That the Cabinet: 1. agree the new swimming pool complex be procured as a ‘Develop and Construct’ Contract and that prior to seeking tenders the design is taken to RIBA Stage D; 2. agree the Restricted OJEU Procurement route is utilised to procure the contractor; and 3. note the Sansome Walk site will be marketed to coincide with the tendering of the new swimming pool to ensure a more precise value of the capital receipt is known at the time of the contract evaluation.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
2.1The Council at its meeting on the 26 March 2013 agreed
i. the site at Perdiswell for the new swimming pool complex.
ii. Option 1 as its preferred option with Option 2 being the minimum specification for the new swimming pool complex.
iii. the indicative Business Plan and the significant assumptions contained with in it particularly that the model excludes in-house operations.
iv. that the operation of the new facility will be via an external operator based on a non-business lease with a peppercorn rent which includes the option to tax.
v. the capital allocation for construction and fees of £10.5 million
vi. to progress to tender and evaluation stage for the construction and allocate a budget of £300,000 for the tender process.
2.2The Cabinet at its meeting on 12 March 2013 agreed that officers investigate and secure further value for the project through sponsorship, partnership, grants and other potential site uses.
2.3Chapter 11 of the Worcester Swimming Pool Feasibility Study report states that the choice of an appropriate procurement route is crucial to the success of any project and that the new swimming pool has some unique requirements such that a range of viable procurement options need to be appraised.
2.4The report states that each of the commonly adopted procurement routes have differing characteristics in respect of: • Client control of design; • Cost certainty; • Risk; • Ability to accommodate change; • Time; • Quality control.
2.5The report further states:
i. The design needs to be of a suitable quality, finished with good quality materials that are robust in nature and well-constructed.
ii. The centre consists of swimming pool areas that are notoriously complicated to build and as such recommend that the risks inherent in constructing the pools, along with other risks, are transferred away from the Council.
2.6Deloitte Real Estate (DRE) recommends that the proposed / selected procurement route should provide the Council with:
• robust and functional design solutions, proven to be durable; • a transfer of project and more specifically design risks to the contractor; • minimal risk of project / programme over run; • minimal risk of project / programme overspend; • a tender price early on in the project to inform decisions on affordability; • minimal snagging that ensures the facilities can be used from day one after handover; and • reduced lifecycle costs.
2.7There are effectively two choices, available to the Council related to how it procures the construction contract, Design and Build or Develop and Construct, both of which will be carried out utilising a National EU approved framework or via the appropriate EU procurement route.
2.8In accordance with the recommendations of this report a procurement exercise has been undertaken in relation to the appointment of the Lead Consultant and Design Team which is presented later on the agenda for Cabinet’s approval.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Worcester City Masterplan UpdateThat the Cabinet agree to: 1. approve the allocation £75k from the “City Plan Fund” towards the production of an upda...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.