Resolved
That the Sub-Committee notes the update on the Kiln Co-Working Innovation Space Project.
Place and Economic Development Committee decided this item on Monday 28 January 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Sub-Committee notes the update on the Kiln Co-Working Innovation Space Project.
1.1The Place and Economic Development Sub-Committee note the update on The Kiln Co-working Innovation Space Project.
2.1The Council has previously agreed that 2 Copenhagen Street should be used as supported co-working innovation space for the creative sector in a partnership project with the Kiln Co-working Community Interest Company (CIC). The Council has agreed to provide £100,000 funding for the project and Worcestershire LEP is providing £195,000 for the Kiln’s internal fit out of the property.
2.2The Policy and Resources Committee agreed a rent free period of two and half years followed by a further period of two years at 50% rent reduction.
2.3The Place and Economic Development Sub-Committee have agreed ‘in principle’ to be a member of The CIC and to have a nominated Worcester City Council member as a non-executive director on The Kiln CIC board.
2.4Detailed surveys and inspections identified a number of structural problems with the building which would need to be addressed before the Kiln fit out. In October 2018 the Policy and Resources Committee approved £300,000 for the structural repairs work.
2.5It was agreed that the Kiln CIC can have temporary use of vacant ground floor space at the Guildhall North Wing until the refurbished accommodation is available.
3. Information
3.1Premises Refurbishment
Preliminary works to inject the damp proof course; repair windows; and other minor building works are in progress and due to be completed in January 2019. The tender pack for the main building works programme was published in November. The date for tender returns was 20 December 2018.The target date for award of contract is w/c 21st January and works due to start on site 18th February 2019. Procurement of items, which are not part of the main building works tender e.g. furniture, kitchen units, IT is in progress. These items are within the Kiln Fit Out budget.
The target date for completion of works is end of July 2019.
3.2Project Management
The project management structure has been reviewed to reflect the increased scope of works. The new structure is as follows: Premises/Design Team – responsible for overseeing the building refurbishment and fit out works. Business Plan Team – responsible for developing the Kiln Business Plan and operational services, financial plan and funding. Kiln Project Delivery Team – review updates from the premises/design and business plan teams, risks and issues.
Project milestones have been updated to reflect slippage. See Appendix 1.
3.3Funding and finance
The Worcestershire LEP Funding agreement has been signed. WLEP have agreed that some of the building refurbishment work costs can be claimed from their grant funding. They have also agreed an extension to 15th March 2019 for the final claim.
Raise Partnership and officers from the Council Economic Development and Finance teams have re-profiled the budget and will be monitoring and managing expenditure to comply with the March deadline.
3.4Kiln Temporary Space
Kiln 0.5 opened in the Guildhall North Wing in late November. The space can accommodate 13 users, at any one time, and has been fitted out with office furniture, signage and other decorative props to reflect the Kiln branding. These items will be transferred to 2 Copenhagen Street when the building is ready for occupation.
The temporary space has generated plenty of interest. The Kiln CIC has received bookings from 6 businesses, for both fixed and hot desk use, and expressions of interest from a further 6. The types of users include graphic design, coding, clothing design and animation businesses. The space is booked on an open ended basis.
During the next few months, The Kiln CIC will use the space to raise awareness of the Kiln fit out in no. 2 Copenhagen Street and to pilot operational procedures.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
PED Jan 2019 Appendix 1: The KilnAppendix | 1 pages | Download |
PDF |
The Kiln Co-Working Innovation Space, 2 Copenhagen Street: Progress Update 2019Report | 2 pages | DownloadRead as text |
Follow Place and Economic Development Committee at Worcester and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Mar 2026 | MinutesThat the minutes of the meeting held on 26 th January 2026 be approved as a correct record and signed by the Chair. | Approved | Open |
| 16 Mar 2026 | Review of the Shrub Hill Quarter Supplementary Planning DocumentThat the Committee: 1. approves the draft Shrub Hill Quarter Supplementary Planning Document, as set out in appendix ... | Approved | Open |
| 16 Mar 2026 | Review of the Air Quality Supplementary Planning DocumentThat the Committee: 1. approves the draft Air Quality Supplementary Planning Document, as set out in appendix 1, for ... | Approved | Open |
| 16 Mar 2026 | Review of the Affordable Housing Supplementary Planning DocumentThat the Committee: 1. approves the draft Affordable Housing Supplementary Planning Document, as set out in appendix ... | Approved | Open |
| 16 Mar 2026 | Review of A Guide to Shopfronts and Signage Supplementary Planning DocumentThat the Committee: 1. approves the draft Shopfronts Guide Supplementary Planning Document, as set out in appendix 1,... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.