elevated running costs (£572k) and a fees and charges income shortfall (£129k). The fees and charges pressure is mainly due to lower permit uptake and shortfall in anticipated Medium Term Financial Savings. Running cost pressures include elevated energy costs (£201k), facilities management and cleaning (£237k), and other costs (£134k). Demand for parking can fluctuates throughout the year, making forecasting challenging. Budget proposals for 2026/27 will seek to address the underlying parking budget shortfall going forward.

• Financial services overspend of £0.388m, primarily driven by interim staffing costs incurred during the transition to permanent recruitment. The favourable movement since Quarter 1 reflects a reduction in temporary staffing, as several roles have now been filled permanently. Additionally, some staff have reduced their working hours, contributing to the improved position.

• Environmental Health and Housing Standards overspend of £0.224m due to slippage in the implementation of the new House in Multiple Occupation (HMO) licensing scheme and associated income, which had originally been anticipated to start earlier in the year. Budget Monitoring Q2 2025-26

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Budget Monitoring Q2 2025-26 EXE25-039Report 341 KB DownloadRead as text
PDF
EXE25-039 Appendix D: Savings ValidationAppendix 253 KB Download

At this meeting

Whole meeting

Who was there

12 of 15 attended
AB
Councillor Ann-Marie BarkerChair, present
EN
Councillor Ellen NicholsonVice-Chair, apologies
SG
Councillor Steve GreentreeCommittee Member, present
IJ
Councillor Ian JohnsonCommittee Member, present
LL
Councillor Liam LyonsCommittee Member, present
LM
Councillor Louise MoralesCommittee Member, present
DR
Councillor Dale RobertsVice-Chair, present
RC
Richard CarrOfficer, present
SF
Stephen FitzgeraldOfficer, present
KF
Kevin FosterOfficer, apologies
BK
Beverley KucharOfficer, present
AO
Adesuwa OmoregieOfficer, present

All 15 on the meeting page

On this subject at Woking

Search all
  1. Budget Monitoring Q2 2025-26 EXE25-039This decision
  2. Budget Monitoring Q1 2026-27 EXE26-036Noted
  3. Budget Monitoring Draft Outturn 2025-26 EXE26-032Noted
  4. Budget Monitoring Q3 2025-26 EXE26-006Noted
  5. Budget Monitoring Q1 2025-26 EXE25-038Noted
  6. Budget Monitoring Q4 and Draft Outturn 2024-25 EXE25-025Noted

More from Woking Executive

All decisions
MeetingDecisionOutcome
16 Sep 2026 Foundation Strategic Authority (FSA) EXE26-093The Executive Resolved That (i) the current position regarding the proposed establishment of a Foundation Strategic A... Noted Open
16 Sep 2026 Housing Operational Policies EXE26-051The Executive Resolved That (i) the Asbestos Policy be approved; (ii) the Lift Policy be approved; and (iii) the Stra... Approved Open
16 Sep 2026 Lakeview Estate Refurbishment Scheme EXE26-057The Executive Resolved That ( i ) the contract for the Lakeview Estate Refurbishment Project works be awarded to the ... Decided Open
16 Sep 2026 Revenue Refunds, Credit Balances and Write-Back Policy EXE26-101The Executive Resolved That (i) the Revenue Refunds, Credit Balances and Write-Back Policy be approved; (ii) the Head... Approved Open
16 Sep 2026 Enforcement Agent Procurement EXE26-112The Executive Resolved That ( i ) the commencement of a procurement exercise for the provision of Enforcement Agent s... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies