Item7

Resolved

That the Cabinet:- 1. agrees to transfer the operation and management of Nunnery Wood Sports Complex and St John’s Sports Centre to a Leisure Trust operator for an interim management period of two years with an option to extend for up to one further year; 2. agrees to delegate to the Corporate Director, Service Delivery and the Section 151 Officer authority to agree any necessary agreements and financial arrangements with Wychavon Leisure Trust operator; 3. recommends Council to agree to the TUPE transfer of the Nunnery Wood and St John’s Sport Centre employees to Wychavon Leisure Trust; and 4. recommends Council to delegate to the Corporate Director - Service Delivery and the Section 151 Officer authority to conclude any necessary agreements and financial arrangements for the transfer of the employees to Wychavon Leisure Trust.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Cabinet, 12 pages

Background

2.1Cabinet agreed on the 11th December 2012 a number of savings required from across the Council as part of the MTFS budget for 2013-18. For the Safer & Stronger Communities Service this amounted to a total of £138,000. Of this figure £103,000 in 2013-14 and a further £25,000 in 2014-15 were identified to be delivered from the two in-house managed Sports Centres; Nunnery Wood and St Johns Sports Centres. 2.2 A service review was undertaken by the Business Development Manager and Finance to identify options and proposals that could achieve the savings required. Whilst at the same time seeking to minimise the impact on the standard and quality of service delivered, access to services and ensuring the Council maintains its obligations under the Joint-Use Agreements. 2.3 The Sports Centres income levels peaked in 2009-10.However, in an ever increasingly competitive market place and compounded by a decrease in consumer leisure spend due to the recession, the option to increase income targets is not viable. This continued decline in income will put the Council’s financial position at risk. Therefore, the only option is to review potential efficiencies, assess the delivery model options and look at mitigating reductions in service.

Actuals 2008-09 2009-10 2010-11 2011-12 2012-13 Income Income Income Income Income NWSC 374,402 351,940 332,633 329,598 301,102 SJSC 440,267 617,900 611,305 592,193 591,470 Total 814,669 969,840 943,938 921,791 892,572 2.4 The Sports Centres have a proud reputation for delivering excellent services. This has been identified through high user satisfaction [annual sports centre customer surveys], and externally recognised and accredited by industry quality assurance standards. The Sports Centres were awarded with the ‘Excellent’ standard by Quest; the Sport and Leisure Industry quality assurance and benchmarking award.

2.5As part of the budget planning process consideration has been given to when and how customers use and access the Sports Centres, occupancy, usage and income profiling. The conclusion reached is that in order to deliver the savings required, significant changes in service delivery and quality are required unless a more radical solution involving some form of outsourcing is considered. These changes could include;

• Closure of the Sports Centres to the public at certain times of the day / week, • Ceasing the delivery of certain activities, • Reducing staffing levels; this will have a dramatic effect on the ability to be competitive, drive new business and may reduce the quality of service offered. Additionally it could result in the Council incurring redundancy costs.

3. Agreed Savings Solution – Interim Management Arrangement

3.1In order provide the greatest protection to the service as possible one of the options considered is the viability of transferring the centres to a Leisure Trust.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Sports Centres Interim Management: Key DecisionDecisions 12 pages DownloadRead as text

More from Worcester Cabinet

All decisions
MeetingDecisionOutcome
21 Mar 2017 MinutesThat the minutes of the meeting held on 14 th February 2017 be approved as a correct record and signed by the Chairman. Approved Open
21 Mar 2017 The Shambles Public Realm Improvement - Key DecisionThat the Cabinet agree to approve expenditure of £400,000 from the 2015-16 New Homes Bonus Allocation for public real... Agreed Open
21 Mar 2017 Worcester City Masterplan UpdateThat the Cabinet agree to: 1. approve the allocation £75k from the “City Plan Fund” towards the production of an upda... Agreed Open
21 Mar 2017 Perdiswell Golf CourseThat the Cabinet agree to: 1. endorse the proposals in this report, in particular the maintenance of ‘pay and play’ p... Agreed Open
21 Mar 2017 Refurbishment of the Cinderella Sports Ground - Key DecisionThat the Cabinet agree to: 1. approve the project to refurbish the Cinderella Sports Ground as a Community sports fac... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies