AI summaryWoking Executive approves procurement start for Lakeview Estate refurbishment of 14 residential blocks, with works due to run from Spring 2026 through to 2029.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedVia LCP MW24-H framework mini-competition, single principal contractor
MoneyValue in exempt appendixBudget code LRWAYQ142, funded from HRA and Section 20 leaseholder contributions
What happens nextReturn to Executive for contract awardHead of Housing Assets authorised to progress procurement
Who it affectsLakeview Estate residents and 99 leaseholdersAcross 14 residential blocks following 2024 cladding removal
What was decided
Approval granted to commence procurement of a contractor to deliver the Lakeview Estate Refurbishment Scheme. Report P10
Procurement will be run through the London Construction Programme Housing Major Works framework (LCP MW24-H, Lot 2.3) by mini-competition. Report P11
Leaseholders will not be recharged for cladding or external wall system replacement, but will be recharged for other Qualifying Works such as windows, doors and roofing. Report P13, 1.5
Why
To meet statutory landlord duties for resident safety and building compliance, and replace temporary fire safety measures with permanent solutions. Report 3.2, 2.1
To address end-of-life components including roofs, windows and doors alongside the external wall systems. Report 3.3, 5.2
In 2024 combustible cladding was removed and a temporary external covering was installed; without a permanent solution the buildings will not remain fit for habitation. Report 5.1
What happens next
Run the mini-competition through the LCP MW24-H framework and return to the Executive for approval of the contract award. Report P12, 4.1
Carry out Section 20 leaseholder consultation with 99 affected leaseholders. Report 9.22, 9.23
Subject to approval, commence a phased, block-by-block construction programme from Spring 2026, running approximately 30 to 36 months through to 2029. Report 6.6, P20
Options considered
Rejected: Do nothing or delay the decision. Temporary measures would fail, leaving homes uninhabitable and escalating costs Report 7.2
Rejected: Use multiple contractors. Would increase risk, reduce efficiency and value for money, and add contract management burden Report 7.3
Rejected: Open procurement under the Procurement Act 2023. Would extend programme, increase internal resource demand, and add risk of unsuitable bidders Report 7.4
Chosen: Use the LCP MW24-H Lot 2.3 framework via mini-competition. Most advantageous route; pre-vetted supply chain, compliant, reduced programme time and risk Report 7.5, 6.4
Implications
Legal: Procurement under PCR 2015 via the LCP framework; Section 20 Landlord and Tenant Act 1985 consultation applies. Cladding costs cannot be recharged to leaseholders per Building Safety Act 2022 principle and MHCLG guidance, so these will be borne by the Housing Revenue Account. Report 9.1, 9.2, 9.3, 9.4, 9.5
Financial: Funded through the HRA capital programme (Budget Code LRWAYQ142) and Section 20 leaseholder contributions. Stringent budget monitoring will apply, and the project is included in the HRA 30-Year Business Plan. Report 9.8, 9.9, 9.10
Risk: Leaseholders may legally challenge Section 20 contributions, which could leave the Council liable for the full cost. Cost increases would add pressure to the HRA. Contractor underperformance risk mitigated through framework monitoring and contract management. Report 9.17, 9.18, 9.16
Climate: Refurbishment avoids the higher carbon impact of demolition and redevelopment. New external wall insulation, high-performance windows and doors, and roof replacements will improve thermal efficiency and lower fuel bills. Report 9.25, 9.26
Staffing: No additional Council staff are anticipated; external consultants are supporting procurement. Report 9.12
Other: Local Government Reorganisation: decision to refurbish may not align with a future unitary authority's plans, but the work is being commissioned ahead of LGR because of fire safety risk. Report 9.27, 9.28
Who and where
99 leaseholders at Lakeview Estate, who will be consulted under Section 20 Report 9.22, 9.23
Tenants and residents of the 14 residential blocks Report 6.1, P21
The wider Lakeview Estate community during the 30 to 36 month construction period Report 6.6
Timeline
2024: Combustible cladding removed from 14 blocks and temporary external covering and insulation installed Report 5.1
18 June 2025: Resident and Landlord Partnership Meeting held Report P67
21 August 2025: Public exhibition on Lakeview cladding works for leaseholders, tenants and other interested parties Report P68
Late 2025: Housing Leasehold Manager to be appointed to deliver Section 20 consultation Report 9.22
Spring 2026: Construction works expected to commence, delivered phased and block by block Report 6.6, P20
2026 to 2029: Construction programme across three consecutive financial years, approximately 30 to 36 months Report 6.6, 1.4, 9.11
Plain English for the jargon
HRA: Housing Revenue Account, the ringfenced account that funds council housing
LCP MW24-H: London Construction Programme Housing Major Works framework used to appoint the principal contractor
Section 20: Consultation process under the Landlord and Tenant Act 1985 used when landlords recharge qualifying works to leaseholders
Qualifying Works: Works that can be recharged to leaseholders, such as windows, doors and roofing renewals
LGR: Local Government Reorganisation, including the creation of new unitary authorities
MHCLG: Ministry of Housing, Communities and Local Government, which has issued non-statutory guidance on cladding cost recovery
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10
Resolved
The Executive Resolved That ( i ) approval be granted to commence procurement of a contractor to deliver the Lakeview Estate Refurbishment Scheme; (ii) procurement will be undertaken through the London Construction Programme Housing Major Works framework (LCP MW24-H Framework (Lot 2.3)) by way of a mini-competition; (iii) the Head of Housing Assets, in consultation with the Strategic Director – Communities, be authorised to progress the procurement and return to Executive for approval of the contract award; and (iv) leaseholders will not be recharged for the element of the proposed works which consists of cladding/external wall system replacement, but will be recharged for other Qualifying Works. Reason: To fulfil the Council’s statutory responsibilities for resident safety and building compliance and ensure the buildings remain habitable through replacement of temporary fire safety measures with permanent solutions, and to address end-of-life components such as roofs, windows, and doors alongside external wall systems.
