Parsonage Way - Update

Agreed Committee 1 paper

Policy and Resources Committee agreed this item on Monday 30 July 2018. Below is the council's own wording, with the papers it was decided on.

Item20

Resolved

That the Committee: 1. agree to note the findings in this report in respect of the feasibility work undertaken at Parsonage Way; and 2. agree to endorse the conclusions in this report that no further work should be undertaken to establish whether Parsonage Way is a suitable location for Worcester City Football Club.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Policy and Resources Committee, 5 pages

Recommendation

1.1That the Committee notes the findings in this report in respect of the feasibility work undertaken at Parsonage Way; and

1.2That the Committee endorses the conclusions in this report that no further work should be undertaken to establish whether Parsonage Way is a suitable location for WCFC.

Background

2.1At its meeting on 19 September 2017, the Policy and Resources Committee endorsed the principle to secure a long term home for Worcester City Football Club (“WCFC”) at Parsonage Way and to allocate up to £100,000 to undertake feasibility work to establish whether Parsonage Way could be developed as a community sports facility.

2.2Authority was also delegated to the Corporate Director – Finance and Resources to continue commercial negotiations with Worcestershire FA and WCFC.

2.3This report provides an update on the work that has been undertaken since the decision of the Policy and Resources Committee on 19 September 2017, in particular with reference to the following matters:

 Public consultation and engagement  Feasibility studies  Heads of terms for a lease with Worcestershire FA and WCFC  Property matters  Business plan proposal from WCFC

2.4In light of these matters, this report outlines options for the Committee to consider

3. Public consultation and engagement

3.1The report to P&R Committee on 19 September 2017 identified the need for early public consultation on any proposals for the development of Parsonage Way. WCFC carried out two separate public consultation events in November 2017.

3.2It should also be noted that there has been significant interest in the proposals from Warndon Parish Council, including the attendance of the Chairman of the Parish Council at the Council’s P&R Committee. 3.3 Public consultation has demonstrated that there is a mixture of views about whether Parsonage Way is a suitable site for WCFC.

4. Update on feasibility studies

4.1To establish whether the site at Parsonage Way is suitable for development as a facility for WCFC together with community sports facilities, a significant amount of detailed feasibility work has been carried out.

4.2The report to P&R Committee on 19 September 2017 explained that the Club would require a basic level of facilities in terms of a new pitch, hard standing for a small stand, a changing block, floodlights and the supply of utilities to a new site. In order to establish the viability of the site for this use, design work was commissioned from Zebra Architects. This design work was then used to inform a number of studies: topographical/geotechnical, highways and ecological.

4.3Topographical/geotechnical studies were carried out by STRI. Their findings show that the land is stable and suitable for sustaining development. There are no identified contaminants. In short, no topographical/geotechnical concerns have been identified. However, technical detailed design work would need to be carried out to level the site which would require significant amount of earthworks before the laying of an irrigation and the establishment of a natural pitch. An indicative cost for this work would be in excess of £200,000.

4.4A highways study was carried out by Systra. The study scoped out the capacity of the highway network and junctions, including sensitivity testing of 850 spectators, 1,500, 3,000, 4,500 and 4,500 plus full capacity at Rugby Club (12,500) total 17,000. Their findings show that with the rugby club and football club at full spectator capacity there would be capacity issues on the surrounding network. This would be an extremely unlikely occurrence and in any event, mitigating measures could be implemented, i.e. football club and rugby club playing at the same time.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Parsonage Way: UpdateReport 5 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Worcester

Search all
  1. Parsonage Way - UpdateThis decision
  2. Application 21/ 00995/ADV - Roundabout at Parsonage WayDecided
  3. Request for Authority to Confirm Public Footpath Diversion Order at Parsonage Way re: WN564Agreed
  4. Footpath Diversion - Land east of Parsonage Way/Trotshill WayDecided
  5. Proposed Diversion of Footpath (564(C) - Land East of Parsonage Way and Trotshill WayDecided
  6. Proposal Relating to Land at Parsonage WayAgreed

More from Worcester Policy and Resources Committee

All decisions
MeetingDecisionOutcome
30 Jun 2026 MinutesThat the minutes of the meeting held on 19 th May 2026 be approved as a correct record and signed by the Chair. Approved Open
30 Jun 2026 Quarter 4 and Annual Key Performance Indicator Report for 2025/26That the Committee agree to note the Council’s quarter 4 and annual performance for the Key Performance Indicators in... Agreed Open
30 Jun 2026 Provisional 2025/26 Outturn - Financial Monitoring ReportThat the Committee agree to note the following: 1. the Provisional 2025-26 Revenue outturn as detailed in section 2 o... Agreed Open
30 Jun 2026 Medium Term Financial Plan 2027/28 - 2031/32That the Committee agree: 1. to note the update; and 2. the MTFP and budget timetable as set out in paragraph 3.2 of ... Agreed Open
30 Jun 2026 Town Investment Plan UpdateThat the Committee agree to note the contents of this report. Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies