Worcester City Council
Policy and Resources Committee, Monday 30 July 2018 at 7.00pm

Quarter 1 Performance Report for 2018/19

Noted Committee 2 papers

Policy and Resources Committee noted this item on Monday 30 July 2018. Below is the council's own wording, with the papers it was decided on.

Item23

Resolved

That the Committee note the Council’s Quarter 1 performance for 2018/19.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Policy and Resources Committee, 9 pages

Appendix 1

Policy & Resources Committee Performance Report

City Plan

Action Status

Cancelled

Overdue; Neglected

Unassigned; Check Progress

Not Started; In Progress; Assigned

Completed

Review of community grants and process Three Members have joined a Task and Finish Group to Sponsor Alice Davey support this review. Additional Members are being sought. Due Date 31-Mar-2019 Terms of reference have been drafted, for circulation prior Original Due 31-Mar-2018 to the first meeting during Summer 2018. Date Current Status The project is on track for completion though slightly behind at present due to the delay in the provision of nominees for Expected the Task and Finish Group, and associated delay therefore in Outcome the first meeting.

Development of Worcester City Masterplan Draft document has been received and is currently being Sponsor Philippa considered by officers with the engagement of Members. Smith Due Date 31-Dec-2018 A detailed report was taken to June 2018 PED Committee. Original Due 31-Dec-2017 Public consultation is to take place during September 2018. Date Current Status The project is amber because consultation took longer than originally planned due to an increased involvement of Expected stakeholders. On track for completion by the end of Outcome December 2018.

2 Feasibility study for new pedestrian footbridge at Kepax Park to Gheluvelt Park This project is now completed as the initial feasibility report Sponsor Philippa has been received and is being considered by officers. Smith Due Date 30-Jun-2018 Report to be presented to July 2018 P&R Committee identifying the next stages of the process. Original Due 31-Dec-2017 Date Current Status Expected Outcome

Sansome Walk future development options Tenders for the demolition contractor have been received Sponsor Philippa and are currently being assessed. It is expected that a Smith contractor will be appointed and programme of demolition Due Date 31-Aug-2019 will progress on schedule. Original Due 31-Mar-2019 Date Current Status Expected Outcome

Local Transport Plan 4 - Worcester Actions Actions to be developed following the adoption of the City Sponsor Philippa Centre Master Plan Smith Due Date 31-Mar-2019 Original Due 31-Mar-2019 Date Current Status Expected Outcome

3 Excellent Council

Stakeholder Management – mapping & plan Communications team has taken on this project and Sponsor David Sutton reviewed project scope. Due Date 31-Mar-2019 Next steps are for the priority stakeholders to be agreed Original Due 31-Mar-2018 and an engagement framework to be developed. Date Current Status Wider Management Team members will be engaged in the process through a workshop in September 2018. Expected Outcome Project currently amber due to delays caused by changes of personnel, but expected to return to green for next period.

Workforce Development Strategy The People Strategy is now scheduled for publication on Sponsor Mark 30th July. Edwards Due Date 31-Mar-2018 Project is red as the overall due date has been missed as milestones for this have slipped due to extensive Original Due 31-Mar-2018 consultation and engagement with managers, trade unions Date and staff Excellence Champions. Current Status

Milestones will be amended for next reporting period Expected including agreeing a delivery plan. Outcome

Improved Contract and Shared Service Plan Project amber as milestone to review shared service and Sponsor David Sutton major contracts plan has been missed. This will be Due Date 30-Sep-2018 considered at Excellence Board in Q2. Original Due 30-Sep-2018 Date Current Status Expected Outcome

ICT Strategy and fit for purpose arrangements Project is Amber as milestone to consider action plan at ICT Sponsor David Sutton Management Board meeting was delayed due to board Due Date 30-Sep-2018 member availability. This has now been completed but has delayed procurement of resource to support delivery of Original Due 30-Sep-2018 action plan. Date Current Status Expected Outcome

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
PR Q1 Report v4Report 9 pages DownloadRead as text
PDF
Quarter 1 Performance Report for 2018/19Report 2 pages Download

At this meeting

Whole meeting

On this subject at Worcester

Search all
  1. Quarter 1 Performance Report for 2018/19This decision
  2. Quarter 4 and Annual Key Performance Indicator Report for 2025/26Agreed
  3. Quarter 4 and Annual Performance Report for 2025/26Noted
  4. Quarter 4 and Annual Performance Report for 2025/26Agreed
  5. Quarters 2 and 3 Performance Report 2025-26Decided
  6. Quarter 3 Performance Report For 2025/26Agreed

More from Worcester Policy and Resources Committee

All decisions
MeetingDecisionOutcome
30 Jun 2026 MinutesThat the minutes of the meeting held on 19 th May 2026 be approved as a correct record and signed by the Chair. Approved Open
30 Jun 2026 Quarter 4 and Annual Key Performance Indicator Report for 2025/26That the Committee agree to note the Council’s quarter 4 and annual performance for the Key Performance Indicators in... Agreed Open
30 Jun 2026 Provisional 2025/26 Outturn - Financial Monitoring ReportThat the Committee agree to note the following: 1. the Provisional 2025-26 Revenue outturn as detailed in section 2 o... Agreed Open
30 Jun 2026 Medium Term Financial Plan 2027/28 - 2031/32That the Committee agree: 1. to note the update; and 2. the MTFP and budget timetable as set out in paragraph 3.2 of ... Agreed Open
30 Jun 2026 Town Investment Plan UpdateThat the Committee agree to note the contents of this report. Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies