Place and Economic Development Committee, Monday 29 January 2018 at 7.00pm

The Kiln Co-working Innovation Space, 2 Copenhagen Street - Progress Update

Noted Committee 1 paper

Place and Economic Development Committee noted this item on Monday 29 January 2018. Below is the council's own wording, with the papers it was decided on.

Item34

Resolved

That the Sub-Committee: 1. Note the update on The Kiln Co-working Innovations Space Project 2. Agree to allocate £40,000 from the City Plan Fund to install an air conditioning system. 3. Agree ‘in principle’ to the proposal to set up The Kiln as a Community Interest Company (CIC) limited by guarantee; to be a member of The Kiln CIC; and to have a nominated Worcester City Council member as a non-executive director on the Kiln CIC Board
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Place and Economic Development Committee, 7 pages

Recommendation

1.1The Place and Economic Development Sub-Committee note the update on The Kiln Co-working Innovation Space project.

1.2The Place and Economic Development Sub-Committee agree to allocate £40,000 from the City Plan Fund to install an air conditioning system.

1.3The Place and Economic Development Sub-Committee agree ‘in principle’ to the proposal to set up The Kiln as a Community Interest Company (CIC) limited by guarantee; to be a member of The Kiln CIC; and to have a nominated Worcester City Council member as a non-executive director on The Kiln CIC board.

Background

2.1Update on The Kiln Co-working Innovation Space project: (i) A Project Delivery Team has been set up to co-ordinate the strategic development and programme of works to set up The Kiln Co-working Innovation Space and to ensure a legal entity is established for future management. The first priorities of this Team are to prepare a project plan; prepare a business plan; and progress with setting up The Kiln CIC. (ii) A press release was issued about the project in November: http://www.worcesternews.co.uk/news/15683155.Former_Copenhagen_Street_polic e_station_to_become_new_business_hub/ (iii) Worcestershire County Council (as the Accountable body for Worcestershire LEP) has issued the draft funding agreement. Officers are assessing this agreement and negotiating amendments with Worcestershire County Council. (iv) The tender for the Project Manager to manage the refurbishment works will be issued in January 2018. (v) The project milestones are being reviewed to reflect the slippage in the start of the project. The target opening date will be summer 2018.

2.2Air Conditioning The Place and Economic Development sub-committee requested a report on the installation of an air conditioning system. There is an air conditioning system in the building but this is not suitable.

The Kiln Co-working Space Progress Update January 2018/ Author: Janet Yates Version 04 1 A new system would provide heating and cooling for 11 offices with wall mounted units in each room. The outdoor unit would be located to the rear of the building, where the existing external units are. The system would assist with heat management in the building and provide an ambient working environment.

The recommended system is the Mitsubishi heat recovery VRF system, which has a typical lifetime of 5 years. The benefits of this system are that it can offer simultaneous heating and cooling in each room with individual control as required. It is also very energy efficient, giving approximately 300% of the energy going in e.g. 1 kW of electricity provides 3kW of heating or cooling.

The system will cost £40,000, which includes installation. Running costs will be dependent on building losses, ambient temperatures & use. The estimated running cost from the manufacturer is £2,134 per annum. The system would require a minimum of 1 service visit per year, costing approximately £500.

2.3Proposal to set up The Kiln as a Community Interest Company limited by guarantee

A Community Interest Company (CIC) limited by guarantee is owned by its members (referred to as ‘guarantors’); managed by a board of directors; does not have any share capital; and is governed by company law. An essential feature is the statutory asset lock which is designed to make sure that the assets of the CIC are used exclusively for the benefit of the community. Any assets and profits reinvested in the business must be retained within the CIC and used solely for community benefit.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
The Kiln Co-working Innovation Space, 2 Copenhagen Street: Progress UpdateReport 7 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Worcester

Search all
  1. The Kiln Co-working Innovation Space, 2 Copenhagen Street - Progress UpdateThis decision
  2. The Kiln Co-Working Innovation Space Project: Progress UpdateNoted
  3. Loan to Kiln Co-Working Community Interest CompanyNoted
  4. The Kiln Co-Working Innovation Space, 2 Copenhagen Street - Progress Update October 2019Noted
  5. The Kiln Co-Working Innovation Space, 2 Copenhagen Street - Progress Update June 2019Noted
  6. The Kiln Co-Working Innovation Space, 2 Copenhagen Street - Progress Update 2019Decided

More from Worcester Place and Economic Development Committee

All decisions
MeetingDecisionOutcome
16 Mar 2026 MinutesThat the minutes of the meeting held on 26 th January 2026 be approved as a correct record and signed by the Chair. Approved Open
16 Mar 2026 Review of the Shrub Hill Quarter Supplementary Planning DocumentThat the Committee: 1. approves the draft Shrub Hill Quarter Supplementary Planning Document, as set out in appendix ... Approved Open
16 Mar 2026 Review of the Air Quality Supplementary Planning DocumentThat the Committee: 1. approves the draft Air Quality Supplementary Planning Document, as set out in appendix 1, for ... Approved Open
16 Mar 2026 Review of the Affordable Housing Supplementary Planning DocumentThat the Committee: 1. approves the draft Affordable Housing Supplementary Planning Document, as set out in appendix ... Approved Open
16 Mar 2026 Review of A Guide to Shopfronts and Signage Supplementary Planning DocumentThat the Committee: 1. approves the draft Shopfronts Guide Supplementary Planning Document, as set out in appendix 1,... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies