Resolved
That the Sub-Committee consider the Council’s Quarter 3 performance for 2017/18.
Place and Economic Development Committee decided this item on Monday 29 January 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Sub-Committee consider the Council’s Quarter 3 performance for 2017/18.
Appendix 1
Place & Economic Development Sub -Committee Performance Report
Projects & Actions
Action Status
Cancelled
Overdue; Neglected
Unassigned; Check Progress
Not Started; In Progress; Assigned
Completed
Worcester 6 Technology Park Agents continuing to market the site to potential occupiers. Responsible Philippa Easements granted and payment actioned. Project on track. Officer Smith Due Date 31-Mar-2018 Current Status Expected Outcome
Delivery of business incubation units - The Kiln, Copenhagen St. There is a delay with this project due to delays with signing Responsible Philippa off the funding agreement and staff capacity. It is Officer Smith anticipated this project will be completed late August 2018. Due Date 31-Mar-2018 Project showing amber as original target date for completion Current Status was end March 2018. This will be reset for next reporting Expected period. Outcome
Delivery of Skills Strategy – key actions: apprentices and graduates Employment & Skills strategy review is now underway (draft Responsible Philippa will be taken to PED January meeting); a new strategy 2018 Officer Smith – 2021 and a 2018/2019 delivery plan will then be taken Due Date 01-Mar-2019 to/approved by PED at the March meeting Current Status Expected Outcome
2 Implementation of public realm improvements (The Shambles) Project is on track for successful completion but date for Responsible Philippa works yet to be confirmed. Project showing amber for Officer Smith outcome as original target for completion was March 2018. Due Date 31-Mar-2018 Progress amber as draft design was delayed from original Current Status target date in October 2017. This has now been produced Expected for consultation with local businesses in January 2018. Outcome
Project timelines will be reset for Q4.
Cathedral Square Improvements Public realm works completed bar snagging which will Responsible Philippa continue until all issues are addressed. Wilko opens on 1st Officer Smith November to complete the retail scheme. Most of the new Due Date 30-Sep-2017 bars and restaurants are open and appear to be trading well. Current Status Expected Outcome
Commandery improvements Project completed on time and on budget with opening on Responsible Philippa the 29th July 2017. Officer Smith Due Date 29-Jul-2017 Current Status Expected Outcome
St Martin's Gate Car Park solar panel feasibility study Feasibility report taken to the cross party energy group in Responsible Ian Forrester June showing 2 options for smaller capacity 30kWp and Officer 50kWp for the budget of £80,000. Due Date 31-Jul-2017 This project is now complete and will be closed. Current Status Expected Outcome
Car Park Management Consultants Systra presented an overview of their initial Responsible Alice Davey recommendations to the Task & Finish group at the meeting Officer held on the 19th December. Technology workshops will be Due Date 31-Mar-2020 held at the Guildhall on the 16th January and the 7th February, with a site visit to also take place by the end of Current Status February. Expected Outcome
3 Key Performance Indicators
PI Status
Alert
Warning
OK
Unknown
Data Only
Car Park Occupancy (peak time 12.00 -14.00, Mon - Sat only) Current Value 67% Current Target RAG
Aim to Maximise
Major planning applications determined in 13 weeks Current Value 50% Current Target 90% RAG
Aim to Maximise
3 out of 6 major applications were not completed within timescale due to on going s106 negotiations.
4 Minor planning applications determined within 8 weeks Current Value 40% Current Target 90% RAG
Aim to Maximise
Performance has fallen below target following departure of key staff and difficulties in recruiting to vacant posts. Recruitment is on going and relevant appointments are expected to be made during January 2018.
Other planning applications determined within 8 weeks Current Value 52% Current Target 90% RAG
Aim to Maximise
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
08 PED Commitee Q3 DRAFT 0.3 CAPReport | 7 pages | DownloadRead as text |
PDF |
Quarter 3 Performance Report for 2017/18Report | 1 pages | Download |
Follow Place and Economic Development Committee at Worcester and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Mar 2026 | MinutesThat the minutes of the meeting held on 26 th January 2026 be approved as a correct record and signed by the Chair. | Approved | Open |
| 16 Mar 2026 | Review of the Shrub Hill Quarter Supplementary Planning DocumentThat the Committee: 1. approves the draft Shrub Hill Quarter Supplementary Planning Document, as set out in appendix ... | Approved | Open |
| 16 Mar 2026 | Review of the Air Quality Supplementary Planning DocumentThat the Committee: 1. approves the draft Air Quality Supplementary Planning Document, as set out in appendix 1, for ... | Approved | Open |
| 16 Mar 2026 | Review of the Affordable Housing Supplementary Planning DocumentThat the Committee: 1. approves the draft Affordable Housing Supplementary Planning Document, as set out in appendix ... | Approved | Open |
| 16 Mar 2026 | Review of A Guide to Shopfronts and Signage Supplementary Planning DocumentThat the Committee: 1. approves the draft Shopfronts Guide Supplementary Planning Document, as set out in appendix 1,... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.