Word for word from the decision Woking published for this meeting.Source: moderngov.woking.gov.uk
1.1This report seeks approval to commence procurement for a principal contractor to deliver the Lakeview Estate Refurbishment Scheme. The scheme covers essential refurbishment and remediation works to 14 residential blocks, following removal of combustible cladding.
1.2It is recommended to undertake the procurement through the London Construction Programme Housing Major Works framework (LCP MW24-H Framework (Lot 2.3)) by way of a mini-competition as this approach offers best value, compliance, reduced programme time, and performance monitoring.
1.3The works are critical to ensuring the continued safety, compliance, and habitability of the buildings, and to prevent further deterioration of key building elements.
1.4The works associated with this procurement and the resulting project have been included in the forecast of the Housing Revenue Account (HRA) 30 Year Business Plan and Housing Asset Management forecast budgets for future years. It is anticipated that the works will straddle three consecutive financial years.
1.5The works include “Qualifying Works” that will be recharged to Leaseholders within the associated blocks. It is proposed that costs relating to the cladding/external wall system replacement are not recharged to leaseholders. However, all other Qualifying Works (i.e. replacement windows and doors, roofing renewal works, etc) will be recharged in accordance with the leases and legislation/guidance.
EXE25-105 Lakeview Estate Refurbishment Scheme
Purpose of report
2.1The purpose of this report is to secure Executive approval to initiate the procurement process to appoint a suitably experienced contractor for the Lakeview Estate Refurbishment Scheme in line with the new contract Standing Orders (CSOs). The procurement will enable the Council to progress essential building safety and fabric upgrades that address statutory landlord duties, safeguard residents, and secure long-term sustainability of the estate.
Recommendations
3.1The Executive is requested to:
Resolve that
(i) Approval be granted to commence procurement of a contractor to deliver the Lakeview Estate Refurbishment Scheme;
(ii) Procurement will be undertaken through the London Construction Programme Housing Major Works framework (LCP MW24-H Framework (Lot 2.3)) by way of a mini- competition;
(iii) The Head of Housing Assets, in consultation with the Strategic Director – Communities, be authorised to progress the procurement and return to Executive for approval of the contract award; and
(iv) Leaseholders will not be recharged for the element of the proposed works which consists of cladding/external wall system replacement, but will be recharged for other Qualifying Works.
Reason(s) for Decision
3.2To fulfil the Council’s statutory responsibilities for resident safety and building compliance and ensure the buildings remain habitable through replacement of temporary fire safety measures with permanent solutions.
3.3To address end-of-life components such as roofs, windows, and doors alongside external wall systems.
4.0Proposal and Outcome
4.1It is proposed that the Council will appoint a single principal contractor via the LCP MW24-H Lot 2.3 framework mini-competition to complete the Lakeview refurbishment scheme. Lakeview Estate Refurbishment Scheme
4.2The intended outcome is:
i. Delivery of a phased, block-by-block programme from Spring 2026.
ii. Replacement of temporary external cladding/insulation measures with long- term compliant solutions.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Housing Operational Policies EXE26-051The Executive Resolved That (i) the Asbestos Policy be approved; (ii) the Lift Policy be approved; and (iii) the Stra...
Enforcement Agent Procurement EXE26-112The Executive Resolved That ( i ) the commencement of a procurement exercise for the provision of Enforcement Agent s...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.