Internal Audit 2012/2013 Annual Report Including The Audit Opinion And Commentary

Noted Finance 1 paper

Audit and Governance Committee noted this item on Monday 10 June 2013. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

That the Committee note the results of Internal Audit’s work during 2012/2013 and the audit opinion.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Audit and Governance Committee, 15 pages

Purpose of report

1.1To provide:

• the overall results in terms of meeting Internal Audit's (IA's) objectives as set out in the internal audit plan for 2012/ 2013; and • an audit opinion and commentary (Appendix 4).

2. Summary of the Prime Features

2.12012/2013 Key Internal Audit Inputs

A summary of the position is provided at Appendix 1.

2.22012/2013 Key Internal Audit planned Outputs

During 2012/13 Internal Audit were required to:-

- complete a minimum of 12 full systems audits:

of which 5 must suitably assist the External Auditor reach their “opinion”.

- provide sufficient audit resources for other operational areas which assist the Council maintaining / improving its control systems and risk management processes or implementing / reinforcing its oversight of such systems, i.e.:-

provide an on-going consultancy to managers on internal control, for example where system changes are being made;

carry out investigations into any suspected instances of fraud;

service the Accounts Panel and, on internal audit and value for money matters, the Audit Committee and any other Committee requiring input from Internal Audit.

- meet Internal Audit’s external work requirements;

- achieve a benchmark delivery target for 2012/2013 of 90% of operational days over the year as a whole.

Background

3.1The Council is required under Regulation 6 of the Accounts and Audit Regulations 2011 to “undertake an adequate and effective internal audit of its accounting records and of its system of internal control in accordance with the proper practices in relation to internal control”. 4. Policy, Legal, Financial, Equalities and Risk Management Implications

4.1The Internal Audit (IA) plan was approved by the Audit Committee on the 6th March 2012. This report summarises the work of the Worcestershire Internal Audit Shared Service (WIASS) throughout 2012/13. WIASS has delivered the audit programme in conformance with the UK Public Sector Internal Audit Standards as published by the Institute of Internal Auditors.

4.22012/2013 Internal Audit Actual Outputs

2012/13 was a demanding year for the Internal Audit team with the loss of a Lead Auditor early in the year, the departure of an Auditor in November 2012 who had not been in post long, the uncertainty over the permanent appointment of the Service Manager post and a couple of office moves. There was a need to vacancy manage posts for a significant proportion of the year in order to ensure correct resourcing was available to deliver the risk based internal audit plan. In addition there was ‘managed’ long term sickness as well as significant unforeseen long term sickness absence within the Service which placed further pressure on the service and its ability to deliver the internal audit programme. Internal Audit has carefully managed its resource and worked with partners to deliver the full audit programme not only for Worcester City Council for 2012/13 but for all clients.

As can be seen in Appendix 1 the annual budget for systems work was 435 audit days. In considering these figures the Committee should note that, as previously reported, systems work included days used to complete three 2011/2012 audits. This work was required to complete audit work commenced prior to the conclusion of the 2011/2012 year but was not completed. Also included in this figure were several ‘call off’ budgets which by their nature may not be used in full.

Appendix 2 sets out audit report ‘follow up’ summary results that have been compiled during the 2012/2013 financial year. Any exceptions arising from audit ‘follow up’ are reported to Audit Committee. During the 2012/2013 financial year there were no exceptions reported to Audit Committee.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal Audit 2012/2013 Annual Report Including The Audit Opinion And CommentaryReport 15 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Worcester

Search all
  1. Internal Audit 2012/2013 Annual Report Including The Audit Opinion And CommentaryThis decision
  2. Annual Report of Internal Audit for 2025/26Agreed
  3. Internal Audit Progress ReportAgreed
  4. Internal Audit Plan for 2026/27Approved
  5. Internal Audit Strategy, Charter and MandateApproved
  6. Internal Audit Progress ReportAgreed

More from Worcester Audit and Governance Committee

All decisions
MeetingDecisionOutcome
16 Jun 2026 MinutesThat the of the meeting held on 17 th March 2026 be approved as a correct record and signed by the Chair. Approved Open
16 Jun 2026 External Audit Plan 2025/26That the Committee agree to note the External Audit Plan for 2025/26. Agreed Open
16 Jun 2026 Item Involving The Disclosure of Exempt InformationThat under Section 100A(4) of the Local Government Act 1972, the press and public be excluded from the meeting for th... Decided Open
16 Jun 2026 Corporate Risk Management Report - Quarter 4, 2025-26That the Committee agree to note the updated assessment of corporate risks at the end of Quarter 4 as shown in the la... Agreed Open
16 Jun 2026 Treasury Management Annual Report 2025/26That the Committee: 1. agree to note the 2025/26 Annual Report; 2. agree to refer the Annual Report to full Council f... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies